S T A N D A R D O P E R A T I N G P R O C E D U R E

Doc No : Nesb/POD Plant Turnaround 2009 Rev : 0.0


Subject :
Mechanical & Associated Works for DPCU-2 Turnaround January 2009
Prepared By : Date : Page
MFY 04thd february, Page 1 of 1
2009

1.0 INTRODUCTION

These repair procedures is required for painting at external flange area at MD-353 as per PTS
6.2.5.2.5B(2)

2.0 PURPOSE

The purpose of this work as follow:

2.1 To re-painting at external flange area.

3.0 DETAIL OF EQUIPMENT

3.1 Equipment Name : Vessel


3.2 Description : Steam Condensate Tank
3.3 PMT No : 70206
3.4 Technical information: 30.48.00.31 section 6.2.1.2

4.0 REPAIR PROCEDURE


4.1 Type of defect: Findings show painting blistered and bubbling suspected due to hot
temperature.
4.2 Recommended to reapply painting as per PTS painting standard.

5.0 METHOD
1. Perform power tools / wire brush. Ensure the surface is clean and remove all
deposits to provide adequate anchor pattern for paint system.
2. Protect the related equipment before establish painting.
3. Perform visual inspection by INSA.
4. Establish painting system using NO.1C facilities with temperature utility up to 60 o
C (Refer specification as per attached)
5. Perform visual inspection on completed painting by INSA
6. House keeping

4.0 SPECIFICATION

5.1 As per PGB requirement/inspection report.

Prepared by: Approved by

……………………………….. …………………………….
Name: Name:
Date: Date: