EXECUTIVE SUMMARY

57 McIvor Hwy, Bendigo


Victoria 3352
Ph: (03) 1234 5678
June 2, 2011 Fax: (03) 8765 4321

ATTN: !Department of Health

RE: Expression of Interest (EOI) – The New Bendigo Hospital Project

Medi-Build is a Special Purpose Vehicle (SPV) assembled specifically for the delivery of the new
Bendigo Hospital, through a Public-Private Partnership (PPP) delivery method. The members that make
up the consortium have been handpicked based on their experience, capability, availability, and
suitability to collectively produce a world-class regional health service.

Upon selection to tender for, and subsequently deliver the New Bendigo Hospital, Medi-Build is excited
to offer Regional Victoria with a state of the art hospital that is Australia’s first patient centred health
service.

We trust that this expression of interest has met the requirements of that outlined in the EOI message /
brief.

Should you have any questions relating to this expression of interest, please do not hesitate to contact
the undersigned.

Regards,

Daniel J Collins
Daniel Collins
Director
Medi-Build Bendigo Pty Ltd
NEW BENDIGO HOSPITAL
EXPRESSION OF INTEREST

CONSORTIUM DETAILS PAGE 1


RESPONDENT DETAILS

Medi-Build Consortium
Register Name ! ! ! Medi-Build Bendigo Pty Ltd
- Lend Lease Infrastructure Investments
Trading Name! ! ! Medi-Build - Macquarie Capital Group

Address!! ! ! 57 McIvor Hwy - Spotless


! ! ! ! BENDIGO
- Baulderstone
! ! ! !
- Hansen Yuncken
Overview of Operations !! Medi-Build is the vehicle which brings together
and Structure ! ! ! the collective international skills and local Medi-Build’s consortium members represent a complementary blend of proven
! ! ! ! experience of Lend Lease Infrastructure sponsorship, design and delivery excellence, relevant international experience
! ! ! ! Investments and Macquarie Capital Group. The matched by a local expertise in healthcare operations, within a single integrated team.
! ! ! ! corporate structure of Medi-Build is in the
! ! ! ! process of being developed.

Proposed Role and Function! Medi-Build will be the interface with the State
! ! ! ! and will deliver the construction and operational
! ! ! ! requirements, financing arrangements and
! ! ! ! taxation structure that will achieve the highest
! ! ! ! value-for-money solution to the State for the
! ! ! ! new Bendigo Hospital project.

CONSORTIUM DETAILS PAGE 2


Register Name ! ! ! Lend Lease Infrastructure Investments Limited

Trading Name! ! ! Lend Lease Infrastructure Investments

Address!! ! ! Level 2 The Gauge, 825 Bourke Street


! ! ! ! VICTORIA HARBOUR! ! ! !

Overview of Operations and" Lend Lease Infrastructure Investments Limited are the wholly owned infrastructure investment division of the Lend Lease Corporation. Lend
Structure " " " " Lease is one of the world’s leading fully integrated property solutions providers, with strong development, investment management, project and "
" " " " " construction management and asset and property management capabilities. Founded in Sydney in 1958 by Dutch immigrant and innovator Dick
" " " " " Dusseldorp, the group was born out of a vision to create a company that could successfully combine four disciplines; property, financing, " "
" " " " " development and investment. With over 5,000 competed projects across 30 countries, more than 10,000 employees and a strong network of "
" " " " " subcontractors and alliances, they have a proven track record of executing critical and complex projects for their partners. Lend Lease’s " "
" " " " " capabilities span the entire property value chain, from the origination of opportunities through to delivery of great outcomes. Lend Lease is listed "
" " " " " on both the Australian and New Zealand Stock Exchanges. They are also one of the world’s few investment-grade-rated community developers, "
" " " " " with a rating of BBB– from Standard & Poor’s and Baa3 from Moody’s.

" " " " " Lend Lease takes a long-term view operating with strong corporate governance, transparency and accountability. Sustainability has become an "
" " " " " integral part of their culture, as they believe every action adds up. Through design and investment in new technologies, they are committed to "
" " " " " delivering the next generation of sustainable property and infrastructure solutions. Lend Lease are committed to being Incident & Injury Free "
" " " " " wherever they have a presence. This philosophy reaches every part of our operations and extends to employees, partners, clients, suppliers and "
" " " " " subcontractors. #
! ! !

! ! ! ! ! ! !

Proposed Role and Function! As sponsor and equity provider to Medi-Build, Lend Lease Infrastructure Investments maintains a role in the bid leadership across areas of
! ! ! ! development and financing

CONSORTIUM DETAILS PAGE 3


Register Name ! ! ! Macquarie Capital Group Limited

Trading Name! ! ! Macquarie Capital Group

Address!! ! ! Level 2, 101 Collins Street


! ! ! ! MELBOURNE! ! ! !

Overview of Operations and" Macquarie Capital Group Limited forms part of the Macquarie Capital business which is wholly owned by Macquarie Group Limited, a leading
Structure " " " provider of full-service corporate advisory, financial markets and retail services in Australia. Macquarie Group Limited is one of Australia’s largest
" " " " companies, ranking in the top 15 by market capitalisation on the Australian Stock Exchange.

" " " " Macquarie Capital comprises the Macquarie Group’s Wholesale structuring, underwriting, corporate advisory, specialist funds (including
" " " " infrastructure and "real estate funds) and private equity capabilities in:

- Mergers and acquisitions, takeovers and corporate restructuring advice!!

- Equity capital markets and equity and debt capital management and raising

- Specialised funds management including infrastructure, real estate and private equity funds

- Debt structuring and distribution

- Private equity placement! !

" " " " An active participant in the Australian PPP market, Macquarie Capital has recent involvement in large PPP infrastructure projects within
" " " " Australia, including the Victorian Desalination Plant (Vic) and Airport Link (Qld). Macquarie is currently has closed twelve health sector PPPs / PFI
" " " " including Royal Women’s Hospital (Vic) and Peterborough Hospital (UK)." "

Proposed Role and Function! As sponsor, financial advisor, debt and equity arranger for Medi-Build, Macquarie will be focused on delivering the most competitive financing
! ! ! ! and commercial package to the State, in addition to its role in the integrated bid leadership.

CONSORTIUM DETAILS PAGE 4


Register Name ! ! ! Spotless Group Limited

Trading Name! ! ! Spotless

Address!! ! ! Level 2, 101 Collins Street


! ! ! ! MELBOURNE! ! ! !

Overview of Operations and" Spotless works with over 40 hospitals and health organisations throughout Australia and New Zealand. They#deliver more than 30 specialised
Structure " " " managed services to the health sector including clinical, non-clinical, supply management and distribution services.# Recognised as one of the
" " " " largest healthcare support specialists, their systems not only meet but exceed the requirements of the Australian Council on Health Standards
" " " " Accreditation Guidelines.

! ! ! ! Customers can relieve critical and other care staff from non-patient tasks with a full transfer of risk. We offer a range of health support services !
! ! ! ! from food services and linen through to waste removal, asset and facilities management and security. Their integrated approach to service !
! ! ! ! delivery also ensures the highest levels of compliance with Australian and New Zealand Healthcare Standards.

" " " " Spotless’ integrated service program transforms service culture, focussing on client satisfaction and outcomes. Through integrating separate "
" " " " service departments into a single customer centered solution, they can deliver measurable improvements in value and high quality services.
! ! ! ! Customers enjoy the benefits of transparent contracts with high levels of accountability and guaranteed outcomes in terms of cost, service and !
! ! ! ! quality. This enables their customers more time to concentrate on achieving the best possible clinical care whilst we concentrate on reducing !
! ! ! ! operating costs and providing exceptional patient care support.

" " " " Spotless provide global benchmarking of services and standards, allowing best practices and principles to be applied. Our technical experts "
" " " " work in partnership with our customers to help identify cost synergies and efficiency opportunities. Other features include specialised software "
" " " " programs such as the Buckeye food management system – road tested quality assurance programs and proprietary systems and procedures, "
" " " " and key performance indicators built into the program to measure and quantify performance.
! ! ! !

Proposed Role and Function! Spotless will be the Hard and Soft Facilities Manager, responsible for the maintenance lifecycle and the soft services offering an
! ! ! ! integrated solution through a single point contact help desk.

CONSORTIUM DETAILS PAGE 5


Register Name ! ! ! Baulderstone Victoria

Trading Name! ! ! Baulderstone

Address!! ! ! Level 9, South Wharf Tower


! ! ! ! 30 Convention Centre Place
! ! ! ! SOUTH WHARF! ! ! !

Overview of Operations and" Baulderstone have been "Creating what matters" in Australian building and infrastructure for their clients and the community, for over 80 years.
Structure" " " Born of the union between two trusted names in Australian construction, MR Hornibrook, and AW Baulderstone, they have a rich heritage and
" " " " strong relationships. Today, Baulderstone are part of the Lend Lease Infrastructure Group and one of the largest Building and Engineering
" " " " companies in Australia, with over 1400 people across the country. They remain the tried and trusted name in Australian construction. Their
" " " " buildings include icons of local and worldwide significance including the UNESCO heritage-listed Sydney Opera House, Sydney's Anzac Bridge,
" " " " Brisbane's Story Bridge, Melbourne's Etihad Stadium and#Adelaide's Convention Centre. Baulderstone’s mission is always to provide
" " " " sustainable#solutions that deliver more innovation, more value, more talent, more leadership, more teamwork and more of what you expect and
" " " " deserve from your construction partner.

