Академический Документы
Профессиональный Документы
Культура Документы
No I Description MAIN ESTIMATE Road Approaches: Carriage way / Total Width of flyover Width of Foot-path Type of Foundations Trestle portion side -1 135m @ Trestle portion side -2 380m @ Ret. Wall portion side -1 165m @ Ret. Wall portion side -2 145m @ Amount (Lakhs)
II
SUB ESTIMATE 1. Filling Between retaining walls, GSB, WMM & BT etc. Side -1 165m @ 0.631lakhs/RM Side -2 145m @ 0.631lakhs/RM 2. Forming of Service roads 850m @ 0.35 lakhs/RM 3. Provision for Junction Improvements, medians, Rotary etc. 4. Provision for Storm water drains and foot-paths/CD structures 5. Provision for Stucco Plastering SUB TOTAL 6. Escalation Charges @ 7.5% LUMP SUM PROVISIONS 1 Land acquisition Extent of Land (Approximately) Guideline Value
III
2 Shifting of Electrical posts, water mains and sewage mains etc 3 Provision for Lighting arrangements 4 Provision for variation in depth of footings 5 Disposal of Surplus excavated earth Provision of sign boards, caution boards, information boards and 6 road furniture like mega lux, cats eys road marking etc. 7 Provision for Pier protection and fencing 8 Provision for Rain water Harvesting 9 Provision for Opening ceremony and Photographs etc. Provision for investigation charges, for preparation of estimate, 10 tender documents & advertisement charges @ 1.5% 11 Provision for construction of Pylons 12 Provision for white wash, colour wash, zebra painting 13 Contribution to Labor welfare fund @ 0.3% 14 Quality Control charges @ 1% 15 Petty supervision Charges @ 2.00% 16 Contingences @3.00% TOTAL Say
35.30 5.00 5.00 7.06 23.53 47.06 70.59 3499.82 35.00 Crores
Name of Work: Construction of Flyover at Government Hospital Junction in Erode Town Rough cost Estimate Amount Sl.No Description (Lakhs) I MAIN ESTIMATE Road Approaches: No of lanes 2+2 Carriage way / Total Width ofFour lane) lane) flyover( Two Bustand road & Perundurai road 17.2m E.V.N road 14.2m Width of Foot-path : Nil Type of Foundations : Isolated Open Trestle portion side -1 270m 2.00 lakhs/RM 1215 Trestle portion side -2 140m 2.00 lakhs/RM 630 Trestle portion side -3 170m 2.00 lakhs/RM 680 Flat Slab 30m 2.00 lakhs/RM 135 Ret. Wall portion side -4 2x60+2x50m 0.57lakhs/RM 125.40 Ret. Wall portion side -2(E.V.N road) 2x50m 0.37lakhs/RM 37.00 II SUB ESTIMATE 1. Filling Between retaining walls, GSB, WMM & BT etc. Side -4 2x60+2x50m 220m @ 0.731lakhs/RM 160.82 Side -2 2x50m 100m @ 0.631lakhs/RM 63.10 2. Forming of Service roads 1800m @ 0.35 lakhs/RM 630.00 3. Provision for Junction Improvements, medians, Rotary etc. 50.00 4. Provision for Storm water drains and foot-paths/CD structures 165.00 5. Provision for Stucco Plastering 25.00 SUB TOTAL 3916.32 6. Escalation Charges @5% 195.82 III LUMP SUM PROVISIONS 1 Land acquisition Extent of Land (Approximately) 65055 Sq.ft Guideline Value @ 0.025 lakhs/Sq.ft 1626.38 2 Shifting of Electrical posts, water mains and sewage mains etc 45.00 3 Provision for Lighting arrangements 40.00 4 Provision for variation in depth of footings 25.00 5 Disposal of Surplus excavated earth 20.00 