Вы находитесь на странице: 1из 13

4

Voltage Dips and Short Supply


Interruptions – Case Study
Zbigniew Hanzelka

C4.1 HV MEASUREMENTS

Identification of the power quality in a transmission system is urgently needed in order to


formulate properly the contracts and asses the suitability of the existing documents. For this
purpose, the power quality factors in lines delivering electric power from a transmission system
have been measured at the Power Distribution Company (PDC) [46].

C4.1.1 The Measuring System


The main part of the 110 kV distribution system operated by the PDC is a ring-operated network.
The whole 110 kV distribution system is operated as a system with a solidly grounded neutral
(Figure C4.1). The PDC-operated 110 kV distribution system is connected with neighboring
operators’ distribution systems and with the 220 kV transmission system by means of three
autotransformers, 160 MVA each, installed at three substations: (a) LUB – industrial and
household customers; (b) WAN – predominantly industrial customers; (c) SKA – near to
a heat and power generating plant.1 At these points instruments have been installed to
measurer the power quality factors. The measurements were carried out over seven months,
at three measurement points. The effect of these measurements is recorded in the database
which contains, among other things, the recorded voltage dips.

1
The number of end customers connected to the distribution system exceeds 800 000.

Handbook of Power Quality Edited by Angelo Baggini


© 2008 John Wiley & Sons, Ltd
G20

Figure C4.1 Block diagram of the example distribution system connections to the transmission
system

C4.1.2 Voltage Dips and Short Supply Interruptions


Tables C4.1–C4.3 give a summary of the recorded voltage dips and short supply interrup-
tions. Most of the disturbances occur within a short time interval.

Table C4.1 Number of voltage dips – WAN (L1/L2/L3)

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 1/3/0 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0


15–30 1/0/4 2/3/3 1/1/1 0/0/0 0/0/0 0/0/0
30–60 0/1/3 0/0/1 0/0/1 0/0/0 0/0/0 0/0/0
60–90 1/1/1 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0
90–100 1/2/3 0/0/0 0/0/0 0/0/2 2/1/3 0/1/0
Number of recorded voltage dips: 44

Table C4.2 Number of voltage dips – SKA (L1/L2/L3)

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 2/3/2 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0


15–30 1/1/0 2/4/2 0/1/1 0/0/0 0/0/0 0/0/0
30–60 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0
60–90 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0
90–100 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0 0/0/0
Number of recorded events: 19
G 21

Table C4.3 Number of voltage dips – LUB (L1/L2/L3)

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 0/0/3 2/2/4 0/0/0 0/0/0 0/0/0 0/0/0


15–30 1/0/11 3/2/0 0/0/0 0/0/0 0/0/0 0/0/0
30–60 0/1/2 0/1/2 0/0/0 0/0/0 0/0/0 0/0/0
60–90 1/0/4 0/0/7 0/0/1 0/0/7 0/0/11 0/0/5
90–100 1/0/1 0/0/0 0/0/0 0/0/0 0/1/0 0/0/0
Number of recorded events: 74

Substation Threshold value


90 % 80 % 70 % 60 %
SKA 19 6 6 6
WAN 44 35 24 21
LUB 74 59 45 42

Figure C4.2 Dependence of the number of dips on the selected threshold value, which defines the
disturbance

The dependence of the number of dips on the selected threshold value, which defines
the disturbance, is presented in Figure C4.2. For each location it can be seen that there is a
reduction in the number of disturbances with a decrease in the threshold voltage.

C4.1.3 Aggregation procedures


Analysis shows that the use of phase and time (1 and 3 min) aggregation significantly
reduces the number of disturbances. This does not concern the substation LUB, where a
particularly large number of disturbances occurred in a single phase (L3) – see Table C4.4,
Table C4.5 and Table C4.6.
Figure C4.3 shows a comprehensive comparison of the effect of various types of
aggregation on the number of voltage dips for given measurement points.
G22

Figure C4.3 Dependence of the number of dips on the selected method of aggregation

Table C4.4 Substation WAN


1 min aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 4 0 0 0 0 0
15–30 2 2 2 2 0 0
30–60 1 0 0 1 0 1
60–90 1 0 0 0 0 0
90–100 0 1 0 0 4 4
Number of recorded events: 25

3 min aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 4 0 0 0 0 0
15–30 2 2 2 2 0 0
30–60 1 0 0 1 0 1
60–90 0 0 0 0 0 0
90–100 0 0 0 0 3 4
Number of recorded events: 23
G 23

Phase aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 3 0 0 0 0 0
15–30 5 5 1 0 0 0
30–60 4 1 1 0 0 0
60–90 3 0 0 0 0 0
90–100 6 0 0 2 6 1
Number of recorded events: 38

Table C4.5 Substation SKA


1 and 3 min aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 3 0 0 2 0 0
15–30 2 6 0 2 0 0
30–60 0 0 0 0 0 0
60–90 0 0 0 0 0 0
90–100 0 0 0 0 0 0
Number of recorded events: 15

Phase aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 5 0 0 0 0 0
15–30 3 4 1 0 0 0
30–60 0 0 0 0 0 0
60–90 0 0 0 0 0 0
90–100 0 0 0 0 0 0
Total of recorded events: 13
G24

Table C4.6 Substation LUB


1 min aggregation
Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 1 3 0 1 2 0
15–30 9 1 0 1 0 0
30–60 3 1 2 0 0 0
60–90 1 5 1 1 6 5
90–100 1 1 0 0 1 0
Number of recorded events: 46

3 min aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 0 2 0 1 2 0
15–30 9 1 0 2 0 0
30–60 3 1 2 0 0 0
60–90 0 6 1 1 4 2
90–100 1 1 0 0 1 0
Number of recorded events: 44

Phase aggregation

Dips (%) 10–100 ms 100–500 ms 500 ms to 1 s 1–3 s 3–20 s 20 s to 1 min

10–15 3 6 0 0 0 0
15–30 12 5 0 0 0 0
30–60 3 3 0 0 0 0
60–90 5 7 1 7 11 5
90–100 2 0 0 0 1 0
Number of recorded events: 71

C4.2 SELECTED CONTRACTS AND NATIONAL


REGULATIONS

The examples refer to three well-known power quality contracts.


G 25

C4.2.1 USA (based on [22])


In this contract the concept of qualifying sag has been defined. A voltage dip is referred to
as the qualifying sag when the r.m.s. value of any of the three phase voltages is lower than
75 % of the nominal voltage.2 The minimum duration of a voltage dip has not been defined.
Thus the provisions of the contract comprise all cases of disturbances, with the exception
of voltage dips associated with protection systems operation, and voltage dips which occur
on unloaded lines and therefore are causing no effects.3
The deepest voltage dip occurring within a 15-minute time interval is regarded as the
qualifying sag. The observation interval starts at the instant of occurrence of the first dip and
ends at the instant of the last voltage dip ending, or after a time of 15 minutes has elapsed.
Voltage dips which occur after this time are treated as belonging to the next observation
interval. The further procedure consists of the aggregation of this way of obtaining the
results of measurement. For example, according to the contract, for a single customer when
measurements are taken on several busbars, a program seeks for the worst case (the deepest
dip). This kind of data processing, which may be referred to as time (15 minutes) and spatial
(according to location) aggregation, significantly reduces the number of dips with respect
to the number of non-aggregated qualified dips.
If the residual voltage of one out of the three phase voltages drops below 75 % of the
nominal value then, for contractual purposes, the so-called sag score4 comes into effect:

1 − UA + UB + UC /3

It is equal to the average voltage dip on the three phases. For instance, for UA = UB =
UC = 0722 (pu) the sag score = 0278; for UA = 0818 UB = 0574 UC = 0823 the sag
score = 0262.5 If instead of a voltage dip, a voltage swell above 1 pu occurs on one or
two phases as a result of, say, the neutral point potential shift, then the value 1 is assumed
for calculation of the sag score. Thus all values of the sag score belong to the interval:
0.0833–1. The value 0.0833 applies to the case where UA = 075 UB = UC = 1. The greater
the value of the sag score index, the more severe the disturbance.
Also the concept of the so-called sag score target was introduced. This index is
determined for a customer who has many points of recording voltage dips. It is the sum
of sag scores for all measurement points, which is compared to the value set forth in the
contract. Mutual financial commitments are determined at the end of each year if the sag
score targets of a given customer exceed the value agreed upon by the parties to the contract.
If, for example, the sum of the sag scores is 3.28 and the limit value in the contract is 3,
the difference of 0.28 is multiplied by the agreed compensation rate.

