Вы находитесь на странице: 1из 11

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 22 (2004) 289–299
www.elsevier.com/locate/ijproman

Programme management: a critical review


a,*
Mark Lycett , Andreas Rassau b, John Danson b

a
Department of Information Systems and Computing, Brunel University, Uxbridge, Middlesex UB8 3PH, UK
b
Global Manufacturing Supply IT, GlaxoSmithKline, Stockley Park West, Uxbridge, Middlesex UB11 1BT, UK
Received 20 December 2002; received in revised form 7 February 2003; accepted 27 June 2003

Abstract

There is an increasing recognition that programme management provides a means to bridge the gap between project delivery and
organisational strategy. Significant tensions tend to arise across this gap, however, between the inward-focused and task-oriented
view of projects and strategy-focused and often emergent wider organisational view. It is argued within this paper that standard
programme management approaches actually exacerbate these tensions. Through a critical review of standard programme man-
agement approaches, a number of issues are highlighted that concern (a) an excessive control focus, (b) insufficient flexibility in the
context of an evolving business strategy, (c) ineffective co-operation between projects within the programme. These issues are traced
back to the two flawed assumptions underlying programme management; namely that (a) programme management is in effect a
scaled-up version of project management and (b) a Ôone size fits allÕ approach to programme management is appropriate. In
combination these observations are used to provide grounding for a fundamentally different approach to programme management
designed for flexibility, enabled for adaptability in a changing business environment and focused throughout on the effective
management of key stakeholder relationships.
 2003 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Programme management; Project management; Multi-project management; Strategy; Learning

1. Introduction context [2,5,6]. In this context the foundations have been


laid for a new discipline, commonly referred to as Pro-
Traditionally, the vast majority of practical and theo- gramme Management – defined as the integration and
retical developments on project management have been management of a group of related projects with the intent
related to single projects considered in isolation [1]. This of achieving benefits that would not be realised if they
can be traced back to the origins of the project manage- were managed independently. Whilst connected, this is
ment discipline within the construction industry. Over distinct from portfolio management.
time, however, issues have arisen where multiple projects The aim of this paper is thus to provide a critical
are undertaken within organisations including (a) risk summary of the status of programme management,
that the lack of co-ordination and overall control will highlighting the implications of the state-of-the-art for
negatively impact efficiency and effectiveness [2] and (b) both research and practice. Consequently, key issues
confusion over responsibility for managing multiple de- that have driven the development of the theoretical
mands on staff [3]. In some circumstances matrix struc- discipline are reviewed alongside the practical difficulties
tures may diffuse authority to the point that managers can that arise when attempting to apply programme man-
no longer carry out their responsibilities [4]. As a conse- agement principles in practice. The paper begins by
quence, there has been an increasing awareness of the synthesising the perceptions that surround programme
requirement for a new perspective on the management of management in order to state the fundamental goals of
projects, distinct from that applied in a single project the approach. These goals provide a benchmark for
assessing emerging programme management standards,
*
Corresponding author. Tel.: +44-1895-203050; fax: +44-1895-
which are then reviewed. A detailed critical analysis of
251686. programme management is then presented and a num-
E-mail address: mark.lycett@brunel.ac.uk (M. Lycett). ber of issues highlighted that concern (a) an excessive

0263-7863/$ - see front matter  2003 Elsevier Ltd and IPMA. All rights reserved.
doi:10.1016/j.ijproman.2003.06.001
290 M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299

control focus, (b) insufficient flexibility in the context of objectives. The fundamental goals of programme man-
evolving business strategy and (c) ineffective co- agement can be categorised twofold:
operation between projects within the programme. The • Efficiency and effectiveness goals. Aspects of manage-
cause of these issues is traced back to the two underlying ment that a proficient project manager should address,
and flawed assumptions namely that (a) programme even in the cases where related projects are undertaken
management is in effect a scaled-up version of project without overall co-ordination. It is believed that a gen-
management and (b) a one size fits all approach is ap- eral improvement in management efficiency and effec-
propriate. Lastly, the paper concludes by presenting a tiveness can be achieved by taking an integrated
coherent research agenda and recommendations on how approach to these particular aspects of management.
programme management can best be used in practice. • Business focus goals. The external alignment of pro-
jects with the requirements, goals, drivers and culture
of the wider organisation. These goals are associated
with defining an appropriate direction for the constit-
2. The fundamental goals of programme management uent projects within a programme as well as for the
programme as a whole.
Programmes exist to create value by improving the Goals appropriate to each category have been sum-
management of projects in isolation [7]. Thus, while they marised in Table 1 alongside literature representative of
create benefits through better organisation of projects, each specific orientation. Two points are made in respect
they do not in themselves deliver individual project of this classification (see Table 1).
Table 1
Programme management goals and goal categories
Goal Description Representative literature
Efficiency and effectiveness goals
Improved co-ordination Assist in identification and definition of project interdependencies [7,8]
and thereby reduce the incidence of work backlogs, rework and delays
Improved dependency Reduce the amount of re-engineering required due to inadequate [7,8]
management management of the interfaces between projects
More effective Improve the effectiveness and efficiency of the allocation of shared resources [7–9]
resource utilisation
Assist in providing justification for specialist resources that deliver an overall
improvement to programme delivery and/or business operations
More effective Provide a means to identify and improve upon transferable lessons. (Mentioned in 10 but
knowledge transfer otherwise not developed
in the literature)
Facilitate organisational learning

Greater senior Enable senior management to better monitor, direct and control the [7–9]
management ÔvisibilityÕ implementation process

Business focus goals


More coherent Improve communication of overall goals and direction both internally [7,8]
communication and externally to the programme
Target management attention clearly on the realisation of benefits
that are defined and understood at the outset and achieved through
the lifetime of the programme and beyond
Assist in keeping personal agendas in check
Improved project Ensure that project definition is more systematic and objective, [7,11]
definition thereby reducing the prevalence of projects with a high risk
of failure or obsolescence
Enable either the unbundling of activities in a strategic
project-set into specific projects
Enable the bundling of related projects together to create a
greater leverage or achieve economies of scale

Better alignment with Improves the linkage between the strategic direction of organisations and the [7,9]
business drivers, management activities required to achieve these strategic objectives
goals and strategy
Provide an enabling framework for the realisation of strategic change and the
ongoing alignment of strategy and projects in response to a changing business
environment (via project addition/culling, etc.)
M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299 291

