Course objectives
Correctly setting up an estimate Calculating the perimeter Setting up the concrete foundation takeoff Calculating concrete labor and material costs
Provide HO #1
Add perimeter (48 + 48 + 26 +26) = 148.0 ft. or 2(L + W) 148.0 ft x 8.0 ft x 0.83 ft = 982.72 cf.
Sectioning
Breaks construction down into smaller pieces More accurate More time consuming Use where large volumes of concrete required, but unusual angles, etc.
Sectioning red 2) 24.33 ft x 8.0 ft x 0.83 ft = 323.10 cf. blue 2) 48.0 ft x 8.0 ft x 0.83 ft = 637.44 cf. sum = 960.54 cf
Centerline length
Avoids adding corners twice Most common method in commercial wk
Useful for conc., rebar, walls, etc.
Formula to know:
Outside Building line length or perimeter (4 * thickness or width of any given strip)
SOL = Po (4T)
Complete in-class activity #1 calculate the amount of footing concrete required
Calculating Rebar
Rebar weight per linear foot See text (pg. 133 for splicing req.
Calculating formwork
2 Types
Structural (concrete) formwork
Foundations Walls Columns Beams
Refer to HO#1 Calculate the formwork and concrete required for the wall
Duration =
Course objectives