2
This value has been chosen based on the new ITIC curve. Also customers have adopted this value as critical for
their equipment.
3
Whether the supplying line is loaded or not is decided from the current measurement at the instant of a voltage dip
occurrence. If the current value is lower than a certain level, the line is considered a hot reserve. The measurement
of current often helps to settle who caused the dip: the customer or the supplier?
4
The r.m.s. voltage values are assumed constant during the considered voltage dip. The sag score can also be a
function of time if phase voltage r.m.s. values are assumed to vary with time.
5
In the case of supply interruption, contractual provisions relevant to this disturbance are applicable. There are
two separate contracts, pertaining to voltage dips and supply interruptions.
G 26

C4.2.2 France [44],[57]


In the Emerald Contract (EdF),6 changes in r.m.s. voltage value with amplitude contained
in the range 10–99 % and with a duration of 10 ms to 3 min are regarded as voltage dips.
The threshold values adopted in the contract are: dip duration longer than 600 ms, depth
greater than 30 %, respectively. Voltage dips which successively occur in times shorter than
100 ms are considered a single disturbance.
According to the contract, a short interruption occurs when the residual voltages of the
three line-to-line voltages are simultaneously lower than 10 % for a duration greater than
1 s and shorter than 3 min.
The number of interruptions that occur within one year is a subject of the contract.
Table C4.7 gives numbers of short supply interruptions, which have occurred on systems
with a voltage higher than 50 kV. The supplier guarantees that these values will not be
increased in the future.
Under the Emerald Contract EdF agrees not to exceed the number of seven short
interruptions per year for customers with a declared voltage above 50 kV. There is an option
of defining the limit value for the sum of short and long supply interruptions.
At the customer’s request, where technically practicable and financially feasible, the
supplier may guarantee better supply conditions on individually negotiated terms.
Figure C4.4 shows the annual cumulative numbers of long and short supply interrup-
tions for 3000 feed points on French HV and LV systems. A global trend toward better
supply quality, which results from company decisions taken in the early 1980s, continued in
the years 1988–1998. When the period of 1990–1995 is considered, the effectiveness of these
actions might be questionable. This situation has resulted from a period of an exceptional
number of thunderstorm days during this time. Figure C4.4 illustrates two theses:

1. An abrupt improvement of power quality factors should not be expected; such a situation
never happens in practice. The time constant of changes in the quality of power supply
is extremely long.
2. The indices characterizing voltage dips are very sensitive to atmospheric phenomena.

Table C4.7 The number of short supply interruptions on


HV system, according to French data [44]

1996 1997 1998


Short interruptions 5 5 5

6
As stated in [45], the number of long and short supply interruptions was the most difficult obstacle to reaching
agreement between the parties. Many customers have had no interruptions over several years. Therefore, the
provision that allows for the possibility of a certain number of interruptions is regarded as a deterioration of the
quality of supply. This is one of the reasons for introducing customized contracts. In such a case, a provision
allowing for one interruption over three years has been introduced. Usually the number of disturbances experienced
by the customer over the last 4–5 years has been set as the permissible value.
G 27

Figure C4.4 Cumulative numbers of long and short supply interruptions on HV and LV
systems [45]

C4.2.3 South Africa [50],[51],[66]


The duration of a voltage dip is the time measured between the instant at which the r.m.s
voltage value falls below 90 % of the declared voltage and the instant at which it rises above
90 % of the declared value. The amplitude of a voltage dip equals the maximum voltage
change during the disturbance, and its duration is the maximum voltage dip duration for the
most disturbed phase.
A South African user specification [50] [51] contains an interesting classification table
for voltage dips that may be considered when doing an expert evaluation (Table C4.8).
The Y-type area reflects dips that are expected to occur frequently in typical HV and
MV systems, and against which customers should protect their plant. The X-type areas (X1
and X2) reflect normal HV protection clearance times and hence a significant number of
events in this area. Customers should attempt to protect against at least X1-type dips. The
T-type area reflects close-up faults, which are not expected to happen too regularly – and