Firstly, the aspect of Ôknowledge transferÕ has, for the


Sponsoring Group
most part, been neglected within the programme man-
Senior
agement discipline. Projects are by definition transient Programme
Business
Director
phenomena and very few companies have developed the Management
means to identify and build upon transferable lessons
[12]. Indeed, an effective means of transferring learning
from experience on projects has been noted as one of the
Programme Business
key factors leading to consistently successful projects Manager Change
[13]. In spite of this, knowledge transfer is normally only Manager
given a cursory reference in the context of programme Programme Management
management. Consequently, it is argued that knowledge Project Management
and information sharing between projects should be a
Project Board
cornerstone of effective programme management.
Project
Secondly, it is essential that programme management Executive
Senior
approaches address both the areas of efficiency and ef- Senior User
Supplier
fectiveness and business focus. As it stands, programme
management efforts are often conceived in ‘‘loose’’ form
(see [14]) and projects are related only by virtue of a
specific internal management feature or features, such as Project
Manager
shared resources or common technologies. This ap-
proach does not necessarily harness the full potential of
programme management and can serve to diffuse its Fig. 1. Programme and project roles as per managing successful pro-
gramme approach [8].
value. Whilst emerging programme management meth-
odologies claim to address both the types goals, in
slightly different hierarchy of roles whereby the Pro-
practise they are designed predominantly around the
gramme Client acts for the business as a whole in de-
goals of efficiency and effectiveness. Again, this serves to
termining the strategic requirements for the programme
diffuse the value of programme management.
and the Programme Manager has overall responsibility
for realising the anticipated benefits from the pro-
gramme. The common feature of these and other ap-
3. Emerging standards
proaches, however, is that the Programme Manager role
sits in a linear hierarchy at a level above the project
A standard approach to programme management is
managers, implying a direct reporting relationship.
now starting to emerge, based on the same fundamental
There is no recognition, within these standard ap-
principles as the standard approaches to project man-
proaches, that the programme management role may be
agement; structure and control. In broad terms, the
a distinct although not necessarily hierarchically supe-
common themes in these approaches are: (a) a hierarchy
rior role to that of the project managers.
of roles, (b) a linear lifecycle and (c) a set of defined
activities.
3.2. Programme management lifecycle
3.1. Programme roles and responsibilities
The second key feature of the standard approaches is
One of the crucial elements of any programme is the their basis on a lifecycle directly analogous to the equiv-
definition of the programme organisation. The model alent project lifecycles (see for example PRINCE2). The
used within the Managing Successful Programmes staged programme lifecycle is based on the assumption
(MSP) approach [8] is typical of the designs presented that a defined input will be provided at the outset of the
within the literature and is represented in Fig. 1. The programme, which definitively outlines the overall direc-
MSP approach singles out three key roles: (a) the Pro- tion and make-up of the programme. Consequently, the
gramme Director who as ultimate responsibility and perception is that the alignment with strategy can
accountability for the programme; (b) the Programme achieved by up-front definition of the appropriate
Manager, who is responsible for the setting up and groupings and that, subsequently, ÔadjustmentÕ is all that
running of the programme and (c) the Business Change is required to keep the programme and the strategy in line.
Manager, who has responsibility for the benefits man- The lifecycle is illustrated in Fig. 3.
agement and realisation processes. Here, the separation The stages that are generic to most approaches are
of benefits delivery from the Programme Management programme: (a) identification, (b) definition, (c) execu-
recognises the fundamental difference between project tion and (d) closure. Programme identification defines
delivery and benefits realisation. Pellegrini [7] suggests a ‘‘the overall objective for the programme and positions
292 M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299