Provision of sign boards, caution boards, information boards and road 6 furniture like mega lux, cats eys road marking etc. 20.00 7 Provision for Pier protection and fencing 20.00 8 Provision for Rain water Harvesting 10.00 9 Provision for Opening ceremony and Photographs etc. 10.00 investigation charges, for preparation of estimate, tender 10 documents & advertisement charges @ 1.5% 39.17 11 Provision for construction of Pylons 10.00 12 Provision for white wash, colour wash, zebra painting 10.00 13 Contribution to Labor welfare fund @ 0.3% 11.75 14 Quality Control charges @ 0.50% 19.59 15 Petty supervision Charges @ 1.00% 39.17 16 Contingences @1% 39.17
TOTAL Say
1480
A m o u n t
L(m) B(m) D(m) Qty 1 Earth work excavation in all classes of soils for Retaining walls Abutments, wings and column piers.(up to 4m depth)
Unit
Amount (Rs)
3 6 70 2
Total say 25000 2 Earth work excavation in kankar not requiring blasting for Retaining walls Abutments, wings and column piers.Below 4m Abutment Wings Piers R.Wall 3 6 70 2 16.20 6.60 7.30 215.00 5.20 4.80 7.30 4.50 Total Say 3 Benching Hardrock of 10cm thick 16.20 Abutment 3 6.60 Wings 6 7.30 Piers 70 215.00 R.Wall 2 5.20 4.80 7.30 4.50 0.10 0.10 0.10 0.10 1.00 1.00 1.00 0.50
102 ###
5,30,400
25.27 19.01 373.03 193.50 Total 610.81 cum Say 620 cum 4 Vibrated cement concrete of grade M10 for leveling course. 16.20 5.20 0.10 25.27 Abutment 3 6.60 4.80 0.10 19.01 Wings 6 7.30 7.30 0.10 373.03 Piers 70 215.00 4.50 0.10 193.50 R.Wall 2 Total 610.81 cum say 620 cum
200 ###
1,24,000
2300 ###
14,26,000
C / O### 5 Vibrated cement concrete of grade M30 for Retaining walls (Below sill level) B / F ### 215.00 3.75 0.50 806.25 cum R.Wall 2 say 825.00 4500 ###
Vibrated cement concrete of grade M30 for Retaining walls (Above sill level) 215.00 1.60 3.00 2064.00 cum R.Wall 2 say 2100.00 cum
4500 ###
94,50,000
7 Vibrated cement concrete of grade M30 for Abutments and Wings (Below Sill level) : as per calculation say
320.00 cum
4500 ###
14,40,000
8 Vibrated cement concrete of grade M30 for Abutments and Wings(Above Sill level) as per calculation 255 cum say 260 cum 9 Vibrated cement concrete of grade M35 for Foundation of column piers. 7x7+(1.8 Piers 1715.00 cum 70 x1.8)+ 7.00 7.00 0.50 (7x7+1. Trapizodal 1512.00 8x1.8)x(1 portion 70 .0/3) 50.04 0.30 cum Total 3227.00 cum say 3300 cum 10 Vibrated cement concrete of grade M35 for Column Piers Piers 700.07 cum 60 1.18 1.50 6.60 Piers(centre) 152.74 cum 10 1.18 1.50 8.64 Total 852.81 cum say 860 cum 11 Providing and fixing PVC Seepage pipes to Drain the back fill. Abutment Wings 3 3 18 24 Total 54 Nos 72 Nos 126 Nos :
5000 ###
13,00,000
4500 ###
1,48,50,000
4500 ###
38,70,000
say
126 Nos
12 Vibrated Reinforced Cement concrete M 30 for Bed Block cum Dirt wall over Abutments Bed block Dirt wall 3 6 14.20 9.35 0.90 0.28 Total say 13 Supply and fixing of Electrometric rubber bearing of size (450x250x39 mm size) 0.30 1.04 11.50 cum 16.32 cum 27.82 cum 30 cum
6300 ###
1,89,000