Table C4.8 Characterization of depth and duration of voltage dips [51]

Range of dip depth Range of residual Duration t


U (expressed as voltage Ur (expressed
a % of Ud ) as a % of Ud ) 20 < t ≤ 150 ms 150 < t ≤ 600 ms 06 < t ≤ 3 s

10 < U ≤ 15 90 > U ≥ 85
Y
15 < U ≤ 20 85 > U ≥ 80
20 < U ≤ 30 80 > U ≥ 70 Z1
30 < U ≤ 40 70 > U ≥ 60 X1 S
40 < U ≤ 60 60 > U ≥ 40 X2 Z2
60 < U ≤ 100 40 > U ≥ 0 T
Note: In the case of measurements on LV systems it is acceptable to set the dip threshold at 0.85 pu.
G28

which a utility should specifically address if excessive. S-type dips are not as common
as X- and Y-type events, but may occur where impedance protection schemes are used,
or where voltage recovery is delayed. Z-type dips are very uncommon in HV systems
(particularly Z2-type events), as this generally reflects problematic protection operation
[25],[26]. Voltage dips with a longer duration than 3 s are considered in [50] as undervoltage
events. This standard contains, however, no classification of undervoltage events. Based
on the classification in [50] voltage dips may be presented as total numbers that occur
differentiated on the seven categories Y, X1, X2, T, S, Z1 and Z2.
The South African standard gives limits for voltage dips in the form of a maximum
number of voltage dips per year for defined ranges of voltage dip duration and retained
voltage, designated as dip window categories (Table C4.8). All voltage dips caused by force
majeure or caused on the customer’s side (short circuits, large drive starts, etc.) are excluded
from this number. According to the document it is expected, for most of the time and most
customers, that the number of dips will be considerably less than the numbers set as the
minimum standards.

BIBLIOGRAPHY
[1] Ahang L. D., Bollen M., Characteristics of voltage dips (sags) in power systems. IEEE Trans-
actions on Power Delivery, vol. 15, no. 2, pp. 827–832, 2000.
[2] Amentagui J., Power quality measurement & control procedures in Spain. CIRED 2003, Round
table on Power Quality at the Interface T&D.
[3] Ball R. F., Thoughts on voltage dip severity index. The National Grid Company plc.
[4] Ball R. F., Voltage dips: indices and objectives. The National Grid Company plc.
[5] Beaulieu G., Borloo G., Bollen M., Koch R., Malgarotti S., Mamo X., Recommending power
quality indices and objectives in the context of an open electricity market. CIGRE/IEEE-PES
on Quality and Security of Electric Power Delivery Systems, Montreal, 7–10 October 2003.
[6] Beaulieu G., Bollen M., Koch R., Malgarotti S., Mamo X., Sinclair J., Power quality indices
and objectives for MV, HV and EHV systems. 17th International Conference on Electricity
Distribution, CIRED, Barcelona, 12–15 May 2003.
[7] Bollen M., Characterization of voltage sags experienced by three-phase adjustable-speed drives.
IEEE Transactions on Power Delivery, vol. 12. no. 4, pp. 1666–1671, 1997.
[8] Bollen M. H. J., Understanding power quality problems – voltage sags and interruptions, IEEE
Press Series on Power Engineering, 2000.
[9] Bollen M., Time aggregation of voltage dips. Discussion in the CIGRE Working Group.
[10] Bollen M., Comparision of the different indices. Discussion in the CIGRE Working Group.
[11] Bollen M. H. J., Ongoing standard work on statistical presentation of voltage dips. Discussion
in the CIGRE Working Group.
[12] Bollen M. H. J., Goossens P., Robert A., Assessment of voltage dips in MV-networks: deduction
of complex voltage from the measured rms-voltages. CIRED, Barcelona, 2003.
[13] Bollen M., Sabin D., Thallam R., Voltage-sag indices – recent developments in IEEE P1564
Task Force. CIGRE/IEEE-PES on Quality and Security of Electric Power Delivery Systems,
Montreal, 7–10 October 2003.
[14] Bollen M., Sabin D., Thallam R., Sannino A., Voltage sag indices: recent developments in
IEEE P1564 Task Force. EPRI PQIG, Paris, 2003.
G 29