the programme within the organisationÕs corporate and resource management, (b) monitoring and control,
mission, goals, strategies and other initiatives’’ [ 8,p. 69]. (c) configuration management and change control, (d)
In the IBM approach [16], it is suggested that this stage risk and issue management (e) benefits management,
should also include the determination of the best can- and (f) stakeholder management.
didate grouping of projects whilst in the OGC approach The principle objective of Programme Planning and
this is deferred until programme definition. Haughey Resource Management is to organise work in a way that
[15] suggests that, at the identification stage, it is im- accomplishes the programme objectives and achieves
portant to give boundaries to the programme explaining benefit across a programme of projects [8]. The funda-
exactly what will be delivered. Indeed, this is conveyed mental difference between this activity and project
within the OGC approach by means of the Programme planning is that the activity is not just the organisation
Brief, which should include the programme vision, of many inter-related projects but also includes the
outline benefits, risks and issues, as well as estimates of maximisation and utilisation of the resources and asso-
costs time-scales and effort. Thus, just as in the case of a ciated schedule(s) to implement these projects [8]. In
Project Brief, up front definition is achieved on the size, addition, in cases where programmes do not have ded-
constitution and projected duration of the proposed icated resources, resource management may be applied
programme. at the organisational level [5]. Pellegrini [7] makes the
The Programme Definition stage includes: (a) the re- point that the practice of applying a rigid critical path
finement of the programme vision and objectives, (b) through a programme network (as would be implied by
creation of the programme organisation and (c) estab- the more standard programme planning approaches)
lishment of the processes and support structures re- may not be advisable. This is based on a view that there
quired to facilitate the management of the programme. is often no single, clear outcome for a programme and a
Here, the inter-dependencies of the projects that make level of intuition is required.
up the programme are clarified and used as the basis for Programme Monitoring and Control involves tracking
the high-level programme plan, which provides an in- progress on individual projects and taking action as and
dication of the sequencing of projects [15]. when required [7]. The essential purpose is to alert the
During the Programme Execution stage the individual programme manager to any project interdependencies
project managers run the identified projects and the that are becoming critical in terms of delivery date, re-
Programme Manager has responsibility to monitor source-utilisation, costs or benefits [8]. This is achieved
progress, assess risks and report on progress [15]. Spe- via an audit discipline, which examines the activities
cific activities during this stage include: (a) ensuring that within the programme with the intent of establishing
the target business environment is adequately positioned how closely they conform to internal standards and
to receive the changes and (b) ensuring that benefits and procedures or external codes of practice [8]. In many
risks are properly managed throughout the programme. ways, the programme monitoring and control discipline
In both the OGC and IBM methodologies it is suggested is analogous with the project management discipline,
that projects are implemented in a series of groups, with albeit that the reporting structures may differ slightly
periodic review points following each grouping. In and the control steps will of course depend on the
outline terms, this idea relates to the concepts of evo- context.
lutionary project management and rolling wave plan- The need for Configuration Management and Change
ning, thus providing some mechanism for business Control is clearly expressed in most of the standard
alignment. approaches to programme management. MSP, for ex-
The Programme Closure stage is concerned with ample, utilises a Programme Blueprint as a means of
benefits realisation. The essential objective of this stage indexing the overall configuration to be managed, the
is to ensure that the programme delivers the planned configuration comprising information about the orga-
benefits and that these are fully realised where possible nisation, its people processes, tools and systems [8]. This
[8]. The nature of this realisation is by formal assess- follows a common view that all programmes must have
ment. In addition, it is this stage at which confirmation well-defined baseline from which to measure costs and
is obtained that all projects in the programme have been benefits and that this baseline should define the overall
formally closed. scope in order to facilitate change control. Configura-
tion management is supposed to ensure that the blue-
3.3. Programme management activities print is always cohesive and consistent and is coupled
with a programme-level change-control process, which
A range of different programme management activi- is applied to essential sets of information about the
ties have been proposed, each focused around the as- programme; in particular the programme blueprint and
sumption of hierarchy of programme roles and a linear programme plan.
programme lifecycle as described above. The key com- Programme Risk Management differs from that con-
mon areas proposed in the literature are: (a) planning ducted at the project level in that it addresses strategic
M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299 293