" " " " The company culture is built on the mindset that Baulderstone is more than a construction company - they are a service business. Simply "
" " " " stated, how Baulderstone interact and serve their clients is equally as important as the project they deliver. That’s why they have an internal "
" " " " culture that values teamwork, encourages leadership, and strives to deliver an overall experience superior to those offered by their competitors. "
" " " " It’s why Baulderstone’s clients come back to them year after year, and it’s why their project portfolio across Australia is second to none.

! ! ! !

Proposed Role and Function! Baulderstone will coordinate the D&C JV to create of a world class design, evaluate build ability and the cost of the construction, determine an
! ! ! ! innovative construction methodology, establish a timely construction programme and manage the delivery of the project.

CONSORTIUM DETAILS PAGE 6


Register Name ! ! ! Hansen Yuncken Pty Ltd

Trading Name! ! ! Hansen Yuncken

Address!! ! ! 609 Olive Street


! ! ! ! ALBURY/WODONGA ! ! !

Overview of Operations and! As one of the leading construction companies in Australia, Hansen Yuncken is at the forefront of change and innovation in the building industry.
Structure ! ! ! The company is known for its pioneering role in both the application of new technologies and the development of new construction techniques
! ! ! ! and project delivery methods. Founded in Melbourne in 1918 by Otto Yuncken and Lauritz Hansen, Hansen Yuncken has grown steadily in
! ! ! ! stature as a respected builder of major construction projects. They consistently seek to provide value and innovation across all aspects of a
! ! ! ! project. Hansen Yuncken offers a wide range of services in order that their clients will achieve the best outcomes for their project delivery and
! ! ! ! facility operation. "Building Value" is an intrinsic part of the culture at Hansen Yuncken.

! ! ! ! Hansen Yuncken's philosophy is one of fair dealing, high quality client service and building value. They are committed to developing and
! ! ! ! maintaining long-term relationships by focusing on achieving their client's project objectives. These relationships are the foundation of the
! ! ! ! company's longevity and success, earning Hansen Yuncken a proud reputation as a diligent, responsive and innovative contracting
! ! ! ! organisation.

! ! ! ! Hansen Yuncken has strong history and presence in central Victoria since they first opened an office in Shepperton in 1925. In that time they
! ! ! ! have gained unrivaled experience and relationships while producing extensive public and private projects in Victorian regional cities such as
! ! ! ! Bendigo, Shepparton, Ballarat, Albury/Wodonga, Beechworth and Echuca. They continue to maintain their strong presence and reputation in
! ! ! ! regional Victoria today through their established Albury/Wodonga branch office. Their local knowledge from local employees and subcontractors
! ! ! ! gives them an unmatched advantage for delivering outstanding outcomes for their clients in regional Victoria.

Proposed Role and Function! Hansen Yuncken is a member of the D&C JV with Baulderstone. As part of the integrated D&C JV, they will provide established local experience
! ! ! ! and knowledge to assist coordinate the creation of a world class design, evaluate build ability and the cost of the construction, determine an
! ! ! ! innovative construction methodology, establish a timely construction programme and manage the delivery of the project.

CONSORTIUM DETAILS PAGE 7


DESIGN CONSULTANTS

Name! ! ! ! Bates Smart! !

Overview of Operations and! Bates Smart is a highly regarded Architectural practice that has consistently demonstrated an ability to deliver integrated projects of large scale.
Structure ! ! ! Bates Smart provides architectural, interior design, urban design and strategic services from design feasibility to final documentation and
! ! ! ! contract administration services. Bates Smart have previously shown that they are capable across a range of sectors, including health care,
! ! ! ! tertiary, research, commercial, residential, hospitality, and community projects.

With over 150 years of experience, many of the firm’s earliest projects remain operational due to the deep understanding of durability, flexibility "
" " " " and sustainability. Bates Smart has an impressive portfolio at an Australian and International level, with notable projects in Victoria including the "
" " " " current Royal Childrens Hospital, the Alfred Centre Stages 1 and 2, and Federation Square.

Proposed Role and Function! Bates Smart / Silver Thomas Hanley (acting in an integrated Joint Venture) will act as Lead Design Consultant, providing Master Planning and
! ! ! ! world class Architectural Design Consultancy Services, including design and Health Planning.

Name ! ! ! ! Silver Thomas Hanley! !

Overview of Operations and! Silver Thomas Hanley approach Health Care projects with a strong design and operational knowledge, in order to provide unique and
Structure ! ! ! operationally sustainable solutions. The architecture and design employed by STH seeks to provide solutions that enhance the experience for all
! ! ! ! users of their facilities.

Silver Thomas Hanley also boasts an impressive portfolio of large health care projects. Notable Victorian examples include Casey Hospital, "
" " " " Orange Hospital, Ballarat Hospital, Mercy Hospital for Women, and the Royal Children’s Hospital. Silver Thomas Hanley is one of the few "
" " " " specialist Health Architecture firms that operate within Australia.

Proposed Role and Function! Bates Smart / Silver Thomas Hanley (acting in an integrated Joint Venture) will act as Lead Design Consultant, providing Master Planning and
! ! ! ! world class Architectural Design Consultancy Services, including design and Health Planning.
CONSORTIUM DETAILS PAGE 8
DELIVERY OF PROJECT VISION, OBJECTIVES
AND UNDERSTANDING OF KEY ISSUES
UNDERSTANDING AND PROPOSED APPROACH

OUR UNDERSTANDING OF THE PROJECT VISION AND OUR APPROACH TO DELIVERING THE PROJECT VISION
OBJECTIVES AND OBJECTIVES

Medi-Build understands the importance of regional hospitals and the key role they Fundamental to delivering these objectives for the Bendigo Community is the key
play for the thousands of Victorians within these communities. The key objective for strategy of selecting ‘the right team’, bringing together world leading resources in
Medi-Build and the New Bendigo Hospital is to save lives and improve the health of finance, design, delivery and operations for the New Bendigo Hospital.
Victorian’s within the communities of Central Victoria. The aim for patients in the
region to be able to receive world class treatment without the need of travel to Medi-Build has carefully considered the selected proven organisations to achieve an
medical facilities in metropolitan areas is a key understanding of Medi-Build. It is also integrated team of world leading Australian companies. The consortium members are
important that the facility is able to educate and train the next generation of world all leaders in the world in their individual fields and have the experience and capability
class medical practitioners in the community, therefore the importance of education in health and social infrastructure when viewed collectively that is without comparison.
and research facilities in the New Bendigo Hospital. Medi-Build has the unique ability Medi-Build is able to present a complete and innovative solution for the New Bendigo
to deliver these objectives to Central Victoria while also delivering outstanding value Hospital that guarantees the delivery of outstanding design, quality and value for
for money to the Victorian State Government. money.

Medi-Build further enhanced their ability to delivery second to none innovation and
quality for the New Bendigo Hospital by embarking on a global study tour of the
Our Understanding newest and most advanced hospitals in the world. From the tour we were able to
discover
- Better treatment and outcomes for patients in Central Victoria
- Current trends in healthcare design to improve outcomes of patients
- The improved ability for collaboration between the Bendigo Hospital and
researchers, specialists and educators in Metropolitan Victoria - Design solutions for research and education within hospitals

- A world class facility in Bendigo that attracts medical practitioners from around the - New and emerging technologies
world
- IT health advances
- Outstanding value for money for Bendigo Health and the Victorian Department of
Health - Improvements for operational outcomes

DELIVERY OF PROJECT VISION, OBJECTIVES AND UNDERSTANDING OK KEY ISSUES PAGE 2


DELIVERY OF PROJECT VISION, OBJECTIVES AND UNDERSTANDING OK KEY ISSUES PAGE 3
PROJECT VISION
DESIGN VISION
A Working Environment
A Healing Environment
For the New Bendigo Hospital to be a leading international hospital and attract the
Medi-Build understands the importance of design and it’s impact on the hospital pro-
best medical staff it needs to provide a leading working environment. Medi-Build !
ject. We believe it is critical to make clinical spaces less sterile and through our previ-
understand this and believes that through our design capability this can be achieved
ous experience and outstanding design team we will be able to set a new benchmark
for the New Bendigo Hospital staff.
in hospital design within Australia. The aim to enhance the connection to the outside
world will be achieved by the use of warm colours, natural materials and a full glass
The building will be designed to maximise the operational efficiency of the facility and
facade. Access to nature is an important part of the healing process and the fully
provide a comfortable working environment for all staff. It will be designed with safety
glazed facade proving natural light and external views to patient rooms as well as a
in mind for staff, patients and all other building users.
roof terrace courtyard, internal greenery and extensive external landscaping will pro-
vide this environment.

