Академический Документы
Профессиональный Документы
Культура Документы
5. In Nodal Operation:
A. There will be no Zones of any type
B. There will still be Congestion Zones
C. There will be Generation Zones
D. There will be Load Zones
1
FERC and NERC Updates
1. The Federal Energy Regulatory Commission (FERC) monitors and investigates
__________ markets.
A. Energy
B. Nodal
C. Risk-Based
D. ERCOT
E. None of the Above
2. The North American Electric Reliability Corporation (NERC) has been designated
as FERC’s Electric Reliability Organization (ERO).
A. True
B. False
6. Since ______, the North American Electric Reliability Corporation (NERC) has
been committed to ensuring the reliability of the bulk power system in North
America.
A. 1970
B. 2007
C. 1968
D. 2009
2
Compliance Update
1. What is the protocol for directives stated in NERC Reliability Standard COM-002-2,
Req. 2?
A. The directive must be clearly stated and logged within 5 minutes by the issuer
B. The directive must be clearly stated by the issuer and logged by the receiving entity that
day
C. The issuer must clearly, concisely, and definitively state the directive, ensure it is
repeated back by the recipient, and acknowledge the correct response
D. All directives must have an assigned NERC identifier for future tracking
B. Review of open mitigation plans to correct previous violations or those closed within the
last year
C. Possible issues with other NERC Standards that come up during the audit
A. Status updates are publicly posted on the NERC website before the
investigation is complete
B. Entities under investigation will be asked to hold pertinent data for a CVI
3
Nodal Program Overview – Project Update and Readiness Scorecard
1. In 2010, ERCOT has scheduled system-wide Load Frequency Control (LFC) closed
loop tests to occur in:
3. ERCOT will offer each training course from its Nodal Curriculum of Courses at least
once every six to eight weeks until November 2010.
A. True
B. False
4. One feature a Market Participant can obtain only through the secure section of the
Readiness Scorecard is to:
A. Contact the Nodal Executive Sponsor
B. Sort and filter each Market Participant’s readiness status
C. View a summary of that Market Participant’s status for all of its metrics
D. Add a calendar reminder
4
ERCOT Network Modeling
1. According to Nodal Protocols, “Transmission Elements” include:
A. Transmission equipment only
B. Resource or generation equipment only
C. Transmission and generation equipment
D. Transmission equipment below 60 KV
3. In Nodal, the Network Model Management System (NMMS) will provide the capability
for…
A. Consistent modeling information
B. Transparency of modeling information
C. A single point of entry for all modeling information
D. All of the above
4. Nodal Protocols require that all model changes pertaining to the Network Operations
Model follow the ________ process.
A. Model Change Submission
B. Network Change Submission
C. Network Operations Model Change Request (NOMCR)
D. Resource Asset Registration Form
5. Which model acts as the “source” model or provides the “base model layer” for all
other models?
A. Planning Model
B. CRR Network Model
C. Network Operations Model
D. SCADA Network Model
6. True or False: Nodal Protocols require the continuous telemetry of voltages, flows
and loads.
A. True
B. False
5
ERCOT Network Modeling (continued)
9. What is the furthest date into the future that NOMCRs can be submitted for Network
Operations Models?
A. Up to 6 months in advance
B. Up to 3 months in advance
C. Up to 90 days in advance
D. Up to 1 year in advance
6
OTS Commitment Dispatch – Reliability in Day-Ahead Adjustment
Period & Real-Time Operations – Module I:
1. Which of the following is true of Resource Commitment in the Texas Nodal
Market?
A. QSEs may commit Resources in response to Day-Ahead Market or Trade
activities.
B. QSEs may commit Resources simply to produce revenue in Real-Time.
C. ERCOT may commit Resources through the Reliability Unit Commitment
process.
D. All of the above
E. A & B
2. Where does the Reliability Unit Commitment find the expected status for
Resources?
A. The Three-Part Supply Offer
B. The Current Operating Plan
C. The Network Operations Model
D. Resource Telemetry
4. Which of the following is not an input to the Reliability Unit Commitment process?
A. Load Forecast
B. Three-Part Supply Offer
C. Output Schedule
D. Current Operating Plan
5. What is the study period of the Day-Ahead Reliability Unit Commitment process?
A. Every hour of the current Operating Day
B. Every hour of the next Operating Day
C. All remaining hours of the current Operating Day
D. Every hour for the next seven days
7
OTS Commitment Dispatch – Reliability in Day-Ahead Adjustment
Period & Real-Time Operations – Module II:
5. Which of the following best describes how Responsive Reserve and Non-Spin
Reserve Ancillary Services are deployed in the Texas Nodal Market?
