Академический Документы
Профессиональный Документы
Культура Документы
PAGE
I.
SUMMARY
89-3
II.
89-3
III.
MARKET STUDY AND PLANT CAPACITY A. MARKET STUDY B. PLANT CAPACITY & PRODUCTION PROGRAMME
IV.
V.
VI.
VII.
FINANCIAL ANALYSIS A. TOTAL INITIAL INVESTMENT COST B. PRODUCTION COST C. FINANCIAL EVALUATION D. ECONOMIC BENEFITS
89-3
I.
SUMMARY
This profile envisages the establishment of a plant for the production of silica (silicon dioxide ) with a capacity of 200 tonnes per annum.
precipitated
The present demand for the proposed product is estimated at 166.83 tonnes per annum. The demand is expected to reach at 402.03 tonnes by the year 2020.
The total investment requirement is estimated at Birr 4.16 million is required for plant and machinery.
The project is financially viable with an internal rate of return (IRR) of present value (NPV) of Birr 4.45 million discounted at 8.5 %.
22 % and a net
II.
Precipitated silica is industrial non-reactive filler which possesses large surface area, high absorption capacity, and high hardness. It imparts good finish and strength and balances the required physico- chemical properties of the product, to which it is applied. Precipitated silica has industrial applications in rubberized foot wear, paint, dyes, printing ink, and plastic products.
A.
MARKET STUDY
1.
Precipitated silica (silicon dioxide) is a non-reactive filler which possesses large surface area, high absorption capacity and high hardness. Precipitated silica has applications in rubberized footwear, paint and dyes, printing ink and plastic products.
The country's demand for the product is entirely met through import. Table 3.1 shows the yearly supply of silicon dioxide during the period 1998 - 2006.
Year
Qty (tonnes)
Value (000 Birr) 392.35 172.11 2,285.89 1,921.25 1,222.11 2,467.43 1,761.77 3,217.32 310.39 13750.62 1527.85
1998 1999 2000 2001 2002 2003 2004 2005 2006 Total Average
22.1 392.35 4.22 263.85 184.74 104.13 132.16 129.69 268.25 1501.49 166.83
89-5
As shown in Table 3.1 the supply from import fluctuates from year to year without any trend. For example, import during the period 1998-2001 ranges between 4.22 tonnes to 392.35 tone. Likewise import during 2002 2006 ranges from 104.13 tonnes to 268.25 tonnes. During the period of analyses highest import was in 392.35 in year 1999 and the lowest in 2000 ( 4.22 tonnes).
Although the import data is very erratic during 1998-2006, the country has been importing on the average about 166.83 tonnes of silicon dioxide per year.
In order to determine the present demand the average quantity imported during the period 1998 2006 has been assumed as the effective demand for the year 2007.
Accordingly, the present effective demand for the product is estimated at 166.83 tonnes.
2.
Projected Demand
Demand for silicon dioxide grows with the expansion of user industries. The industrial sector in the past four years was growing at annual average rate of 7% which is adopted for demand projection. The demand projection executed using this growth rate is shown in Table 3.2.
Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Qty. 178.51 191.00 204.37 218.68 233.99 250.37 267.89 286.65 306.71 328.18 351.15 375.73 402.03
3.
The average C&F price of silicon dioxide in 2006 is found to be Birr 6250/tonne. Allowing 40% for various chargers an ex-factory price of Birr 8750 per tonne is recommended.
For this product the suitable distribution system is direct sale to end users. This system is selected for the reason that the end users for the product are few in number while their individual consumption is high.
1.
Plant Capacity
Based on the outcome of the market study, the capacity of the envisaged plant is about 200 tonne/annum when operating in one shift/day (8 hours/ shift) and 300 days/annum. The capacity can be doubled of further increased, without increasing any significant fixed investment cost, by increasing the number of shifts.
2.
Production Programme
The production program is related to the forecasted demand. Therefore, the capacity utilization rate will be, 75% and 85% for the first and second year respectively. Form the third year onwards full capacity production will be maintained. The production programme is set by assuming that repair and maintenance works will be carried out during off-production hours.
IV.
A.
RAW MATERIALS
The principal raw materials are sodium silicate and sulfuric acid and the total annual cost of these materials is estimated at Birr 1,100,290 (see Table 4.1).
89-8 Table 4.1 ANNUAL RAW MATERIAL REQUIREMENT (AT FULL CAPACITY)
Sr. No 1 2
Material
Cost, 000 Birr Local 258.90 55.48 314.38 Total 906.12 194.17 1100.29
280 120
B.
UTILITIES
The annual consumption (at full capacity) of electricity and water is about 120,000 kWh and 1600m3, respectively. Furthermore, coal and kerosene will also be consumed and the annual requirement of these materials is estimated to be 250 tons and 150 m3, respectively. The total cost of the above utilities will be Birr 1,241,159.