A Community Environment
One of the clear messages gained from our recent international study tour, is the need
Medi-Build believes that the overall health precinct design should contribute to the
for the creation of an environment that is non-institutional, calming and personal,
local community and greater Bendigo. We want to provide a hospital to Bendigo that
particularly in potentially high stress zones. The layout of the hospital can have an
the whole region of Central Victoria can be proud off. This will be achieved by ! !
impact on these issues as significantly as the visual effects. The aim to provide easy
outstanding architectural design in the internal, external and overall master plan that
drop off and collection of patients, separation of back of house functions from front of
will be recognised through out Australia. Medi-Build will engage the Bendigo Art Soci-
house function and the use of communal and private spaces will enhance the patient
ety and the Bendigo Art Gallery to provide artistic consultation to bring a welcoming,
journey by creating a more comfortable environment for their patients and their family.
personal environment to the patient journey within the Bendigo Hospital through the
The Medi-Build design team will achieve these environmental outcomes by applying integration of urban artwork. Community involvement and considerations will be an
the design principles outlined below integral aspect when considering the planning and design of the hospital.

- Create healing spaces to enhance patient perception of well-being


The hospital also needs to provide functionality for local residents and stakeholders
which will be achieved by significant underground car parking and addressing other
- Designs that create reminders of everyday life
stakeholder issues presented in the feasibility stages of the hospital.
- Create a clear, warm and inviting environment

- Provide an open, flexible, supportive, rewarding and engaging place

- Enable art, music, colour and texture to be an integral part of the design

PROJECT VISION PAGE 2


THE FUTURE
‘Whole of Life’ Design Future Proof
Medi-Build will take into account for the lifetime costs of the New Bendigo !Hospital Medi-Build’s design will compliment both the specialist integrated design, and the
during our planning stage. This lifecycle assessment will include operational modelling, to allow for future expansion and continuing operation of a
world class facility. Design decisions will therefore be based on the consideration of
- Capital cost proposed future design changes, capital cost, maintenance costs, lifecycle cost, op-
portunity for innovation, and optimal performance solutions.
- Maintenance costs

- Lifecycle of the system elements When designing to ‘future-proof’ the facility, Medi-Build will consider the following
objectives
- Energy and water consumption

- Greenhouse gas emission - Generally, design structural and services elements in a way that they can be

- Loss of business continuity costs upgraded with minimal disruption to patients and staff

- Structural capacity to allow for future vertical expansion


We understand the importance of providing the highest value of money to the !
- Increased slab to slab heights and structural grids
Victorian Department of Health and the impact of having areas of the hospital !
unavailable due to maintenance and refurbishment to the people of Bendigo. - Installation routes for all large pieces of equipment
We aim to minimise these issues through our expertise and research during the !
- Fibre optics installation for future National Broadband Network (NBN) con-
design and specification of the hospital.
nection

- Minimise the use of load bearing walls (internally)

PROJECT VISION PAGE 3


SUSTAINABILITY
It is well known that buildings have a direct affect on occupants; in the ways in which
they feel (emotionally and mentally) and function. In the health care environment, it is
thought that a patient’s health and well being can be affected by the physical attrib-
utes of the hospital in which they are staying. Such factors include natural light, and
ventilation.

Medi-Builds vision of the new Bendigo hospital is that it will achieve a Green Building
Council of Australia (GBCA) rating of 5 stars, under the Healthcare Version 1 rating
tool.

The Healthcare V1 rating tool aims to achieve the following


- Minimise the environmental impact of healthcare buildings
- Maximise orientation to the north and opportunities for controlled sunlight
exposer for patients, staff and visitors
- Improve patient health outcomes and staff productivity
- Receive recognition for green leadership
- Achieve real cost savings

Subsequently, Medi-Build is aiming to realise these targets. Upon achieving these


items, the new Bendigo Hospital will be a facility that patients can comfortably recover
in, staff can happily work in, and the environment can adequately sustain.

Medi-Build will achieve an Ecologically Sustainable Development (ESD) through the


following methods;
- Displacement ventilation system with digital control for improved efficiency
- Increased natural light to every patient bed through a double glazed facade
with ‘Low-E’ film
- Energy efficient artificial lighting
- Wind and solar power generation
- Rainwater harvesting
- Office and back of house (BOH) natural ventilation

PROJECT VISION PAGE 4


Displacement Ventilation System Rainwater Harvesting
Upon being the successful tenderer, Medi-Build will implement a displacement ventila- Large storage tanks will utilise the surface area of the building’s roof and facade to
tion system into the new Bendigo Hospital. Research shows that 60-65% of all en- capture rainwater for the purpose of irrigating landscaped areas, and flushing toilets,
ergy consumption in hospitals is a direct result of HVAC systems. The displacement etc.
system will essentially extract the air from the lower levels and remove it through an
exhaust / stack method, in order to maintain the ideal temperature throughout the Any rainwater harvested will be used strictly for non potable purposes, and treated for
hospital, whilst removing all unnecessary HVAC clutter on each level. This is a much certain applications if necessary. Rainwater harvesting provides yet another opportu-
more efficient system than the tradition HVAC approach, and was used with much nity to reduce costs, whilst also minimising resource usage (fresh water / drinking
success in the Royal Women’s Hospital. water).
In addition, the Displacement System will be digitally controlled, which allows con-
sumption to be accurately measured and used for further research and adjustment Natural Ventilation
from a sustainability standpoint. The use of natural ventilation throughout the hospital will be a major objective of Medi-
Build. Natural Ventilation is pivotal in providing an ambience that suggests that the
Lighting, Daylight, and External Views hospital is truly integrated with the atmosphere of the outdoors. Administration areas
Medi-Builds objective in this area will be to provide as much daylight as possible to and back of house corridors will be heavily targeted in an effort to increase staff com-
each patient room, and provide energy efficient artificial lighting where possible (e.g. fort (while not neglecting patient comfort at the same time).
LED’s, etc).

External views will also play a major role, in providing the patient/s with a space that
makes them feel as though they are not locked within a hospital.

Wind and Solar Power Generation


Whilst space is the constraining factor in utilising wind and solar power generation,
Medi-Build are keen to implement this into the new Bendigo Hospital. This is achiev-
able through wind turbines, and solar panels, and in combination, will generate a por-
tion of the power used to operate the hospital (reducing running costs as a result).

PROJECT VISION PAGE 5


INTEGRATED FACILITY MANAGEMENT

Medi-Build has a long history in providing facilities management to large scale projects The hospital design will include two (2 no.) loading bays on either side of the dividing
of this nature, Spotless will form an integrated services provider, having a single desk / road, to ensure that food and linen is always deliverable, and receivable.
point of call for the following services
- Off site laundry Cleaning
- Off site kitchen Medi-Build will provide all hospital cleaning services to the appropriate hygiene stan-
- Cleaning dards, as we have delivered in health care facilities previously. We will also provide
- Security cleaning of retail premises and food and beverage establishments (within the
development).
Off Site Laundry & Kitchen
An offsite laundry and kitchen will be utilised in the delivery of the new Bendigo Hospi- Security
tal. Located within only a 9 minute drive of the hospital (via two alternative routes), in Medi-Build will provide security services through means of technological devices, and
the suburb of Eaglehawk, the facilities will be staffed by employees who have been manned security that monitors the New Bendigo Hospital.
sourced by Medi-Build in the City of Bendigo, and surrounding regions.

The kitchen facilities will be operational 24/7, and provide all of the staff and patient
meals to the hospital. Given the short travel time and available technology by way of
refrigerated/heated transport vehicles, etc. this method of food preparation and !
delivery can be achieved with great success, as it has been at various other Victorian
Hospitals.

The offsite laundry will operate in much the same manner, with Medi-Build providing a
service to make sterilised sheets and linen available to the hospital on demand. Linen
changes will occur on a frequent basis, as is the standard in hospitals throughout
Australia and the world.

PROJECT VISION PAGE 6


INNOVATIVE FACILITY MANAGEMENT

Jimmy Possum Furniture Information and Communication Technology (ICT)

Medi-Build has a preliminary agreement, and is in discussions (exclusively) with Jimmy Medi-Build will adopt the Victorian whole of Health information and communication
Possum to provide all non-medical furniture items to the new Bendigo Hospital. technology strategy; HealthSMART, in the development of the new Bendigo Hospital.
HealthSMART is a seven-year $360 million strategy to modernise and replace ICT
Jimmy Possum is a leading Australian furniture designer and manufacturer from "" systems throughout the Victorian Public Healthcare Sector. The ICT improvements
Bendigo. They are already a major employer in the Bendigo region and this opportu- provide healthcare agencies with the tools required to meet the growing healthcare
nity will allow them to further extend their Bendigo employment force, whilst also pro- demands expected in the future
viding the new Hospital facility with ‘a personal / community touch of Bendigo’.
In abiding by the Governments strategy to deliver ICT improvements and provide the
Jimmy Possum is not only renowned for leading furniture designs and quality prod- opportunity for advancing technology in the health sector, Medi-Build will work to pro-
ucts, but also sustainable design and manufacture methods; through the use of recy- vide effective ICT systems in the following areas;
cled timbers, etc. - Clinical Systems
- Patient and Client Management Systems
The furniture that Jimmy Possum will provide to the new Bendigo Hospital is purely - Resource Management Systems
non-medical, and would likely encompass mainly sofas, chairs, tables, etc. in admini- - Picture Archiving Communication Systems
stration areas, foyers, corridors, and the like. - 24/7 Help desk
- Disaster Recovery Capabilities

PROJECT VISION PAGE 7


PROJECT VISION PAGE 8
SENSITIVE CONSTRUCTION

Medi-Build has had extensive experience undertaking construction works in existing To limit the impact of greenhouse gases emitted for the construction of the new hos-
hospitals and has developed unrivaled procedures to allow minimal disruption to the pital as well as the embodied energy needed, Medi-Build will use Hanson ‘Green”
existing facility. We will limit noise, vibration and disruption by undertaking processes concrete for the structure of the building. This concrete requires a significantly smaller
such as amount or carbon to be used in the manufacturing process than traditional concrete
while still having the same characteristics of traditional concrete. Hanson have a
- Bored piles instead of driven piles quarry and batching plant on the southern side of Bendigo where all ‘Green” concrete
will be produced. This will limit the amount of transport required and improve the local
- Electric cranes instead of diesel
economy and employment in Bendigo.
- Programme loud works around critical hospital procedures
Medi-Build’s construction consortium members are accredited with ISO 1400:2004
- Ensure continues access for ambulances and emergency vehicles
“Environmental Management Systems” and will ensure a minimal effect on the local
- Ensure no dust leave the construction areas environment during the construction of the New Bendigo Hospital.