A. LFC provides the desired output level for Resources providing these services
B. The reserved capacity is deployed by LFC or Operator Instruction and
SCED determines the desired output level.
C. These Ancillary Services are deployed only by Verbal Dispatch Instruction
D. These Ancillary Services are deployed only when SCED fails to solve.
8
Outage Scheduler – Module I:
1. The “Actual Start” entry field appears on the Detailed Outage or Summary screen
will not accept entries until ____ hours prior to the Planned Start time.
A. 1
B. 2
C. 3
D. 4
4. Actual Start and Actual End Dates & Times may be entered on the Detailed Outage
Screen and/or the Summary Page.
A. True
B. False
5. Supporting Information is not required for which of the following Outage types?
A. Forced Outages
B. Unavoidable Extensions
C. Planned Outages
D. Forced Extensions
9
Outage Scheduler – Module II:
6. For TSP Planned outages submitted more than 90 days in advance, ERCOT will
approve or reject the request no later than ______ days prior to the proposed Start
Date/Time.
A. 2
B. 4
C. 30
D. 75
7. To indicate that the a Resource will be off-line in an outage request, the HSL and
LSL fields must be set to:
A. The Normal HSL and LSL values
B. The Emergency Limit values
C. One (1) and One (1)
D. Zero (0) and Zero (0)
9. If a Resource Derating is going to last more than _____ hours, the QSE must enter
a Planned, Maintenance or Forced Outage request as appropriate, based on the
proposed Start Date and Time.
A. 2
B. 24
C. 48
D. 168
10. A Level 1 Maintenance Outages denotes equipment that must be removed from
service within __________ to prevent a possible Forced Outage.
A. 1 hour
B. 24 hours
C. 7 days
D. 30 days
11. Forced Outage requests are automatically accepted by the ERCOT Outage
Scheduler upon submittal.
A. True
B. False
10
Outage Scheduler – Module III:
12. Which of the following statements about a Simple Transmission Outage is true?
A. Only involves one Transmission Element
B. May have a duration between 3 and 24 hours
C. Must not cause a topology change or change in the Locational Marginal
Price
D. There’s no such thing as a Simple Transmission Outage
15. The Outage Evaluation process runs a sequence of power flow and contingency
studies to determine if submitted outages pose the threat of an insecure operating
state.
A. True
B. False
11
Wind Generation in the ERCOT Nodal Market – Modules I & II:
1. In 2009, Wind Generation made up what percentage of ERCOT’s installed
capacity?
A. 1%
B. 6%
C. 11%
D. 19%
[Questions for Wind Generation: Module III & IV Continued on Next Page]
12
Wind Generation in the ERCOT Nodal Market – Modules III & IV:
7. Which statement about a WGR’s Resource Limit is true?
A. COP HSL must be greater than the WGRPP
B. COP HSL must be less than or equal to the WGRPP
C. COP LSL must be equal to the Minimum Wind Forecast
D. HSL is not required for a WGR
8. Market Rules for WGR’s Resource Limits require the COP to be updated within
______.
A. 3 days of commercial operation of Wind Farm
B. Four hours of receiving updated forecast
C. One hour of receiving updated forecast
D. One SCED dispatch cycle
9. To calculate Capacity Shortfall Charges for RUC, what does ERCOT use to
determine the available capacity from a WGR?
A. COP HSL value at the time of the applicable RUC
B. COP HSL value at the end of the Adjustment period
C. The Real-Time telemetered HSL
D. The higher of “a” and “b”
10. During Real-Time operations, where does SCED get operational data from WGRs
such as status and limits?
A. Telemetry
B. Current Operating Plan
C. MIS certified area
D. Both “a” and “b”
12. Which statement is true regarding allowances for deviation above Base Point for
WGRs and Conventional Resources?
