Академический Документы
Профессиональный Документы
Культура Документы
SRI LANKA
1. Construction of
132kV Transmission Lines from
Matugama GSS to Ambalangoda GSS
Polpithimukalana to Aniyakanda GSS
Maningala to Pannala GSS
2. Replacement of
Steel Ground Wire with OPGW from
Biyagama GSS to Sapugaskanda PS
Kotugoda GSS to Kelaniya GSS
Kelaniya GSS to Kolonnnawa GSS
Chilaw GSS to Kotugoda GSS
Pannipitiya GSS to Paragastota In & Out
Panadura GSS to T – Off point
Transmission Division
Ceylon Electricity Board,
P.O. Box 540, Colombo 02,
Sri Lanka.
June 2004
Document – Revision 2
Pages
1 Scope of Works
1.1 General Description of the project 1 6
1.2 Plant & Equipment Including Spare Parts 7 7
1.3 Civil works, installation and other services 7 7
1. SCOPE OF WORKS
(a) 132kV double circuit three phase transmission line of, single 400mm2
ZEBRA (61/3.18mm) ACSR with one galvanized ground wire and one
optical fibre ground wire (OPGW):
(i) From Mathugama to Ambalangoda -:28 km
(ii) From Polpithimukalana to Aniyakanda including π-off connection to
one circuit of the Kotugoda / Kelaniya 132 kV Transmission Line at
tower No: 34 A; the T-OFF connection shall be as shown in the
drawing no. TD/CE/1/44/TYP-06 and subjected to the approval of the
Employer’s Representative. -: 5.5 km; however the final length of the
line will be confirmed at the pre-bid meeting.
(iii) From Maningala to Pannala including π -off connection to one circuit
of the Kotugoda / Puttlum 132 kV Transmission Line at tower No: 43 -
: 14 km.
(b) Replacement of one galvanized steel ground wire with Optical Fiber Ground
Wire (OPGW) in following existing transmission lines including erection of all
necessary connectors, fittings and accessories for OPGW. Directional
routing facility must be available at outdoor type Patch Panels to be located
at all T-Off and π-off terminations as described below :-
(i) From Biyagama Grid Substation to Sapugaskanda Power Station-: 2
km
(ii) From Kotugoda Grid Substation to Kelaniya Grid Substation.-: 19.5
km
In order to facilitate connections to Aniyakanda Grid Substation,
outdoor type Patch Panel should be provided at Polpithimukalana
(tower No 34A).
(iii) From Kelaniya Grid Substation to Kolonnawa Grid Substation -: 6.5
km
(iv) From Chilaw Grid Substation to Kotugoda Grid Substation -: 49 km
In order to facilitate connections to Pannala Grid Substation and
Bolawatta Grid Substation, outdoor Patch Panels should be provided
at Maningala (tower No. 43) and Bolawatta (tower No. 55).
The existing transmission lines where the ground wires to be replaced with
OPGW , will be at energized (full hot line) state throughout the contract period
and the Contractor will be expected to carry out the Works under live line
condition (full hot line). The removed galvanized steel ground wire shall be
neatly bundled and shall be delivered to the asset management stores along
with the removed accessories as instructed by the Employer.
1.1.2 CLIMATE
The climatic data given are for the standard period for 1945-1975. This data has
to be up dated with the latest available data.
The climate is that of a tropical region and the following meteorological
information is set out for guidance only.
(A) AIR TEMPERATURES –
Records are available for the monthly mean daily maximum and daily minimum
temperatures with offset from average. The averages are taken for the standard
period 30 years and all shown in Table 1.1 and 1.2.
(E) WIND
One to three second gusts at 145 km per hour have been recorded with a
mean speed of 27km per hour over 24 hours.
(F) STORMS
The frequency of thunder-storms is high, the isokeraunic level being
approximately 60 days per annum on average for the island.
Refer Plant & Equipment including Mandatory Spare Parts from outside the
Employers country and Plant & Equipment including Mandatory Spare Parts
from within the Employers country in Schedules. (Section 7 of the Tender)
2.1.1 The following drawings which are of a sufficient standard to indicate clearly all
manufacturing and structural details must be prepared by Contractor and
accompany each Tender:-
- Outline and general arrangement for all basic types of towers or supports,
with main dimensions, steel qualities, design spans, body and leg
extensions. Wire clearance diagrams for each tower type, for specified
swing angle.
- Vibration dampers.
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 8
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Drawings need have leading dimensions only. Tower and support drawings
should have provisional dimensions of main members and should indicate the
necessary clearance dimensions for structures for still air and maximum swing
of insulator and jumpers called for in this Specification.
The conductor and earthwire tension charts are to show final sags and tensions
for a range of equivalent spans between approximately 50 % and 200 % of the
basic span in still air at maximum, everyday, and minimum temperature, and the
tension at minimum temperature under full wind.
The successful Contractor will be required at the time of the letting of the
Contract to supply additional copies of such drawings submitted with his Tender
as may be selected by the Employer’s Representative. These drawings
together with copies of the drawings originally issued with the Tender
documents will then be bound up either in the Contract document or in a
separate folder and will be signed both by the Employer and the Contractor for
purposes of identification.
2.1.3 General bar chart of the design, manufacturing, shipping, erection and
commissioning schedule clearly showing the transmission line outages.
2.1.7 List of standards the Bidder intends to follow, for the electrical and for the civil
works.