- Comprehensive traffic management plan

We are committed to working with stakeholders and will aim to limit the impact on the
local community during the construction process by ensuring

- Minimal disruption to the road network

- No loud works outside of 9am-3pm

The construction of the New Bendigo Hospital has the ability to have an enormous!
financial benefit for the local community. Medi-Build will employ local subcontractor,
employees and suppliers to ensure the regional economy received the maximin bene-
fits from this project.

PROJECT VISION PAGE 9


COMMERCIAL OPPORTUNITIES
Quest Apartments would
provide serviced
Accommodation apartments to non critical
patients as well as patient
family and friends
Fitness First would provide
a gym and other health
Health Centre facilities to hospital staff,
recovering patients and
local residents

Ramsay Health Care would


Private Hospital provide a private health
facility within the New
Medi-Build is currently negotiating multiple possible commercial opportunities for the
Bendigo Hospital
New Bendigo Hospital. These potential inclusions to the hospital will improve the serv-
ices the hospital is able to offer while decreasing the financial obligations of the state.
Wilson Parking would
Some possible commercial opportunities are as follows
manage the new
Car Parking underground car parking
for patients, staff and local
residents
BD Biosciences would
Bioscience operate a private
bioscience laboratory
within the hospital
Delaware North would
manage a range of
Retail and Food franchise, food and retail
outlets within the entry to
the hospital.

PROJECT VISION PAGE 10


CONTRACTUAL STRUCTURE
CONSORTIUM STRUCTURE
The Medi-Build integrated approach is a natural consequence of our consortium The Medi-Build consortium structures ensures
structure. The capability of each consortium member enables Medi-Build to provide to
the State the flexibility and certainty that Medi-Build can comprehensively deliver the - Value for money to the Department of Health
New Bendigo Hospital.
- Innovative ideas through Architectural Design

The Medi-Build SPV is the single point of accountability with the state and the Ben- - A world class hospital that will cater for the patients journey from the min-
digo Hospital’s Stakeholders, which ensures that clarity and ease of communication
ute they walk in the door to when they depart through a qualified Facilities
between all parties involved. The consortium is joined by the following agreements
Manager
- Project agreement
- Site occupancy agreement
The consortium structure of Medi-Build is represented in a diagram on the following
- Construction contract
page. This diagram indicates the structure and relationships between each consor-
- Building Direct agreement tium member to give the best possible value for money to the Victorian Department of
- Consultancy agreement Health.
- Finance Direct Agreement
- Service Provider Agreement

Medi-Build have strategically allocated the relevant roles within the consortium to help
deliver the best possible outcome using our experience as a backbone. Experience is
what will separate us from others as it demonstrates our credibility within the health
system field of projects.

This Consortium structure displays the direct agreements that consist between the
parties within the structure. These agreements will help navigate the most desirable
form of communications to help finish the project as timely as possible and will display
the risks that are involved undertaking those roles.

CONTRACTUAL STRUCTURE PAGE 2


FINANCIER DIRECT AGREEMENT
SERVICE PROVIDER
DEPARTMENT OF HEALTH DIRECT AGREEMENT
BUILDER DIRECT AGREEMENT

PROJECT SITE OCCUPANCY


AGREEMENT AGREEMENT

MEDI-BUILD

SHARE HOLDERS
AGREEMENT
SPONSOR
- MACQUAIRE CAPITAL SERVICE
- LEND LEASE INFRASTRUCTURE PROVIDER
INVESTMENTS AGREEMENT

CONSTRUCTION
CONTRACT

D & C : JV
- BAULDERSTONE F/M SPOTLESS
- HANSEN YUNCKEN

CONSULTANCY AGREEMENT

DESIGN TEAM : JV
- BATES SMART
- SILVER THOMAS HANLEY
FINANCE + SECURITY
DOCUMENTS INCLUDING
FINANCIER DIRECT AGREEMENT
+ STATE DEED CHANGE

FINANCIERS
- BENDIGO BANK
- ANZ CONTRACTUAL STRUCTURE PAGE 3
- NAB
- AUSTRALIAN SUPER
PROJECT RISK
Medi-Build have been involved in the delivery of many billions of dollars of both ! Gov- Medi-Build Consortium supports the Victorian Department of Health’s risk allocation
ernment and other privately funded projects and are extremely experienced in the risk guidelines as set out in the Expression of Interest. Medi-Builds Design, Construct and
associated with the New Bendigo Hospital. FM Teams are experienced in the delivery of PPP’s both in Victoria and Australia, and
have deep understanding of market "practice and financiers requirements.
Our experience and capability will allow us to
- Recognise, evaluate and allocate risk via back-to-back contractual structure The State can be assured that each entity accepting a certain project risks possesses
- Document risk allocation a balance sheet that is capable of sustaining the risks offered to it. Through Medi-
- Develop effective risk and mitigation strategies Build, the Victorian State Government can be certain that they have assigned each
- Accept and manage risk risk to the entity most able to handle that individual risk.

Medi-Build’s experienced in the delivery of PPP projects will complement the Victorian Stakeholders Risks
Department of Health’s requirements in respect to allocation of risk. Each consortium Medi-build will engage with the local stakeholders within Bendigo to seek a more
member is experienced and capable in handling the risks allocated with them for the community-based approach toward both the design and delivery of the hospital. We
successful completion of the New Bendigo Hospital project. aim to achieve a project design that incorporates the best interests of the people
around and within the area. Parties that we will interact with will include:
- Local councils, City of Greater Bendigo
Stage Process
- Employees of the existing hospitals
Identification Medi-Build shall workshop key issues internally, which shall
ensure that each possible risk scenario is identified. Medi- - Local businesses
Build shall rely on its previous experiences of relevant other
PPP projects. - Local residents
Allocation Allocate the identified risk to the team member best able to
control it and that also have the financial capacity to absorb
real risk.
Management and Moni- The best able member will apply an organisational structure
toring to ensure the effective review, monitoring and reporting of
the project through the term. Through such pro-active lead-
ership and communication, potential issues will possibly be
avoided before they may become a problem.

CONTRACTUAL STRUCTURE PAGE 4


Risk Principle and Approach State Medi Build

General Issues
Medi-Build will obtain and maintain appropriate insurance cover for a building. The State may specify the
Insurance
minimum insurance types and amounts *

Taxation Medi-Build will take all taxation risks with respect to its participation in the project *

Change in Law The State will bear both the time and cost risks associated with a change in law that is specific to the Project
*

Force Majeure Medi-Builds performance obligations will be suspended for the duration of a Force Majeure Event
*
Site

Site Conditions Medi-Build will accept overall responsibility for Site conditions
*

Cultural Heritage The State will assume responsibility for native title and provide relief in relation to discovery of artefacts
*
Planning and other approvals

Design Medi-Build is responsible for the design of the Bendigo Hospital


*

Medi-Build is responsible for the construction and commissioning of the Bendigo Hospital within the required
Construction and Commissioning time period to deliver the output specifications. Delay in completion will result in a reduced payment period and
*
potentially payment of liquidated damages.