[15] Brooks D. L., Gunther E. W., Sundaram A., Recommendations for tabulating rms variation
disturbances with specific reference to utility power contracts. CIGRE 36.05/CIRED 2 CC02
9923.
[16] Conrad L., Little K., Griff G., Predicting and preventing problems associated with remote fault
clearing voltage dips. IEEE Transactions on Industry Applications, vol. 27, no. 1, pp. 167–172,
1991.
[17] Davenport F.W.T., Voltage dips and short interruptions in medium voltage public electricity
supply systems. UNIPEDE/DISDIP Report, 1990.
[18] Delmo de Macedo Corriera et al., Pilot project for evaluation of the sag performance of
some Brazilian network busbars. CIGRE/IEEE-PES on Quality and Security of Electric Power
Delivery Systems, Montreal, 7–10 October 2003.
[19] Desquilbert G., Foucher C., Fauquembergue P., Statistical analysis of voltage dips. 3rd Inter-
national Conference on Power Quality: End-Use Applications and Perspectives, 24–27 October
1994, Amsterdam.
[20] Dettlof A., Sabin D., Power quality performance component of the special manufacturing
contracts between power provider and customer. 0-7803-6499-6/2000 IEEE.
[21] Didden M., Voltage sags in continuous process-case study (5.5.1). Power Quality and Utilisation
Guide, Leonardo ENERGY (www.lpqi.org).
[22] Dugan R., McGranghan M.F., Santoso S., Beaty H.W., Electrical power systems quality,
McGraw-Hill, New York, 2002.
[23] EN 50160, Voltage characteristics of electricity supplied by public distribution systems.
[24] Geiveldinger C. et al., New power quality contracts in France. PQA, Amsterdam, 1994.
[25] Gosbell V. J., Robinson D., Barr R., Smith V. W., How should power quality be reported?
Electricity 2002 – Winners and Losers from Reforms and Innovations.
[26] V. J. Gosbell, D. Robinson and S. Perera, The analysis of utility voltage sag data. Proceedings
of the International Power Quality Conference, Singapore, October 2002, pp. 479–490.
[27] Häger M., Wahlström B., Friman E., Limits and responsibility sharing with regard to power
quality for the Swedish 220- and 400- transmission system. STRI Report S98–171.
[28] Higgings M., Mansoor A., Sundaram A., Understanding premium power grades. Electrical
Power Quality and Utilisation, vol. 2, no. 7, 2001.
[29] IEEE Standard 493, Recommended practice for the design of reliable industrial and commercial
power systems.
[30] IEEE Standard 1159, Recommended practice for monitoring electric power quality.
[31] IEEE Standard 1346, Recommended practice for evaluating electric power system compatibility
with electronics process equipment.
[32] IEEE Standard 1366, Guide for electric power distribution reliability indices.
[33] IEEE Orange Book.
[34] IEC 61000-2-2, Electromagnetic compatibility (EMC) – Part 2-2: Environment compatibility
levels for low-frequency conducted disturbances and signaling in power supply systems.
[35] IEC 61000-2-5, Classification of electromagnetic environments.
[36] IEC 61000-2-8, Voltage dips and short interruptions on public supply systems with statistical
measurement results.
[37] IEC 61000-2-12, Electromagnetic compatibility (EMC) – Part 2-12: Environment compatibility
levels for low-frequency conducted disturbances and signaling in public medium-voltage power
supply systems.
[38] IEC 61000-4-11, Electromagnetic compatibility (EMC) – Testing and measurement techniques –
Voltage dips, short interruptions and voltage variation immunity tests.
[39] IEC 61000-4-30, Electromagnetic compatibility (EMC) – Part 4-30: Testing and measurement
techniques – Power quality measurement methods.
G
30