issues such as: (a) programme effectiveness in enhancing • The management of the relationship between the in-
the organisations competitive position, (b) the achieve- dividual project managers within the programme.
ment of the programmeÕs benefits and/or (c) the effects It is our contention that all of the problems experi-
of changes in the assumptions underlying the pro- enced when programme management techniques are
gramme business case [7,8]. The MSP technique of risk applied in practice can be related to the ineffective
management calls for the use of a risk log analogous to management of one or more of these relationships. The
the equivalent project-level log [8]. Pellegrini [7], how- issues associated with each of these relationships are
ever, suggests that mechanisms associated with strategic now dealt with in turn.
management might be better suited, such as competitor
analysis and benchmarking. Programme Issues Man- 4.1.1. The interface between programme management and
agement has been described as a formal means of esca- project management
lating project issues to the programme level, logging and Standard approaches to programme management
tracking them as part of the activity [8]. In essence, strive to obtain an inappropriate level of detail driven by
however, programme issues management is little more a desire to exercise an inappropriate degree of control.
than an alternate view of the issue logging and escala- This tends to lead to systems of programme planning and
tion processes that exist at the project-level. control that are complex to the point of becoming un-
Programme Benefits Management has been discussed manageable. Two negative consequences arise as a result:
in the project sense in a number of recent papers (e.g., • Excessive hierarchical bureaucracy and control. It can
[11,17]). The descriptions of the activity provided within be very difficult to achieve an appropriate balance be-
the programme literature do not differ fundamentally tween excessive control and insufficient control in a
from the project level concept, except in relation to the multi-project context [17]. Standard approaches to
division of responsibilities [8]. Whereas the responsibil- programme management tend towards excessive con-
ity of the project manager ends with completion and trol, a bias emphasised by currently available pro-
sign-off of project deliverable (the benefits enabler), the gramme management software, which focuses the
programme organisation also has overall responsibility resource management and integrated planning ele-
for ensuring benefits realisation [8]. One view is that ments [18]. Research indicates that excessive bureau-
benefits management should be entirely carried out at cracy and control has a tendency to create
the programme level, making the point that project inflexibility, bureaucratic overheads of reporting re-
managers are not well positioned to consider the validity quirements and in extreme circumstances relegate pro-
of their projects. MSP splits the activity by specifying a gramme management to little more than a mechanism
number of key stages in terms of benefits management, for reporting [6,19,20]. The negative consequences of
each with associated responsibilities [8]. an overly bureaucratic approach to programme man-
MSP also highlights the important point that stake- agement are: (a) a deterioration of the relationship be-
holders will come and go over the course of a tween project managers and programme managers
programme [8]. As such Programme Stakeholder Man- encouraging a culture of blame and (b) diversion of en-
agement needs to be inherently more flexible and ergy from value adding activities.
adaptable than the equivalent project-level discipline. In • Focus on an inappropriate level of detail. Large inte-
spite of this, none of the current approaches offer a great grated plans/networks are difficult to formulate and
deal of insight as to how this additional flexibility should have a tendency to become cumbersome and exces-
be achieved. sively complex [5,21]. This calls into question the em-
phasis of the standard programme management
techniques on detailed integrated planning. By focus-
4. A critique of current approaches ing at an inappropriate level of detail, there is a real risk
that programme managers will fail to identify the issues
4.1. Significant difficulties of practical application that are of real significance to the programme. Conse-
quently, the focus at the programme level should be on
The review of current approaches to programme the interfaces between projects [21]. This is important
management invites three major criticisms. Which relate given that interdependencies often become associated
to the management of three key stakeholder relation- with issues of ownership. People working on different
ships associated with the programme: initiatives either tacitly cover the same ground or else
• The management of the relationship between the pro- assume that other people will do the work.
gramme manager and the project managers within
the programme. 4.1.2. The interface between organisational strategy and
• The management of the relationship between the con- constituent projects of the programme
stituent projects of the programme and the wider Standard approaches to programme management
business context. largely neglect the need to shape, embed and align pro-
294 M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299