No relief will be given to Medi-Build for delays that are an occurrence of which are within Medi-Build’s control.
Relief for Construction delays
Delays caused by the actions of the State, will result in relief being provided to Medi-Build * *

Payments will be made upon the delivery of the required services. Sub-standard performance will result in re-
Payment
duced payments *

Performance monitoring and review Medi-Build will be required to monitor its performance against the specifications and KPIs
*

Medi-Build must ensure that the Bendigo Hospital remains and all times fit for the intended purpose from the
Fit for the intended purpose
commissioning of the project to the expiry of the term *
FINANCE
FINANCIAL CAPABILITY

Medi-Build are able to deliver funding certainty to the State for the New Bendigo Hos- Medi-Build’s strong financial capability ensures that we are second to none in PPP
pital project through the following attributes financing. The key characteristics of our consortium for the New Bendigo Hospital are

! Experience and commitment of respondent members to enable accep- ! Structure of D&C joint venture provides joint and several parent company
tance of key risks and provision of security packages on market competi- guarantees
tive terms ! Provision of FM security packaging and parent guarantees
! Strong structuring and arranging capabilities combined with a strong bank ! Recognition of expectations of financiers in terms of provision of security in
group to provide funding certainty and an innovative capital markets team accordance with current market practice in large Australian PPPs
in the likely event that the bond markets are once again in the Australian ! Cornerstone equity commitment from related parties to the D&C joint ven-
PPP environment ture members to demonstrate the commitment of both Macquarie Capital
! Robust, committed equity strategy to ensure that all equity is available at and Lend Lease Infrastructure Investments
financial close from sponsors with PPP financing experience - Cornerstone equity investment with 100% of the equity required from both
! Competitive and collaborative approach to work closely with both the pro- the sponsors
viders of capital and the State to optimise the financing solution for the - Underwritten by Macquarie Capital and Lend Lease Infrastructure Invest-
project. ments

Our strong debt capabilities are accredited to

- Medi-Build Sponsors have demonstrated expertise and experience in


structuring and raising financing for large projects
- Very solid support from the four leading banks in Australia, ANZ, NAB,
Commonwealth Bank and Westpac to work with Medi-build on the New
Bendigo Hospital project
- Further support from Australian Super (exclusive) and Bendigo Bank

The five above banks and Australian Super have committed to Medi-Build and form
the core group to finance the project. KPMG have been employed exclusively by
Medi-Build to engage as its financial advisor, providing in-depth experience in com-
petitively financing PPPs.
FINANCE PAGE 2
CONSORTIUM SPONSORS
Medi-Build consist of quality partners who posses strong capabilities and corporate Lend Lease Infrastructure Investments
strength to successfully deliver the funding strategy and requirements for this PPP. Lend Lease have the capabilities, experience and innovations to meet the challenge
Both Macquarie and Lend Lease will be able to deliver unparalleled funding certainty to sponsor the New Bendigo Hospital with the Medi-Build consortium. They have a
and value for money to the State. strong presence on PPP projects in Australia, principally in the health sector and have
a strong track record in partnering with governments to successfully deliver such pro-
Macquarie Capital and Lend Lease Infrastructure Investments relevant PPP funding jects. Lend Lease have strong credentials as a sponsor and with their vast range of
experience is demonstrated by their involvement and investment in these recent pro- experience they are able to bring all the elements together to delivery enduring public
jects: assets and partnerships.
Macquarie Lend Lease
Awards
Victorian Desalination Plant Royal Children’s Hospital Melbourne
! MFSS Investment Stewardship Award for Funds Management - 2009
Eastlink (Victoria) Toolern development (Victoria)
The Royal Women’s Hospital Melbourne South Australian New Schools KPMG
The Medi-Build consortium has brought on KPMG as their financial advisers as they
Macquarie Capital are one of Australia’s, and the world’s leading advisers on private and public transac-
Macquarie Capital are global specialists in financing of PPP infrastructure projects and tions. KPMG have a large amount of knowledge and experience in PPPs, and with
have been at the forefront of this sector for over the last decade. They form part of the this they are able to advise Medi-Build on conceptualising, structuring, negotiating
Medi-Build consortium as major project sponsors as their team bring together a and executing PPPs. Having KPMG engaged as our financial advisor to this project
wealth of experience and specialist industry knowledge. also give us further advantage as they have a range of skilled and experienced pro-
fessional that can give in-depth advice on infrastructure and major projects as well as
Awards in the healthcare sector.
! Project finance deal of the year - 2010
! Asia-Pacific and Global PPP Deal of the Year by PFI and Infrastructure Jour- Awards
nal respectively ! 2011 World's Best Outsourcing Advisors - in recognition of our depth of
! In 2009, Macquarie was also ranked No.1 globally for total value of PFI/PPP experience, global reach and holistic approach.
transactions and No.1 for the total value of Australian project finance trans- ! 2010 World's Best Outsourcing Advisors - in recognition of our depth of
actions (Dealogic). experience, global reach and holistic approach.
! Top two overall in Consultancy Rankings 2009 by OpRisk & Compliance - in
recognition of our experience in risk management.
! Number One Real Estate Tax Advisory Firm, 2008 - in recognition of our
depth of local knowledge combined with our cross-border
FINANCE PAGE 3
FINANCING STRUCTURE
Medi-Build is currently gauging the market to develop a competitive financing struc- Debt funding approach and progress
ture for the new Bendigo Hospital project. Below outlines the current view in regards Medi-Build will utilise the resources and experience of the sponsors to deliver the
to the finance structure of the project. Medi-Build has the intention to use a combina- most effective funding structure for the project. Medi-Build has a well thought out
tion of these six components during the entire life of the project; however the final strategy to deliver value for money outcomes for the state. The funding approach
structure has yet to be decided and will be further developed during the bid phase in requires three key features; reputable partners with a high quality institutions; An In-
conjunction with KPMG. teractive approach to maintain a competitive collaborative process between financiers
and finally a robust structure in terms of structure, gearing and securities, Medi-Build
Form of capital Term and tenor Comments must make sure it is sustainable for the whole life project. In developing the debt
structure, Medi-Build will consider the available market and the optimal level of gear-
Credit foncier debt Whole of life credit foncier from Some banks have indicated
construction completion that whole of life debt might ing for the project.
be available but as a small
portion of the overall debt size
Strategy and approach with debt providers
Bullet debt 5-7 year interest only and repayable The most efficient debt – the
as a bullet state can back-end its pay- Medi-Build’s approach to obtaining commitments from debt providers is based on
ments as it does not need to forming a strong financiers group. Medi-Build believes that a group comprising the
include principal payment, four major domestic banks in ANZ, Commonwealth bank, NAB and Westpac along
however, involves the highest
refinance risk. with Bendigo bank and Australian Super will be required to achieve certainty a com-
Interest only/ 10-12 year tranche that remains Less efficient than interest- petitive funding package. Medi Build will also form a core bank group comprising of
amortiser debt interest-only during construction only but likely to be priced at least two of the major banks with experience and expertise in project financing.
and potentially operations, before more effectively
Medi-Build will work closely and in a cooperative manner with the core bank group to
amortising to balloon
Bonds 25-30 year nominal or indexed Whole of life tenor which ele- develop the financing solution and drive the wider financiers group.
annuity bonds ments refinancing risk. How-
ever, may be comparatively
more expensive than bank
debt
Equity Redeemable preference shares and The level of gearing is ex-
ordinary equity with a coupon that pected for similar projects is in
may be deferred the same range of 85-90%
significant quantum expected
from offshore investors.??
Liquidity facility A standby cash advance facility To support operating expendi-
ture and capital expenditure
overruns.

FINANCE PAGE 4
VALUE FOR MONEY FINANCING
The funding solution will be driven by core bank group, leading the rest of the group The key principles of the strategy are as follows
towards the most competitive package.
! Certainty of financing
KPMG have a great relationship with the financiers in the group as well as Macquarie ‣ Medi-Build will provide certainty of funding to the State for the pro-
and Lend Lease Infrastructure Investments already have a close relationship with all of ject.
the banks in the group as well Medi-Build will be able to draw on these relationships ‣ The approach taken of only having the two project sponsors con-
to drive the financing solutions and resolve any issues that may arise. This is a key tribute to the entire equity funding gives the state certainty that the
differentiating factor in recognising the strength of Medi-Builds financing capability. necessary equity finance will be available for the project
! Alignment of interests
Medi-Build’s ability to obtain the most competitive funding is further strengthened by ‣ Medi-Build members and key contractors are committed to holding
its integrated whole of life solution. This whole of life approach is supported by a cornerstone equity stake in the project
Baulderstone and Spotless our D&C and FM provider during design, construct and ! Flexibility
operational phase. ‣ Medi-Build will be flexible in structuring it’s funding solution and
consider all forms of financing to develop a fully committed debt
Competitive Equity Funding and equity package for the project
Based on what the new Victorian Coalition Government has pledged to the project ! Team
from the 2011-2012 state budget there is an indicative project size of A$630m. Medi- ‣ Medi-Build’s members are experienced with proven capability in
Build has the expectation that both project sponsors will provide a required total eq- delivering large scale complex PPP projects
uity of 20% of the above indicated project cost, which equates to $126m. ! Simplicity
To achieve value-for-money and financial certainty for the State, Medi-Build has put in ‣ Medi-Build is committed to developing a structure that us trans-
place key objectives and principles for the equity funding strategy of the project. parent and sustainable for the whole life of the project, and
The key objectives of the equity strategy are to ‣ In the environment, the State will seek a simple, straight forward
and efficient financing structure
! Create a trusting relationship for the whole term of the project with the Medi-
Build Sponsors who are contributing all of the equity, and Equity Investor Indicative Equity Contribution
! Secure flexible equity capital competitively that is truly reflective of the project
Macquarie Capital 50%
risks in order to deliver value for money outcomes for the state.
Lend Lease Infrastructure 50%
Investments
Total Sponsors 100%