A. WGRs have a wider tolerance than Conventional Resources
B. WGRs have a smaller tolerance than Conventional Resources
C. WGRs have a the same tolerance as Conventional Resources
D. Deviations from Base Points are not allowed
13
SPS
1. Any entity in ERCOT can install and operate a Special Protection System (SPS)?
A. True
B. False
2. When a Transmission Operator (TO) removes an SPS from service, the TO shall
immediately?
A. Call their QSE
B. Notify the Texas RE
C. Notify ERCOT Operators
D. All of the above
5. Who is responsible for monitoring the status of SPS components to ensure the
SPS will operate when needed?
A. NERC Registered Balancing Authorities and Load Serving Entities
B. NERC Transmission Operator and Transmission Owners
C. NERC Regional Reliability Organization
D. Texas Regional Entity (Texas RE)
14
SPS (continued)
8. Owner of SPSs upon installation shall
A. Submit an approval request via a NOMCR
B. Submit a description of the SPS
C. Submit an exit strategy
D. All of the above
9. A Type 2 SPS
A. Must produce an audible alarm
B. Reduces (ramps back) generation
C. Has only local area of impact
D. Involves under-voltage load shedding (ULVS)
15
Emergency Operations
1. What is the purpose of keeping accurate records?
A. Major System events will be recreated with information found in the
operator’s logs.
B. The operator needs to be able to tell a good story.
C. The logs give us information on what happened.
D. It is a requirement.
E. The Operator will need accurate records to “major on the majors and minor on
the minors.”
2. During the event that you heard what was the cause of the Hot Point unit trip?
A. The throttle valves didn’t close all the way and the turbine accelerated to over
6000 RPM.
B. The Generator Step-up transformer tripped and exploded.
C. The generation step-up transformer caught on fire and tripped.
D. There was a hydraulic problem that caused the unit to trip.
E. The turbine lube oil pumps never shut down and caused a fire.
3. What entities might be reading the operator’s logs after a major event?
A. Everyone associated with the event.
B. Only ERCOT will be reading the Operator’s logs.
C. Depending on the size and conditions, it could be NERC, FERC, TRE,
ERCOT, PUCT.
D. Only the Shift Supervisor
E. Only Texas Regional Entity will be investigating the event.
5. When did the hydrogen explosion occur at the Hot Point unit?
A. Before the generator came apart due to over speed
B. After the generator came apart due to over speed
C. After the transformer ruptured from the falling block wall
D. After the turbine lube oil pumps began fueling the fire with lube oil.
E. After the step up transformer exploded
16
Emergency Operations (continued)
7. What are two of the five points associated with active listening?
A. Pay attention, be quiet.
B. Show that you are listening by using verbal indicators; Interject opinions when
there is a break in the conversation.
C. Defer judgment; Don’t respond until the end of the conversation
D. Provide feedback; Defer judgment;
E. Talk to the person to help them remain calm; Get off the phone quickly so that
you can log the conversation.
17
Generator Voltage Regulators
1. What elements are required for a generator to work?
B. Magnetic field
2. The Exciter is the “Back bone” of the generator control system. It is the power source
that supplies ____ current to the voltage regulator which adjusts the magnetizing current
to the field windings of a synchronous generator thereby inducing _____ voltage and
current in the generator.
A. AC/DC
B. DC/AC
3. The voltage regulator and excitation system gives the operator control over?
A. True
B. False
18
Load Shed Requirements
1. Automatic Under-Frequency Load Shed is initiated by __________.
A. Operator Action
B. Substation Relay Action
C. Generator Relay Action
D. Transient Instability
A. Operator Action
B. Substation Relay Action
C. Generator Relay Action
D. Transient Instability
4. If the system frequency fell and Block One circuits tripped, system operators
should take what action after conferring with ERCOT operators?
A. No action since relays arrested frequency decline.
B. Unilaterally shed Block 4 circuits to restore frequency to 60 HZ.
C. Trip Block 4 circuits while restoring an equal amount of Block One circuits.
D. Initiate transformer voltage reduction.
5. If the system frequency fell to 58.9, how much total firm system load would be
shed by UFLS?
A. 5%
B. 10%
C. 15%
D. 25%
6. A system operator needs to get approval from whom before shedding firm system
load in an emergency where system collapse is imminent?
A. Supervisor
B. Manager
C. Vice President
D. No One
19
Load Shed Requirements (continued)
20