V.
A.
TECHNOLOGY
1.
Production Process
Sodium silicate is dissolved in a pressure vessel using steam which is diluted to obtain desired concentration of sodium silicate. The sodium silicate solution is then hydrolyzed with sulfuric acid to obtain precipitated silica. This slurry of precipitated silica is then filtered through a membrane filter and dried in a spray drier.
The technical data and information are compiled from a document provided by the National Research development corporation of India.
B. 1.
The list of machinery and equipment of the proposed plant is indicated in Table 5.1 and the total cost of these items is estimated to be Birr 4,160,700 out of which Birr 3,618,000 is in foreign currency.
2.
The total area of the proposed plant is 3000 m2, out of which 1,000 m2 is a built up area. Therefore, the annual land rent cost is estimated to be Birr 2,400 and the cost of building, including civil work is about Birr 2,500,000.
3.
PROPOSED LOCATION
The envisaged plant shall be located in Hossana town, Lemo Woreda of Hadiya Zone. Table 5.1 LIST OF MACHINERY AND EQUIPMENT Sr. No 1 2 3 4 5 6 7 Machinery Boiler Pressure vessels Tanks (for sodium silicate, with motor gear) Filter press Spray dryer Sulfuric acid storage tank Reactors Qty 1 2 5 1 1 1 1
A.
MANPOWER REQUIREMENT
The manpower requirement of the envisaged plant is indicated in Table 6.1. In addition, the cost of training, which may take place during the erection and commissioning phase is about Birr 30,000.
Sr. No 1 2 3 4 5 6 7 8 9
Position
Req. No.
Salary, (Birr) Monthly 2,500 2,000 1,500 1,200 600 3,600 1,600 2,500 1,600 Annual 30,000 24,000 18,000 14,400 7,200 43,200 19,200 30,000 19,200 30,780
General manager Production and technical manager Chemist Accountant Secretary Operators & Technicians Ass. Operator Production Workers General service Benefit (15% BS) Total
1 1 1 1 1 6 4 10 8
33
235,980
B.
TRAINING REQUIREMENT
89-11
VII.
FINANCIAL ANALYSIS
precipitated silica
Tax holidays Bank interest Discount cash flow Accounts receivable Raw material local Work in progress Finished products Cash in hand Accounts payable
A.
The total investment cost of the project including working capital is estimated at Birr 8.33 million, of which 51 per cent will be required in foreign currency.
The major breakdown of the total initial investment cost is shown in Table 7.1.
89-12
Sr. No. 1 2 3 4 5 6 7 Cost Items Land lease value Building and Civil Work Plant Machinery and Equipment Office Furniture and Equipment Vehicle Pre-production Expenditure* Working Capital Total Investment cost Foreign Share
Total Cost (000 Birr) 192.0 2,500.0 4,160.7 125.0 450.0 620.7 281.8 8,330.2 51
thousand ) and
Birr 150 thousand costs of registration, licensing and formation of the company including legal fees, commissioning expenses, etc.
B.
PRODUCTION COST
3.77
million (see Table 7.2). The material and utility cost accounts for 62.05 per cent, while repair and maintenance take 2.65 per cent of the production cost.
89-13 Table 7.2 ANNUAL PRODUCTION COST AT FULL CAPACITY ('000 BIRR)
Items Raw Material and Inputs Utilities Maintenance and repair Labour direct Factory overheads Administration Costs Total Operating Costs Depreciation Cost of Finance Total Production Cost
Cost 1,100.29 1241.16 100 141.59 47.2 94.39 2,724.63 673.57 375.48 3,773.68
% 29.16 32.89 2.65 3.75 1.25 2.50 72.20 17.85 9.95 100
C.
FINANCIAL EVALUATION
1.
Profitability
According to the projected income statement, the project will start generating profit in the first year of operation. Important ratios such as profit to total sales, net profit to equity (Return on equity) and net profit plus interest on total investment (return on total investment) show an increasing trend during the life-time of the project.
The income statement and the other indicators of profitability show that the project is viable.
89-14
2.
Break-even Analysis
The break-even point of the project including cost of finance when it starts to operate at full capacity ( year ) is estimated by using income statement projection.
BE =
25 %
3.
The investment cost and income statement projection are used to project the pay-back period. The projects initial investment will be fully recovered within 4 years.
4.
Based on the cash flow statement, the calculated IRR of the project is 22 % and the net present value at 8.5 % discount rate is Birr 4.45 million.
D.
ECONOMIC BENEFITS
persons.
domestic needs, the project will generate Birr 3.15 million in terms of tax revenue. The establishment of such factory will have a foreign exchange saving effect to the country by substituting the current imports.