FINANCE PAGE 5
EXPERIENCE AND CAPABILITY
FINANCE

Medi-Build’s capability to raise funding for PPP projects of similar size and complexity Medi-Build’s financial adviser KPMG has a dedicated debt advisory team with exten-
is demonstrated below where their wealth of past experience in funding transactions sive experience in funding Public Private Partnership transactions, which assisted to
in the infrastructure sector and their ability to be able to raise debt and equity financ- deliver projects such as;
ing for a large number of quality projects displays their experience and judgment to ! Moscow-Saint-Petersburg PPP Toll Road (684 kms)
help deliver a successful financing package. ! Pulkovo airport
! Moscow waste disposal plant
Below are past successful PPP projects which show Medi-Builds proven capability to ! Construction of educational centres in Russian regions
deliver committed financing solutions despite the challenges in the current financial
markets. KPMG is a known industry leader and has advised on over 1,700 PPP transactions
with a value of over $285 billion. The combined extensive knowledge and experience
Transaction Date Cost of Medi-build sponsors in arranging debt is demonstrated below
(Aus $m)
Royal Women’s Hospital (Victoria) – Macquarie May 2007 307
Transaction Debt Raised (Aus $m)
New Royal Children’s Hospital (Victoria) – Lend Lease November 2007 946
Victorian Desalination Plant 4,100
Education Works New Schools (South Australia) – July 2009 323
Eastlink (Victoria) 2,370
Lend Lease
North Staffordshire Hospital (United Kingdom) - June 2007 833 The Royal Women’s Hospital (Victoria) 290
Macquarie
New Royal Children’s Hospital (Victoria) 600
Victorian Desalination Plant (Australia) - Macquarie September 2009 5,720
Toolern development in Victoria 1,200
Toolern development in Victoria – Lend Lease May 2010 1,200
South Australian New Schools 250

EXPERIENCE AND CAPABILITY PAGE 2


DESIGN
The Medi-build design team offers the State the required design experience, knowl- Our team is enhanced through specialist advice from professional in the health care
edge, specialist understanding and proficiency to successfully deliver the Bendigo industry which will give us the right insight needed to complete the project success-
hospital. fully. Further enhancing the design team a world study tour was undertaken in 2010
which included visits to hospitals in Holland, Belgium, Spain and the USA to under-
Medi-build understands the scale of the complexity of the project and has aligned an stand the trends in the health care design and prepare for future planning.
experienced design team to work together with key stake holders to successfully de-
liver the requirements of the project. Through previous knowledge and successful
delivery of previous PPP projects the design team understands that the PPP process
requires more creativity and innovation in the design than other forms of procurement. Key Benefits

Medi-Build has selected and structured and team to ensure this is achieved. The Medi-Build Design Team is a collaborative and unified group comprising local,
national and international expertise and experience in Research, Health and PPP pro-
Our Design Team comprises multi-disciplinary architects and research and health care jects. Working on previous projects and during the EOI process the Medi-Build design
specialist. Medi-Build’s design team consists of two experts in their fields; Bates team has a made a cohesive connection with one another that has established work-
Smart and Silver Thomas Hanley. ing relationships within the consortium. Through existing relationships with key stake-
holders and Bendigo project partners we believe the design team will be able to de-
Silver Thomas Hanley has over 30 years’ experience in delivering innovative health liver a world class project. Our combined national and international expertise and ex-
care solutions which represents an exceptional value for money for their clients. perience has provided us with the knowledge required to provide a future ready and
Health being their primary business they have successfully delivered several health-
value for money project
care facilities overseas and nationally, which recognises the level of experience they
have in all facets of the health care industry. Silver Thomas Hanley is locally based in
Melbourne and has over 80 personnel in Melbourne and Sydney. Amongst the pro-
jects delivered abroad and nationally they have provided first class facilities in a range
of health areas including; cancer care, tertiary and research, women’s and children’s
health, mental health, aged care and health PPPs for local and overseas govern-
ments.

Bates Smart being a multi-disciplinary architect has great experience in Health and
research projects. Established in 1853 Bates Smart is Australia’s oldest architectural
firm, this being said they will provide a great amount of knowledge and experience to
the team. They have recently been involved in Australia’s most significant Health Care
and Urban Renewal developments including the Royal Children’s Hospital and the
Alfred Centre Stages 1&2.

EXPERIENCE AND CAPABILITY PAGE 3


BATES SMART SILVER THOMAS HANLEY

The Austin Redevelopment & Mercy Hospital for Women, VIC


Royal Children’s Hospital Parkville, Melbourne
The Austin Redevelopment & Mercy Hospital for Women project contains two hospi-
The RCH design will provide 3000m2 of clinical, research and educational facilities.
tals on the original hospital campus. Silver Thomas Hanley successfully completed
Working on the RCH we have the knowledge and an established relationship between
this project to maintain Austin’s Health’s reputation as one of Australia’s leading teach-
one of the key stakeholders, the University of Melbourne. This new research facility is
ing, training and research centres. With some of the best facilities in the country STH
doubling in space to accommodate for education programs, courses, workshops and
created a unique teaching, training and research precinct including a teaching space
conferences. The design ensures collaboration and communication is achieved be-
and laboratory on each level of the Austin Hospital Tower. Outside of University this
tween the research and clinical areas to better the community.
development has the largest number of students studying health professions on a
single site.
Alfred Centre Stages 2 Prahran, Melbourne
The $180 million Alfred Stage 2 adds an additional four floors to the redevelopment.
The Royal Prince Alfred Hospital, NSW
The design and additional 18,000m2 provides functional and operation needs for the
The RPA redevelopment turned an existing facility into a modern 810 bed Level 6
users which includes – PC2/PC3 laboratories, specialist support facilities, clinical re-
major quaternary/tertiary hospital. With an innovative design a 9 level tower block was
search space, flexible teaching spaces, a lecture theatre and a tutorial feel environ-
designed constructed to provide specialist medical, laboratory and research/
ment. Bates smart has great experience dealing with multi-stakeholders in this area.
education facilities. The RPA development is in an education district and provides a
During the design development and construction phase, Bates Smart worked with
state of the art auditorium and lecture theatres.
Bayside Health, The Burnet Institute, Monash University Medical School, La University
Sunshine Hospital, Victoria: Teaching, Training & Research Facility
Faculty of Health Sciences and the Barker Institute/IDI.
Silver Thomas Hanley are currently designing a new Teaching Training and Research
Building for University of Melbourne, Victoria University and Western Health. This $60
Victorian Comprehensive Cancer Centre (Masterplan), Melbourne
million 5 level building will house lecture theatre and seminar facilities, laboratories and
Bates Smart has completed the Masterplan and Feasibility study for the Victorian
offices to attract nursing and medical students and staff to a collaborative of learning.
Comprehensive Cancer Centre (VCCC). Bate Smart plan to deliver world class facili-
Existing to be refurbished includes the 8 bed Birth Suite (plus 2 new beds) and a 38
ties that links clinical, research and education collectively. The plan enables full inte-
bed Postnatal Maternity Unit in a staged construction.
gration with key stakeholders which will bring Peter MacCallum Cancer Centre, Lud-
wig Institute for Cancer Research, Melbourne Health and Melbourne University all in
the one area.

EXPERIENCE AND CAPABILITY PAGE 4


Project of Similar Size and Complexity Awards

Royal Children’s Hospital Parkville, Melbourne Project of acclaimed architectural and urban design quality as demonstrated through
The Royal Children’s Hospital is the largest hospital redevelopment undertaken by the peer recognition. Silver Thomas Hanely and Bates Smart both have received national
State Government of Victoria. In a goal to achieving a world class health facility this and internal recognition through architectural and urban design quality and have re-
project is similar in size and complexity of the Bendigo project. The RCH is providing ceived the following awards:
many innovative health care concepts to enable it to be future ready and create value
for money for the state. Various design concepts are in place to create a family cen- SILVER THOMAS HANELY
tred design, an environmentally sustainable design and a design that will enable a - RGH – Aged Acute Mental Health Unit
welcoming and nurturing environment. The $1 billion project will provide patient rooms - RAIA SA Chapter Awards, The colorbond Award for Steel Architecture
(85% being of single occupancy) that are designed to respond to the emotional needs Award 2007
of children and enhance patient experience and recovery rates. - Lyell McEwin Hospital Redevelopment Stage A
As required with the Bendigo Hospital project, the RCH is involving multiple key - RAIA SA Chapter Awards, New Buildings Award 2006
stakeholders and community engagement to deliver one of Australia’s most recog- - RAIA SA Chapter Awards, Sustainable Architecture - Commendation 2006
nised health care facilities. The RCH is also trying to achieve a 5 star green star with - RAIA SA Chapter Awards, Collaborative Design – Commendation 2006
the use of environmentally sustainable design principles enhancing a design to heal
and nurture which will also be required of the Bendigo project. BATES SMART
- Victoria Barracks
The Abbotsford regional Hospital and Cancer Centre, Canada - RAIA National Awards, BHP Colorbond Steel Award 2003
The Abbotsford regional Hospital and Cancer Centre, a PPP project in Canada was - RAIA NSW Chapetr Awards, ESD/Energy Efficiency Award 2003
the first in the region. The completion of the project achieved value for money which - RAIA NSW Chapter Awards, Commercial Buildings Architecture Award 2003
was able to deliver 300 hospital beds which would service for over 150,000 people in - RAIA NSW Chapter Awards, BHP Colorbond Award 2003
the direct region. The $355 million facility was built on time, on budget and within - The Architecture Show Magazine and The Francis Greenway society, Green
scope. The building is approximately 60,000sqm and provides specialised health Buildings Awards, Bronze Medal 2002
services including, general acute care, maternity, NICU, cardiac care, palliative care, - Federation Square
emergency, ambulatory care and a cancer treatment centre. Silver Thomas Hanley in - Property Council of Australia Award: Overall Winner 2005
association with Musson Cattell Mackey Partnerships where able to deliver the full - Urban Land Institute Award for Excellence: Asia Pacific 2003
design of this project. The PPP received various awards and a Gold LEED certification - RAIA National Awards, Walter Burley Griffin Award for Urban Design 2003
(equivalent to Australia Green Star). This project is similar in size and followed the - Architecture + Cityscape Awards, Dubai, Winner, Urban Design Category
same procurement process as the Bendigo Hospital and includes high levels of tech- 2003
nical integration and ESD integration which will be required for the Bendigo project. - RAIA Victorian Chapter Awards: Victorian Architecture Medal, The Mel-
bourne Prize, Urban Design Award And Institutional – New Architecture
Award 2003