52650 ccm 1842750 ccm 1895400 ccm Total say 1895500 ccm 14 Vibrated cement concrete of grade M30 for Capping Beam 1228.5 cum Piers 35 13 1.8 1.5 say 1250 cum 15 Vibrated cement concrete of grade M30 for T- Beam and Cross Beams Span (From 1710.72 Estimate) 33 51.84 cum say 1750 cum 16 Vibrated cement concrete of grade M30 for Deck Slab Span (From 2330.46 Estimate) 33 70.62 cum say 2400 cum 17 Vibrated Cement concrete of grade M30 Design mix using of 25mm, 12mm and 6mm for Wearing coat. 12 420 45.00 45.00 25.00 25.00 3.90 3.90 Span (From Estimate) for Approach Slab 33 3 15.49 3.50 12.00 13.20 6134.04 Sqm 138.60
Abutment Piers
### 1.2
22,74,600
4700 ###
58,75,000
5800 ###
1,01,50,000
5400 ###
1,29,60,000
Total 6272.64 say 6300 Sqm 18 Supplying and installation of copper seal expansion joint system 36 14.20 say 19 Supply and fixing of Drainage spouts 511.20 RM 520 RM
300 ###
18,90,000
7000 ###
36,40,000
spouts
33
6 say
20
Vibrated Reinforced Cement Concrete M40 for Crash bariers 539.00 cum 2 770 0.50 0.70 say 540 cum 21 Providing filter media behind Abutment And return wall for 600mm thick Abutment 22 Filling behind Abutments and wings with clean gritty gravel Abutment 400 cum 23 Vibrated Cement concrete of Grade M15 (Nominal Mix 1:2:4) for Base course Below approach slab. 54 cum 24 Vibrated Reinforced Cement concrete M 30 for Approach Slab 54 cum 25 Vibrated reinforced Cement concrete M 25 for Pedestal. 2*6*35 420 0.55 0.75 0.3 3*6 18 0.55 0.75 0.3 Total say 225 cum
620 ###
1,39,500
193.75 ###
77,100
2900 ###
1,56,600
4300 ###
2,32,200
4600 ###
2,50,700
Supply and fabrication of Fe 415 steel required for all RCC items of works for 26 TOR Steel. 1200 MT 1 Provision for Service road 1700m Provision for centre media ,Approch road and traffic island Over the bridge 54455 ### ### 6,48,26,400 14,55,42,460 1,00,00,000 Sub Total ###
3 Provision for junction improvments 4 Provisions for foot path with drain 5 Escalation Charges @5% P.A - 2 Years Lumpsum Provisions
6 provision for shifting of electrical post 7 Provision for shifting of telephone lines 8 Provision for water mains 9 Provision for Lighting arrangements 10 Provision for sewage mains etc 11 Provision for variation in depth of Foundations 12 Provision for Pavement bridge portion 13 Disposal of Surplus excavated earth 14 Provision for Land Acquation and Commensaction to the building 15 Provision of sign boards, caution boards, information boards and road furniture like mega lux, cats eys road marking etc. 16 Provision for Pier protection and fencing 17 Provision for Rain water Harvesting 18 Provision for Opening ceremony and Photographs etc. 19 Provision for construction of Pylons 20 Provision for white wash, colour wash, zebra painting 21 Contribution to Labor welfare fund @ 0.3% 22 Quality Control charges @1% 23 Provision for investigation charges, for preparation of estimate, tender documents @ 1% 24 Advertisemnet charges 25 Petty supervision Charges & contingences @ 2.5% Total
### ### ### ### ### ### ### ### ### ### ###
5,00,000 23,50,00,000 10,00,000 10,00,000 2,00,000 3,00,000 1,00,000 10,00,000 5,28,727 17,62,425 17,62,425 8,812,212
###
44,06,062 47,93,07,556
Say
48.00 Crores
C/O
39048900
604.44
192.75
145542460 1455314960 0