grammes with the evolving business environment [7]. rewards. The tacit assumption is that organisational
This is problematic give the programme management effectiveness can be improved by focusing on individ-
role of building and maintaining a connection between ual project effectiveness. Evidence from a recent de-
the task-focused view of projects and the strategic drivers fence, engineering and construction industry study,
of emergent organisation. Standard approaches to pro- however, suggests that competition between projects
gramme management are based on a project-level view of is not in the best interests of the organisation as a
change-control rather than a strategic view of change whole [24]. Other work notes that: (a) employees of-
management, which results in intrinsic inflexibility that ten do what is necessary for the evaluation in prefer-
manifests itself in two distinct but related ways: ence to what is required for the job [25]; (b)
• Programme lifecycle. Standard approaches focus on a competition creates a level of anxiety that interferes
linear programme lifecycle. The underlying assump- with performance [26] and (c) in an environment of
tion is that the programme can be defined in detail intense competition, projects operate so autono-
at the outset and then carried through to a defined mously that they simply do not know what people
closure point, closely managing the programme scope outside there own team are working on [23].
throughout (see [15] for example). In this context, ac- • Failure to harness organisational learning. Although
tivities such as adjustment of the direction of the some reference is made by the standard methodolo-
programme or addition of new projects to the pro- gies to transfer learning between projects (see [8] for
gramme only occur by exception. Although it is in example), this is not backed up the creation of an en-
theory possible to evolve the programme in response vironment that actually enables this to happen. What
to a changing business environment, the focus on def- is required is not only a statement of intent that learn-
inition and control of programme scope severely ing should be shared, but the creation of supportive
restricts programme flexibility. In essence, an insis- open culture that enables this to happen. In the pro-
tence on tight definition and clear boundaries negates ject arena, natural incentives pressure project manag-
part of the value of having a programme [7]. ers to get on with the next project and not to dwell on
• Programme tenure. Many standard approaches per- the failures of the past [12]. Consequently, knowledge
ceive programmes to have a finite life [15]. This is is gained in a Ôhit and missÕ fashion [27]. As Eskerod
constraining given that the underlying processes used [23] notes, learning that are communicated in such a
to identify strategies, whilst planned to some degree, highly competitive environment are likely to be non-
are fragmented, emergent, evolutionary and largely symmetric in that they will be biased towards the rep-
intuitive [22]. Further to this, emotional and territo- resentation of success.
rial sensitivities unearthed during strategy formula-
tion are actually magnified during strategy
4.2. Fundamentally flawed underlying assumptions
implementation, which may accentuate emergence
and unpredictability [11]. Consequently, it seems ill
Two assumptions underlie all the issues outlined in the
advised to force fixed time-scales at the outset of a
previous section. Firstly, programme management is
programme. An alternate view that programmes
misconceived as a scaled-up form of project manage-
may have an indefinite time horizon [7] is more real-
ment. Secondly, it is assumed that there is a single form of
istic if constrained by the view that they should only
programme management, equally applicable in all cir-
continue so long as they are justified in terms of busi-
cumstances. It is argued here that these assumptions are
ness benefit. This is consistent with a view expressed
flawed and have driven the development of the pro-
by McElroy [9] that programmes need to be able to
gramme management discipline into its current form.
assimilate projects on an incremental basis.

4.1.3. Interface between projects within the programme 4.2.1. Assumption that programme management is a
Standard approaches to programme management scaled up form of project management
also tend to ignore difficulties that are found at the in- Gareis [28] has suggested that any project lasting
terface between projects themselves. Competition, for longer than two years should be classed as a pro-
example, is a natural feature of a multi-project envi- gramme. Similarly, other writers have pointed out that
ronment [23] and manifests itself in terms of rivalry to project managers still think in terms of ‘‘programmes of
achieve high prioritisation ratings and/or strong com- work’’, implicitly taking this to mean a schedule in the
petition to secure specific resources. Project rivalries traditional project sense [7,10]. The assumption of
have two negative consequences: equivalence between programme and project and man-
• Inter-project competition. Organisations often operate agement is made explicit by Gray [14], who has claimed
an internal market forces system where projects com- that a programme, project, sub-project and work
pete for resources. This market is typically reinforced package are simply different levels in a hierarchy of
by individual and team-based performance-related project-type work activities. This underlying assumption
M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299 295