EXPERIENCE AND CAPABILITY PAGE 5


Sustainable Design PPP Design
Medi-Build’s design team has achieved various ESD outcomes which include: The Medi-Build design team has delivered major PPP projects such as:

Royal Children’s Hospital Parkville, Melbourne - Royal Children’s Hospital Parkville, Melbourne
The RCH includes ESD features such as tri-generation, active chilled beams, solar - NSW Police Headquarters Parramatta, Sydney
panels, biomass boiler, rainwater collection, black water treatment plant, low loc ma-
- Casey Hospital, Berwick, Victoria!
terial selection, façade design and orientation and 500 bike parks, The project is tar-
- Orange Hospital, New South Wales
geting a 5 Star Green Star rating.
- International PPP projects:

Alfred Centre Stages 1&2 Prahran, Melbourne - Abbotsford Regional Hospital and Cancer Centre, Abbotsford, Canada,
The Alfred Centre Stages includes leading ESD initiatives such as double glazing, low - Niagara Health, Ontario, Canada
e glass, passive solar design, window louvers, water conservation, low voc material
selection, heat exchange from central plant, economy cycles and variable speeds and
integrated building management systems.

Federation Square Melbourne


Federation Square has been design to incorporate extensive innovative ESD initiatives
including an advanced thermal storage system, passive cooling technology, air pre-
cooling system, solar chimneys and rainwater collection and re-use.

Orange-Bloomfield, Hospital Redevelopment


STH has recently used ESD initiatives in the architecture and design of Orange-
Bloomfield Hospital. ESD strategies and principles introduced include, double glazing,
low e glass, external shading, radiant barriers, introduction of natural light, low voc
material selection, high efficiency chillers and modular boilers and rain water harvest-
ing.

Abbotsford Regional Hospital and Cancer Centre, Abbotsford, Canada,


STH designed the recently commissioned Abbotsford Hospital, Canada to Gold
LEEDTM (Leadership in Energy and Environmental Design) Certification, as adminis-
tered by United States Green Building Council and all recent projects in Australia to
the “Green Star” standard. The Abbotsford Hospital is the first hospital in Canada to
be awarded Gold Certification.

EXPERIENCE AND CAPABILITY PAGE 6


EXPERIENCE AND CAPABILITY PAGE 7
CONSTRUCTION
Medi-Build Construction will comprise a joint venture between Baulderstone and Han- Baulderstone
sen Yuncken who pride themselves on excellence in Victoria’s construction sector. Baulderstone is one of Australia’s largest construction companies, rich in experience
Collectively they possess the highest of talents and expertise capable of delivering and ability in both the building and infrastructure sectors. Their previous involvement
one of Australia’s leading health care facilities to service regional Victoria. Medi-Builds in hospitals and healthcare facilities across Australia further enhances their capacity to
rich history with this joint venture will offer transparent strength and commitment that construct this world-class health service for Bendigo and its surrounds.
will overcome the complexity and challenges constructing the proposed Bendigo Baulderstone have been “Creating what matters” in the Australian construction divi-
Hospital. sion since their inception into the world over eighty (80) years ago. With their 1400
strong employees across the country, Baulderstone have been responsible for com-
Combining the internationally recognised skills of Baulderstone and the locally estab- pleting some of Australia’s leading and most multifaceted projects and will continue on
lished services of Hansen Yuncken brings together a blend of exceptional quality to
this route long into the future. With a project portfolio that encompasses models such
create a PPP of this magnitude. Medi-Build appreciates the complexity in construction as the $250 million Royal Women’s Hospital, Austin and Mercy Hospital ($293 million),
of such a project and with complete confidence can assure a quality and timely com- Epworth Hospital Redevelopment ($23 million), Alfred Hospital Victoria ($93 million),
pletion pioneering the way in which health care facilities are delivered.
Walter Eliza Hall Institute of Medical Research ($112 million) of which were complete
using numerous methods including Public Private Partnerships. Combining these
Construction Advantages
health facilities with the numerous building and infrastructure projects Baulderstone
- Widespread experience in the construction and production of major Hospi- boasts in their portfolio stamp their suitability for the Bendigo Hospital.
tal and Healthcare facilities.
Baulderstone come with the support of Lend Lease who are one of the world’s lead-
- Able to provide and maintain total Victorian workforce of 90% or greater for ing fully integrated property solution providers with strong capabilities in development,
the duration of the project. investment management and project and construction management that filters
through their partner company and will be available to assist in areas of need
- Prior involvement with Victoria’s Public Private Partnerships framework throughout the duration of the project.
having delivered a Hospital or Healthcare facility of significance in Australia.
Demonstrating their stakeholder engagement and commitment to supporting the
- Be financially suitable to the project and have the required available per- community, Baulderstone understand the impacts of construction work on all areas of
sonnel to complete the outlined project. community living. This is achieved with the development in community and stake-
holder programs through all stages of the construction process. Exemplifying this
assurance was demonstrated in the $3 billion CLEM7 road tunnel which was opened
to the people of Brisbane in March 2010. A consultative tactic to the community was
executed which included a one-on-one consultation program, a Visitor’s Centre, an
up-to-date website, a 24 hour contact number and Community Liaison Groups which
netted the imagination of Queensland residents. These methods will be adapted to

EXPERIENCE AND CAPABILITY PAGE 8


service the people of Bendigo to facilitate a smooth construction route and see to it Hansen Yuncken incorporates leading Ecologically Sustainable Development (ESD)
that minimal undesirable effects are felt within the community. into their construction activities with vast expertise and knowledge that continues to
grow with the company. Their knowledge in sustainability in construction will provide
Health and safety of employees, contractors, customers, visitors and the general pub-
instrumental support for the Bendigo Hospital and the design team in making the
lic is paramount to Baulderstone which is embedded throughout all levels of the com- correct choices throughout the project. For the project Hansen Yuncken will provide:
pany. As proof of their high level safety guarantee, Baulderstone are proud to have
been the first top-tier construction company to achieve an Australia-wide accredita- - In-house design managers to assist in integrating ESD into construction
tion on all sites to AS 4801 “Occupational, Health & Safety Management Systems”. documentation
Continuing to strive for the highest levels of safety, the Bendigo Hospital will be no
exception to their commitment that “safety matters” in the workplace. - Cost advice of ESD initiatives

Hansen Yuncken - Ecologically sustainable site management practices

Hansen Yuncken is considered one of Australia’s largest privately owned construction


- Commercial guarantee of Green Start energy rating
companies operating across all states. Since its origin over ninety (90) years ago Han-
sen Yuncken has grown to employ over 800 people and currently has a portfolio con- - Training and induction of building managers and users
taining $2.6 billion in current projects. Change and innovation distinguish Hansen
Yuncken from other locally owned construction companies in the building industry. A solid relationship with their business partners and a strong financial status contrib-
Strong recognition for their pioneering roles in applying new technologies, the uted to their number one (1) ranking for Private Commercial Builder in Business Re-
development of modern techniques, project delivery methods in building and infra- view Weekly survey 2010. A strong balance sheet of $118 million, large cash re-
structure and multi award winning recognition for NSW Public Private Partnerships serves, no current debt and a BBB+ credit rating allows Hansen Yuncken to have in
sets Hansen Yuncken apart from the rest. excess of $270 million worth of available securities placing it in a sturdy position to
partner in the construction of the Bendigo Hospital.

Hansen Yuncken have been committed to producing quality and complex projects
since the beginning including creations such as the $157 million Lyell McEwin Hospital
Redevelopment Stage A & B, Prince of Wales Hospital refurbishment ($18 million),
The Grange Aged Care Facility ($10.5 million), Bendigo Police Station ($16 million) and
the $194 million Orange Hospital being delivered as a Public Private Partnership initia-
tive of the NSW Government.