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 9
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Repair Sleeves
Vibration Dampers
EARTH CONDUCTORS
Steel Wires 7/3.25mm
Clamps
Tension Clamps
Mid-span Joints
OPGW / OFAC
Steel wires
Optic Fiber
Complete OPGW
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 10
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
STEEL TOWERS
Steel Sections
Fabrications
Galvanising
TESTING
Insulator string
Tower
ACSR Conductors
Earth wire
OPGW
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 11
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
2.2.2.1 GUARANTEES
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 12
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Factor of
Description Safety
Conductors, Earthwires and OPGW at Maximum Working 2.5
Tension based on Ultimate Strength
Conductors and Earthwires at Everyday Temperature still Air 4.5
Tension, based on Ultimate Strength
Anchor Clamps and Mid-span Joints, based on Ultimate 0.95
Strength of Conductor and Earthwire
Insulator Strings and Fittings at Maximum Working Tension 3.0
based on Failing Load
Straight Line Supports and Foundations under Normal Working 2.0
Loads
Angle, Section and Terminal Supports and Foundations under 2.5
Normal Working Loads
Towers under Broken Wire Loads 1.25
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 13
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
- Middle Layer mm
- Outer Layer mm
Overall Diameter mm
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 14
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 15
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 16
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
2.2.3.2 OPGW
The bidder is required to fill the spaces in this schedule
Description Unit Offered
Type of OPGW
Conforming to standard (specify standard)
Construction of OPGW
1) Overall
- Number of tubes
- Tube diameter
- Tube material
- Number of fiber/tube
- Length of each fiber per km of OPGW (km)
- Filling compound
- Central strength member
- Heat resistant barrier
- Material of fiber
2) Inner layer
- Material
- Number of wires
- Diameter of wires
- Cross-section
- Lay ratio
3) Outer layer
- Material
- Number of wires
- Diameter of wires
- Cross-section
- Lay ratio
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 17
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Modulus of elasticity
- Initial kg/mm2
- Final kg/mm2
- Short term mm
- Long term mm
Strain margin
- Nominal %
- Maximum allowance %
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 18
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 19
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 20
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 21
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
C: Splice Enclosure
Description Unit Qty
Manufacturers Name and address
Manufacturers type designation and model number
Standards
Number of splices 24
Number of cables 2
Maximum diameter of cable mm 30
Maximum pull on cable kg 40
Suspension
Suspension
Low duty
Low duty
Inverted
Tension
Tension
Tension
Jumper
Normal
Normal
Upright
Heavy
Insulator Disc
Designation
Disc Material (Toughened
Glass or Ceramic)
Classification
socket
socket
socket
socket
socket
socket
Ball &
Ball &
Ball &
Ball &
Ball &
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 22
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Suspension.
Suspension
Suspension
Low duty
Low duty
Inverted
Tension
Tension
Tension
Jumper
Normal
Normal
Upright
Heavy
Protected Creepage Distance mm
per Unit
Minimum nominal Creepage Mm
Distance per Unit
Minimum 50 Hz Puncture kV
Voltage per Unit
Fittings
Material of Clamp
Length of Clamp
Material of spacers
Elastic Limit of Fittings
Insulator String
Number of Units in String Nos
Spacing of Unit in String mm
Minimum Failing Load of kN
Complete Insulator Set
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 23
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Suspension.
Suspension
132 kV Line Unit
Suspension
Normal
Low duty
Heavy
Tension
Tension
Jumper
Normal
Upright
Low duty
Inverted
Tension
Dry 1-minute 50 Hz Withstand
of Normal Insulator Set
Complete with all Fittings
Wet 1-minute 50 Hz Withstand
of Normal Insulator Set
Complete with all Fittings
Dry Impulse withstand Voltage
(1.2/50) of Normal Insulator set
complete with all fittings
Positive wave +kV peak kV
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 24
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 25
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 26
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Supervising Engineers
Headquarters
Project Director
Project Manager
Project Manager
Site Manager
Supervising Engineers
Construction Supervisors
The Tenderer shall list in this schedule the key personnel (including first nominee and
the second choice alternate) he will employ from headquarters and from site office to
direct and execute the works.
The Schedule shall be completed by the contractor and the times entered shall be
binding on the contractor.
The latest date by which an order must be placed to permit completion by the specified
dates shall be entered, together with the guaranteed periods in weeks from placing of
order to the completion of the lines. The completion time of each of the new lines and
lines of which Steel Ground Wire to be replaced with OPGW should be entered in
separate sheets. Also all new lines and lines of which Steel Ground Wire to be
replaced with OPGW should be considered progressing parallely.
All periods shall be in weeks, calculated from the latest date for placing the order. (In
addition to the following table, Gantt chart should also be attached)
Preliminary Survey
Profile Survey
Tower location finalization
Access for Commencement of erection
Steel Structures
Conductors Manufacture
Insulator Manufacture
OPGW Manufacturer
Final Sagging
Final Sagging
Volume of construction
Year Description of the Work
work in US $
Volume of construction
Year Description of the Work
work in US $
Manufacture
Description
Est. Power
CIF Value
Owned (O)
Leased (L)
Capacity
or Used
T or m3
of Each
Rating
Make)
Year
New
No.
of
or
Name and
Item Element Approximate address of Statement of
The tenderer shall enter in this schedule a list of the sections and appropriate value
of the work for which the purposes to use sub contractors, together with the names
and addresses of the proposed sub contractors. The tenderer shall also enter a
statement of similar works previously executed by the proposed sub contractors,
including description, location and value of works, year completed, and name and
addresses of the Employer Notwithstanding such information the tenderer, if
awarded the contract, shall remain entirely and solely responsible for the satisfactory
completion of the Works.