SIMHAPURI ENERGY PRIVATE LIMITED

PROJECT : 2 X 150 MW - PHASE-I - THERMAL POWER PROJECT

C&I WORK PROGRESS DETAILS


Dt: 14.07.2011

Area

Status 100% completed. Control Panels erection

Works

Remarks

Turbine-1

_ Main Tray work completed. Tray work 75% completed. Sub tray work Under progress. Mech. Clearance is not JB erection 40% completed. available. Instruments calibration Instruments Erection Work started. (0%) work started on 13.07.2011. Cable laying 40% completed. Work under progress. Instruments not yet Commissioning Not started. (0%) errected BMS Panels reached Boiler Field control Panels Work under field area.O2 analyzer erection progress. frame work completed. Tray work

Main tray work completed. 70%completed. Sub tray work under progress. JB structures mounting under progress.10.5 meter JB frames erection 75% completed. below no clearance from mech Dept. Boiler-1 Calibration under progress Instruments Erection Not started. (0%)and no clearance from mech.. As per specification Cables not received at site. Single Cable laying 5% completed pair cable laying underprogress. Instruments erection and Commissioning Not started. (0%)cable laying to be completed. Stacker and reclaimer works Control Panels erection0% completed. 8 under progress. Tray work 65% completed. Remaining under progress JB erection 50% completed. Remaining under progress CHP Instruments Erection 52% completed Remaining under progress Cable laying 30% completed. Remaining under progress Instruments erection and Commissioning Not started. (0%)cable laying to be completed. Control Panels erection started. (0%)Civil work under progress. Not Tray work Not started. (0%)Civil work under progress. JB erection Not started. (0%)Civil work under progress. Lime Handling System Instruments Erection Not started. (0%)Civil work under progress. Cable laying Not started. (0%)Civil work under progress.

Lime Handling System Commissioning Not started. (0%)Civil work under progress.

Control Panels erection 80% completed. PLC panels has to erect. 250 mtrs maintray completed out of 600 mtrs. Tray work 29% completed. 250mtrs sub tray to be done. Not started. (0%)Front available. Intake & RO plantJB erection Instruments Erection Not started. (0%)Calibration due. Cable laying Not started. (0%)Tray work to be completed. Commissioning Not started. (0%) Instruments erection and cable laying to be complete.

PLC panels are available at Control Panels erection started. (0%)site for erection. Front end Not is also there. Tray work DM Plant JB erection 75% completed. sub tray work is pending. Not started. (0%)

Material not yet received at site. Instruments Erection Not started. (0%)Calibration due. Material not yet received at Cable laying Not started. (0%) site. Instruments erection and Not started. (0%)cable laying are to be completed. 100% completed. Control Panels Erection _ 50% completed work from ABB scope. Remaining 50% Tray work 50% completed. will be start from WIPL scope. JB erection Not started. (0%)No clearance. Instruments Erection Not started. (0%)Calibration due. Cable laying Not started. (0%)Tray work is erection and Instruments to be completed. cable laying are to be Commissioning Not started. (0%) completed. Commissioning Tray work JB erection 85% completed. Main tray work is pending

RCW

100% completed. _ Front available for vibration Cooling Towers-1Instruments Erection 25% completed. switches. Cable laying 100% completed. _ Instruments erection is to Commissioning Not started. (0%) be completed. Control Panels erection Under Progress _ Tray work 80% Completed Console work pending. Substation Ethernet- 60% RCW,AHP pending Automation Cable laying FO-Not started. Material received at site. System Commissioning Not started. _

AHP-1

ESP-1

Control Panels erection completed _ Tray work Not started. (0%)Civil work under progress. JB erection Not started. (0%)Civil work under progress. Instruments Erection Not started. (0%)Civil work under progress. Cable laying Not started. (0%)Civil work under progress. Commissioning Not started. (0%)Civil work under progress. Tray work 98% completed. _ JB erection 100% completed. _ Instruments will be erected Instruments Erection Not started. (0%)after completion of inside field work. Cable laying will be started Cable laying Not started. (0%)after completion of thermal insulation work. Instruments erection and Commissioning Not started. (0%)cable laying to be completed.

Not started. (0%)Civil front not available. Tray work Not started. (0%)Civil front not available. Compressor & JB erection Dryer House Instruments Erection Not started. (0%)Civil front not available. Cable laying Not started. (0%)Civil front not available. Commissioning Not started. (0%)Civil front not available. Control Panels erection completed _ Tray work Not started. Civil front not available. JB erection Not started. Civil front not available. CEMS-1 Instruments Erection Not started. Civil front not available. Cable laying Not started. Civil front not available. Commissioning Not started. Civil front not available. 100% Completed Control Panels erection _ Tray work 100% Completed _ Earthing JB erection Under Progress RCW Pump House pending DCS-1 Modules Mounting Not Started _ Cable laying 20% Completed _ Cable termination 3% Completed _ Commissioning Not Started _

SIMHAPURI ENERGY PRIVATE LIMITED


PROJECT : 2 X 150 MW - PHASE-I - THERMAL POWER PROJECT

C&I WORK PROGRESS DETAILS


Dt: 14.07.2011

Area

Works

Status

Remarks

Turbine-2

100% completed. Control Panels erection _ Tray work 70% completed. JB erection 30% completed. Due to insufficient man Instruments Erection Not started. (0%) power, The work in turbine2 is slow. Cable laying 37% completed. Commissioning Not started. (0%) Field control Panels Not started. Mech. Front not available. erection Main tray work under progress. (Main tray Tray work 40%completed. length:498 m + Sub tray length: 50 m)
JB frames erection Structures 10 structures are ready to fabrication erect. under progress .

Boiler-2

Calibration under progress Instruments Erection Not started. (0%)and no clearance from mech.. As per specification Cables Cable laying Not started. (0%) not received at site. Instruments erection and Commissioning Not started. (0%)cable laying to be completed. Main tray connecting work Tray work 80% completed. is pending. JB erection 100% completed. _ Front available for vibration Instruments Erection 25% completed. switches. Cooling Towers-2 Cable laying 100% completed. _ Instruments erection and Commissioning Not started. (0%)cable laying are to be completed. Tray work Not started. (0%)Civil front not available. JB erection Not started. (0%)Civil front not available. Instruments Erection Not started. (0%)Civil front not available. AHP-2 Cable laying Not started. (0%)Civil front not available. Commissioning Not started. (0%)Civil front not available.

Tray work JB erection

ESP-2

CEMS-2

DCS-2

70% completed. Trench work pending 100% completed. _ Instruments will be erected Instruments Erection Not started. (0%)after completion of inside field work. Cable laying will be started Cable laying Not started. (0%)after completion of thermal insulation work. Instruments erection and Commissioning Not started. (0%)cable laying to be completed. Tray work Not started. (0%)Civil front not available. JB erection Not started. (0%)Civil front not available. Instruments Erection Not started. (0%)Civil front not available. Cable laying Not started. (0%)Civil front not available. Commissioning Not started. (0%)Civil front not available. 1 Control Panels erection 00% Completed _ Tray work 100% Completed _ Earthing JB erection Under Progress RCW Pump House pending. Module mounting will be Modules Mounting Not Started start after completion of Inter panel cable laying. Cable laying 10% Completed _ Cable termination Under Progress _ Commissioning Not Started _