Академический Документы
Профессиональный Документы
Культура Документы
Paper presented at
Hydro Vision 2000, August 8 – 11, Charlotte, N.C. USA
ABSTRACT
After 25 years of operation, site investigations at the hydro power plant Portile De Fier I
showed that complete refurbishment of the turbine and generator would be necessary
within a short period of time for safety reasons. Cracks on important turbine parts were
increasing operational risks. The plant is operated in peak mode with frequent start and
stop sequences. To optimize day-to-day operation and fulfil the main requirements for
high plant availability, high reliability and just-in-time delivery, a new redundant
automation and control system was installed as well as a plant diagnostic system. A
number of effective and highly sensitive condition-monitoring tools were implemented for
supporting lean maintenance.
Introduction
The hydro power plant Portile De Fier I (HPP PdF I, also named „Iron Gate I“) on the
Danube was commissioned between 1970 and 1972 with six 178 MW Kaplan turbines
each on the Rumanian and Serbian sides. With these 12 units of 9.5 m runner diameter,
it is the largest river power station in Europe.
Several site investigations were made to analyse the status and condition of the power
plant. It was found that for safety reasons, complete refurbishment of the main turbine
and generator components would be necessary. In addition to this refurbishment, the
machines should also be modernized to increase their power output and improve energy
production with an enhanced degree of automation. The increase in output would be as
much as 132 MW for the 6 Rumanian turbines alone.
Sulzer Hydro, now VA TECH ESCHER WYSS (EW), has been working on this project
since 1993. Several site investigations and discussions were held in order to prepare an
optimally attractive proposal to the customer. In particular, EW put together a complete
upgrading and automation package, including generator modernization coordinated with
ABB.
After evaluating several tenders, the Rumanian government decided in August 1997 to
modernize the hydro power plant for safety and economy reasons. CONEL (the
Rumanian Electricity Company) were then instructed to ratify a contract with EW as
main contractor for works execution.
The main work involved, both on site and in several shops (mainly at UCM Resita, IMGB
Bucuresti and VA TECH Escher Wyss), can be summarized as follows:
· Manufacturing of one complete new runner and six sets of new runner blades (five
hubs will be overhauled)
· Manufacturing of six new turbine shafts
· Manufacturing of new main generator stators and pole windings (by ABB as
subcontractor)
· Manufacturing of new stator cores
· Manufacturing of new stator core for the auxiliary generator (part of the excitation
system)
· Manufacturing of new generator stator windings and new poles for the auxiliary
generator
With the liberalization of energy markets, power plant business is coming under
increasing price pressure. This trend is also having a significant effect on control system
and automation technology.
Whether migrating to a newer technology, integrating a new system or adding
functionality, a strong partner familiar with the complete turbine, generator, governor,
protection, diagnosis and auxiliary processes is indispensable. Such partner must also
be able to provide the necessary products, expertise and support services for meeting
all the requirements of fast project handling, as well as homogenous overall plant control
system design.
Modernisation and refurbishment of the PdF I plant control system started in October
1997. After analysis and investigation of the general status and condition of the existing
plant control system, the refurbishing solution was mainly established prior to contract
signing. Besides complete replacement of the control room equipment, the unit control
boards (UCB), the temperature measuring system, the unit low-voltage distribution
(LVD), related sensors and actuators, and the electrical field wiring, it was decided to
also replace the speed governor including mechanical cam and related governor head,
the excitation and voltage regulation system, and the electrical protection system.
The main goal of refurbishment was to increase system availability, stability and self-
diagnosis capability while retaining a clear and simple human-machine interface (HMI).
To keep the entire system as robust, fail-safe and manageable as possible, it is based
on control and protection redundancy for maximum safety and availability.
Unit 1 - 6
Machine Hall
Process Process
HZ HZ
Synchronisation Voltage
kV kV
SIHydro
Control Room
Unit Conditions
Rev. Local
Standstill
Idle Running
MPI
Auto
Excitation
Synchronisati on
ESD
Lamps ON
G Lamps Test
L T P
Mechanical
Protection
Profibus DP1 / DP2
TRIP TRIP
Low Voltage RELAIS A RELAIS B
Governor Turbine Generator Excitation /
Hydraulic Instrumentation Instrumentation Breaker Distribution
P L T T T T P
The diagnostic system consists of 2 diagnostic client stations, 1 SUDIS master server
station and 6 unit diagnostic systems linked by the diagnostic system bus (Fig. 6).
Switch
smartMONITOR of
- Air Gap Characteristics
Hub - PD Characteristics
- Vibration Characteristics
WinCC WinCC - Cavitation Characteristics
Local DB Local DB SUDIS - Temperatures
Global DB - Diagnosis of events and alarms
GPS Joint
Vibration Characteristics
PD Characteristics
AG Characteristics
Cavitation Characteristics
Redundant System Bus
(Industrial Ethernet H1)
Unit 1-6
Safety monitor
Alarm / Protection
Conclusion
Extensive site investigations in close cooperation with the owner, proven engineering
experience in upgrading and refurbishment and new, higly optimised new runners are
fundamental for a safe and profitable plant operation in the next 30 years.
References
Authors