Академический Документы
Профессиональный Документы
Культура Документы
PROJECT
MANAGEMENT
International Journal of Project Management 24 (2006) 187–189
www.elsevier.com/locate/ijproman
Editorial
We can derive logically that we need such a tool, we can- book-keeping, developed 500 years ago, and used and
not derive logically that Configuration Management is nec- shown to work since that time. I have shown [2] that the
essarily the best tool. We have to draw on empirical standard methods of cost and management accounting,
evidence for that. when applied to projects, become Earned Value Analysis.
As the project is completed, we want to monitor its per-
Lemma 9. Earned Value Management is a useful tool for
formance and ensure it does actually work as expected and
Cost Management.
produce the desired benefit.
This lemma draws on the field of cost and management
Corollary 13. Benefits Management is an essential compo-
accounting.
nent of Scope Management.
5. Time Management
2. Project organization
Also for the outcome to be of benefit it must be obtained
Premise 1 says that resources are assigned to the project to within certain timescales. There are at least three ways in
do the work to bring about the change. We have also identi- which time can have an impact:
fied seven roles associated with Project Management.
Appropriate people and other resources need to be identified 1. Sometimes the output only has the desired benefit at a
and marshalled to the project to fulfil these requirements. certain time. For instance in event management (such
Corollary 14. Project organization is an essential compo- as a sporting event) there is a defined time at which
nent of Project Management. the event must start, to the nearest minute. If the project
is late, all the benefit is lost.
At any level of breakdown we will need to match roles 2. Sometimes the output only has the desired benefit over a
and responsibilities and the skill requirements to the prod- limited market window. For instance new toys have a six
ucts and work at that level. week market window over Christmas. If the project is
Corollary 7D. Organization breakdown is an inherent com- late, the benefit is not lost absolutely, but benefit is lost
ponent of Project Organization. in proportion to any time the project is delayed.
3. Finally, because of the time value of money, the later the
project is delivered the more it costs, and so value is
3. Quality Management eroded. Here we have to draw on theory from another
management subject, (Economics and Finance) to
We have identified above that the project deliverable enlighten our theory of Project Management.
must function in the desired way; that it must perform.
We will specify how we expect the product to perform, Corollary 17. Time Management is an inherent component
and what standards it should meet. We must then ensure of Project Management.
that the specification and standards are met, that the out-
put functions as required, and that the desired outcomes Empiricism 3 I don’t entirely agree with.
are achieved. That is Quality Management. Empiricism 3: Bar Charts, Critical Path Analysis, Critical
Corollary 15. Quality Management is an inherent compo- Chain, and Resource Smoothing are useful tools for Time
nent of Project Management. Management.
L4: The work of the project is non-routine We have also identified several roles:
L5: and therefore risky
L6: Projects have five stages of: concept, feasibility, design, R1: The owner who provides the resources to buy the
execution, close asset and will receive the benefit from its operation.
L7: Management has five steps: plan, organize, implement, R2: The users who operate the asset on the owner’s
control behalf.
L8: Projects and Project Management are fractal R3: The sponsor who will channel the resources to the
L9: Earned value management is the appropriate tool for project on the owner’s behalf.
managing cost. R4: The resources who are assigned to the project and will
Project Management comprises: do the work to deliver the asset.
R5: The broker, who works with the owner and sponsor
C1: Project contract and procurement management. to define the required outcome (benefit) from the
C2: Information management. project, and the output (change) which will achieve
C3: Financial management. that.
C4: Resource management. R6: The steward, who works with the broker to identify
C5: Project appraisal. the means of obtaining the output, the work and
C6: Project definition. resources required.
C7: Breakdown. R7: The manager who manages the temporary organi-
C8: Risk management. zation, to ensure the right work is done to deliver
C9: The management of the project. the defined output, and monitors and controls
C10: The project and project management life-cycles. progress.
C11: Scope management.
C12: Requirements management.
C13: Benefits management. References
C14: Project organization.
C15: Quality management. [1] PMI. Guide to the project management body of knowledge. 3rd ed.
C16: Cost management. Newtown Square (PA): Project Management Institute; 2004.
[2] Turner JR. The handbook of project based management. 2nd ed.
C17: Time management. London: McGraw-Hill; 1999.
[3] Turner JR. The management of large projects and programmes for
We have identified some tools from empirical web delivery. Aldershot: Gower; 2004.
experience:
J. Rodney Turner
E1: Configuration management. Lille School of Management
E2: Bar charts, critical path analysis, critical chain, United Kingdom
resource smoothing. E-mail address: rodneyturner@europrojex.co.uk