EXPERIENCE AND CAPABILITY PAGE 9


Royal Women’s Hospital
Location: Parkville, Victoria This $293 million redevelopment comprised 440 new inpatient beds, new emergency,
Contract Value: $250 million intensive care and critical care units. Existing operating facilities and the mental health
Construction Period: Apr 2005 – Jun 2008 unit were redeveloped and expanded to accommodate a greater number of patients
Type of Contract: Design & Construct (PPP) and improve patient care.
Client: Department of Human Services/RWHP
The success of this project was largely due to the collective effort between the design,
This new Women’s Hospital provides advanced amenities and services supported by construction and the Facility Provider overcoming obstacles which will be an essential
a family friendly environment further enhancing patient care. This $250 million hospital requirement for the Bendigo Hospital Project.
consists of a new stand-alone, nine level structure which provides treatment facilities
for gynecology, obstetrics, neonatal paediatrics, cancer care and complete sexual
health treatment. Alfred Hospital
Location: Melbourne, Victoria
This pinnacle of building excellence was delivered as a Public Private Partnership un- Contract Value: $90 million
der the Government’s Partnership Victoria policy. The Royal Women’s Health Partner- Construction Period: Sep 2004 – Oct 2006
ship financed, designed, built and will continue to maintain the hospital for a 25 year Type of Contract: Construction Management
timeframe. From initial planning to final completion, Baulderstone worked within the Client: Department of Human Services/The Alfred in Partnership
partnership to deliver a world-class health facility which is seen as a model Public
Private Partnership for Victoria. Their success in such a large scale health facility illus- The Alfred Centre provides many similar features and services as those outlined for
trates Baulderstone’s expertise and skill in producing a benchmark project which sup- Bendigo hospital. This stage is a multi-level hospital providing patient information and
ports their ability to complete the Bendigo Hospital. services area, pre-admission and consulting areas, education and admission services
as well as a specialised retail division. It required construction to house 81 beds which
include overnight and medical day procedure beds, and specialist areas designed for
Austin and Mercy Hospital surgery admission and recovery.
Location: Heidelberg, Victoria
Contract Value: $293 million Associated building and infrastructure works had to be integrated with the existing
Construction Period: Nov 2001 – Jan 2006 hospital, which was done in such a way that it remained fully functional for the extent
Type of Contract: Managing Contractor of the project. This was made possible through extensive cooperation and communi-
Client: Major Projects Victoria cation with hospital personnel and the construction team. Design and construction of
the Alfred was done in such a way to accommodate future expansion with proceeding
Baulderstone controlled the entire design and construction of the four separate divi- stages.
sions of the project. This incorporated a new four level car park below the hospital
structures, a new clinical block for the two hospitals and a complete refurbishment of This project shows Baulderstone’s capability to deliver a project of such magnitude
the existing Austin Hospital structures. and with the use of the same Architect in Silver Thomas Hanley will add further value
to the process of completing the Bendigo Hospital Project.
EXPERIENCE AND CAPABILITY PAGE 10
Orange Hospital Bendigo Police Station
Location: Orange, NSW Location: Bendigo, Victoria
Contract Value: $194 million Contract Value: $16 million
Type of Contract: Design & Construct PPP Type of Contract: Lump Sum
Client: NSW Health Client: Victoria Police

Orange Hospital was an NSW Government initiative developed as a social infrastruc- The construction of a new 24 hour police station in Bendigo was completed by Han-
ture Public Private Partnership completed in mid-2010. This PPP involved Hansen sen Yuncken in late 2007. This modern police facility covers an area of over 5,000m2
Yuncken in the design, construction, finance and maintenance of the new hospital and hosts 170 staff from varying police operational units. Constructed on Bendigo’s
and related infrastructure within the existing Bloomfield Health Campus in regional main thoroughfare it delivers an accessible and user friendly facility for not only local
NSW. residents but the increasing number of visitors travelling to the area an annually.

Similar to the Bendigo Hospital, this consisted of a new multi-level Hospital with both Similar to the Bendigo Hospital Project, this facility was constructed in the very heart

integrated Cancer Care facilities and a new Mental Health services. The construction of Bendigo to provide essential services to the public residing in regional Victoria. Site

of the new core hospital building consisted of 200 general beds, four (4) operating access issues were overcome through Hansen Yuncken’s management techniques
that have seen them continue to construct major regional projects right across Austra-
theatres, sixty (60) specialist treatment areas, multiple radiotherapy bunkers and ac-
companying community health areas. The construction was of significant size of lia.

32,000m2, refurbishment of two (2) existing heritage buildings and a new helicopter
The completion of a challenging design and construction complex in Bendigo will
pad with comparable issues surrounding the new Bendigo Hospital facility.
strengthen Hansen Yuncken’s capability in partnering with Baulderstone to produce
the Bendigo Hospital PPP.
As a PPP and delivering similar health facility requirements, this is a relevant example
of Hansen Yuncken’s experience in constructing significant projects to regional areas
of Australia.

EXPERIENCE AND CAPABILITY PAGE 11


EXPERIENCE AND CAPABILITY PAGE 12
FACILITIES MANAGEMENT
With over 50 years experience, Spotless currently employs over 40 000 staff who Spotless foster long-term partnerships with their customers, ensuring they benefit
deliver a diverse range of integrated services. Spotless focuses on providing Managed from their expanding breadth and depth of services. Spotless service offerings con-
Services, cleaning, food, laundry, painting, and retailer services. tinue to expand through increased product development and opportunities to inte-
grate multi-services.
Spotless is also a leader in delivering sustainable solutions through re-use initiatives,
and water and energy savings. Combined with their already comprehensive involve- Spotless clients benefit from their Managed Services' focus on
ment in large projects Australia wide, Spotless has a wealth of knowledge in operating - reducing your operating costs
as an integrated team.
- using technology to streamline processes

Large projects and experience that Spotless have experience include; - outsourcing non-core services - so that you can focus on what you do best

- Special Event Hospitality Services - implementing systems and processes that enable risk minimisation and

management
- Housing New South Wales (the largest residential maintenance contract in

the Southern Hemisphere) - managing for whole-of-life - no surprises

- Southbank Education and Training Precinct - accurate reporting.

- Headquarters Joint Operations Command (HQJOC)

- Sterilised Hospital Linen Services

- New Zealand Police

EXPERIENCE AND CAPABILITY PAGE 13


Daniel Collins

Rohan Chandler

Mark McSweeney

Jordan Kiely

Kostandinos Stamatopoulos

Trent Moernhout

Anthony Badagoff

Zdravko Knezic
BIBLIOGRAPHY

! Advanced Construction Management Lectures & Workshops (Semester One, 2011). Delivered
by Guillermo Aranda-Mena (and the various guest presenters)

! The New Bendigo Hospital. 2011. Project website.


http://www.newbendigohospital.org.au (accessed May, 2011)

! Bendigo Health. 2011. Information concerning the New Bendigo Hospital.


http://www.bendigohealth.org.au (accessed May, 2011)

! Partnerships Victoria. 2011. New Bendigo Hospital.


http://www.partnerships.vic.gov.au (accessed May, 2011)

! Silver Thomas Hanley – Health Architecture. 2011. Practice / Philosophy / Projects /


Sustainability.
http://www.sth.com.au (accessed May, 2011)

! Bates Smart. 2011. Studio / Projects / Recognition.


http://www.batessmart.com.au (accessed May, 2011)

! Spotless. 2011. About us / Services / Experience / Sustainability.


http://www.spotless.com (accessed May, 2011)

! HealthSMART. 2011. Victorian Health IT website.


http://www.health.vic.gov.au/healthsmart/ (accessed May, 2011)

! Green Building Council of Australia (GBCA). 2011. Rating tools – Healthcare.


http://www.gbca.org.au (accessed May, 2011)

! Jimmy Possum. 2011. Australian made & designed furniture.


http://www.jimmypossum.com.au (accessed May, 2011)

! Baulderstone. 2011. Information on projects, vision, etc.


http://www.baulderstone.com.au (accessed May, 2011)

! Hanson Yuncken. 2011. Information on projects, vision, etc.


http://www.hansonyuncken.com.au (accessed May, 2011)

! Lend Lease Infrastructure Investments. 2011. Information for finance, PPP’s.


http://www.bovislendlease.com (accessed May, 2011)
! Macquarie Capital Group. 2011. Business / Corporate, Institutions & Government / Advisors /
About Macquarie.
http://www.macquarie.com.au (accessed May, 2011)

! KPMG. 2011. Home page.


http://www.kpmg.com.au (accessed May, 2011)

! Bendigo Bank. 2011. Home page.


http://www.bendigobank.com.au (accessed May, 2011)

! ANZ. 2011. Home page and financial advice / corporate information links.
http://www.anz.com.au (accessed May, 2011)

! National Australia Bank (NAB). 2011. Home page and financial advice / corporate information.
http://www.nab.com.au (accessed May, 2011)

! Australian Super. 2011. Home page.


http://www.australiansuper.com (accessed May, 2011)

! Multiplex Standard EOI guidelines


! Multiplex intranet (accessed May, 2011)

! Baulderstone Health Project guidelines


! Baulderstone intranet (accessed May, 2011)

! IBM. 2011
! http;//www.ibm.com.au (accessed May, 2011)

! Hospitals & Sustainability - Curtin University (B Burger and P Newman)


! http://sustainability.curtin.edu.au/local/docs/Hospital_Final_lowres.pdf (accessed May, 2011)