(PROJECT PROCEDURE)
UNDERGROUND CIVIL WORKS 6838-01-09-41-0001 Rev. 0
STRATEGIC STORAGE OF CRUDE OIL
Page 1 of 3
PROJECT, VISAKHAPATNAM
1.1 GENERAL
CONTRACTOR shall prepare and submit to OWNER/PMC upon the dates stated
hereafter, drafts of various PROJECT PROCEDURES. The Project Procedures
shall comprise planning, organization and control and other documents necessary
for the efficient co-ordination of the work.
Within fourteen (14) days of the award of work CONTRACTOR shall submit all
the project procedures for owner comments/approval. OWNER/PMC will respond
with any comments within ten (10) days. CONTRACTOR shall revise and reissue
the project Procedures for approval within seven (7) days upon which it shall be
put into effect.
The Project Procedures shall include, but not be limited to, the following items
which shall be submitted for approval upon or before the dates stated.
• Engineering Procedure
• Procurement and subcontracting procedure including examples of:-
- Purchase order
- Inspection expediting monitoring procedure
- Layout drawings of warehouses and open storage areas at
worksite.
- Warehousing & storage procedure.
- Procedure for storage of explosives
• Procedure for establishing temporary facilities, site office, lay down areas,
arranging facilities at site for OWNER/PMC
• Pre-commissioning and commissioning procedure
• QA/QC Procedure including
- Invoice Register
- Invoice
- Change order/Deviation permit
1.3 The names and addresses of approved subcontractors shall be included in the
Project Procedures upon approval by Owner/Consultant.