[40] IEC 61000-4-34, Electromagnetic compatibility (EMC) – Part 4-34: Testing and measuring
techniques – Voltage dips, short interruptions and voltage variations immunity tests for equip-
ment with input current more than 16 A.
[41] IEC 61000-6-1, Electromagnetic compatibility (EMC) – Part 6-1: Generic standards – Immunity
for residential, commercial and light-industrial environments.
[42] IEC 61000-6-2, Electromagnetic compatibility (EMC) – Part 6-2: Generic standards – Immunity
for industrial environment.
[43] IEC 60947-4-1, Low voltage switchgear and control gear – Part 4-1: Contactors and motor-
starters – Electromechanical contactors and motor starters.
[44] International Telecommunication Union, Geneva, 1989, Emerald Contract for the supply of
electric at the Green Rate, EdF (Electricité de France).
[45] Javerzac J. L., Contracting the quality of electricity: the French experience, 0-7803-64499-
6/2000, IEEE.
[46] Matusz G., Maj T., Hanzelka Z., Loziak W., Voltage dips and short supply interruptions in
contracts for the electric power supply from high voltage transmission systems. Power Quality
PCIM Europe, Nurnberg, 20–22 May 2003.
[47] McGranaghan M. F., Effects of voltage sags in process industry applications. Stockholm Power
Technical Conference, Stockholm, Sweden, 18–22 June 1995.
[48] McGranaghan M., Gunther E., The economics of custom power. Power Quality and EMC in
Power Quality, Colloquium of Czech National Committee and 36 Study Committee of CIGRE,
Dept. of Power Engineering, CTU Prague, 28 September 2001, Prague.
[49] Mueller D., Understanding power quality measurements. Power Quality, August 1999.
[50] NRS 048-2, Electricity supply – Quality of supply. Part 2: Voltage characteristics, compatibility
levels, limits and assessment methods. Published in the Republic of South Africa by the South
African Bureau of Standards (http://www.sabs.co.za).
[51] NRS 048-4, Electricity supply – quality of supply. Part 4: Application guidelines for utilities.
Published in the Republic of South Africa by the South African Bureau of Standards.
[52] Olguin G., Stochastic assessment of voltage dips caused by faults in large transmission system.
Department of Electric Power Engineering, Chalmers University of Technology, Goteborg,
Sweden, 2003.
[53] Pazos F. J., Measuring voltage dips oriented towards power quality contracts. CC02 9837, 1998.
[54] Pierz P., Rosołowski E., Quality of electric power in industrial plants (in Polish). Elektroinsta-
lator 9/2000.
[55] Pohjanheimo P., A probabilistic method for comprehensive voltage sag management in power
distribution systems. Doctoral Thesis, Helsinki University of Technology, Power System Labo-
ratory, 2003.
[56] Power quality indices and objectives, Joint Working Group CIGRE C4.07/CIRED.
[57] Robert A., Hoeffelman J., De Jaeger E., CIRED 2001 – Session 2: Power Quality & EMC.
[58] SEMI F47-0999, New standard – specification for semiconductor processing equipment voltage
sag immunity.
[59] Smith J., The impact of voltage sags on industrial plant loads. Paper C-24, PQA’91, First
International Conference on Power Quality: End-Use Applications and Perspectives, Paris 1991,
pp. 171–178.
[60] Stephens M., PQ in continuous manufacturing (1.5). Power Quality and Utilisation Guide,
Leonardo ENERGY (www.lpqi.org).
[61] Thallam R. S., Power quality indices based on voltage sag energy values. Power Quality
Proceedings, September 2001.
[62] The 3rd CEER Benchmarking Report on Quality of Electricity Supply – C05-QOS-0103,
December 2005.
G 31

[63] Transmission Power Quality Benchmarking Methodology. EPRI Final Report, December 2000.
[64] Understanding premium power grades. EPRI Final Report, November 2000.
[65] Voltage dips measurement. UIEPQ-9559, October 1995.
[66] Voltage sag indices – Draft 4, Working Document for IEEE P1564, August 2003.
[67] www.lpqi.org.

Вам также может понравиться