and its consequent weaknesses are reflected in the vari- tured approach can be applied equally effectively in all
ous components of the standard programme manage- contexts. This outcome is reminiscent of one school of
ment methodologies: thought in the project management domain, which
• Strict hierarchical perspective. Programme manage- believes that project management principles are uni-
ment organisations proposed within the standard versal and generic (see [29]). Counter to this, a second
methodologies are strictly hierarchical, with a tradi- school of thought argues that the appropriateness of
tional line reporting relationship between the project principles will depend on the characteristics of the
manager and the programme manager. In a pro- project, the organisation(s) in which it is performed
gramme context insistence on a rigidly hierarchical and the environment in which the organisation is op-
arrangement can lead to a negative spiral of bureau- erating [17].
cracy and control. While standard approaches recognise a number of
• Time-constrained linear programme lifecycle. The different types of programme (e.g., strategic, business
standard methodologies assume a relatively simple cycle, infrastructure and R & D), little guidance is of-
linear input process, whereby the programme is es- fered in terms of: (a) the necessary difference in ap-
tablished based on defined organisational strategy proach for different programmes or (b) how the
and then slight adjustments are made to the pro- standard approaches might be adapted to an uncon-
gramme as it progresses towards its target state. This nected-projects scenario. Herein lies a paradox since,
assumes a substantially complete and stable input whilst there has been an increasing recognition in the
definition, which justifies the investment of effort to literature of diversity of different programme forms and
create a detailed programme plan charting the course contexts, there has also been a convergence on a pur-
of the programme through to completion. Insistence portedly generic programme management approach that
on a relatively rigid form of programme life cycle in- fails to account for such differences. The key programme
trinsically limits the ability of the programme to design considerations are as follows:
adapt in response to changing business strategy. • Programme benefits and project goal interdependence.
• Parity of approach pervading programme management A key error in programme initiation hinges around
techniques. The assumption of basic equivalence be- the failure to clarify the direction and purpose of
tween project and programme management disciplines the programme. Pellegrini [7] argues that different ra-
is reflected throughout the majority of the proposed tionales for programmes should lead to different pro-
programme management techniques. For example, gramme management structures and identifies three
the proposed approach to programme planning is es- types of programme, each of which requires a differ-
sentially scaled-up versions of the equivalent project- ent programme management approach. Firstly, a
level technique. The effects of this are: (a) a potential ÔportfolioÕ programme is used to co-ordinate distinct
tendency towards complexity, bureaucracy and con- projects using a common resource or skills base. Sec-
trol; (b) limitations on the ability to evolve the scope ondly, a Ôheart beatÕ programme is applicable in situ-
in response to changing business drivers, goals and ations where there are requirements for regular
strategies and (c) a mechanical perspective that does improvements to existing systems, infrastructure,
not offer insight into how to manage the softer issues business processes and the like. Lastly, the Ôgoal-
that very often arise at the programme level. orientedÕ approach to programme management,
• The implicit reinforcement of the similarity of roles. which is focused around the translation of vague, in-
An assumption commonly encountered in practise is complete and evolving business strategies into tangi-
that programme management is simply a step on ble actions.
the career path for project managers. In fact it has • The nature of the constituent projects. There is a
been demonstrated that many talented individuals common perception that organisations should apply
find the transition between project and programme a standard approach for the management of all
management a huge challenge [7]. Many of the in- projects in a programme, regardless of type of the
stincts that good project managers acquire over years project type, size, urgency or the type of resource
of experience may actually be counterproductive in a used [30]. The presumed benefits of this approach
programme management context. For example, it is include comparable progress reporting and the pos-
typical of the project management mind-set that pro- sibility for people to move freely between projects
ject scope is guarded defensively. This is likely to without having to learn a new approach. Similarly,
highly restrictive in a programme context. there is a common perception that projects within a
programme are fundamentally homogeneous and
4.2.2. Assumption that there is a one size fits all approach the engagement required is the same in all cases.
to programme management This assumption is called into question, however,
Standard approaches to programme management by work suggesting that non-homogeneity adds an
implicitly assume that a single rigid and highly struc- important layer of complexity to programme man-
296 M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299

agement [5]. More specifically, it has been found


that better results are achieved at a project level
when people tailor procedures to the type of project Project to
Improved Coordination
that they are working on [30]. Extending this logic Programme
to the engagement between the projects and pro- Improved dependency management

grammes, it is likely that different types of project


More effective and efficient resource
will benefit from different programme management utilisation
approaches.
More effective transfer of knowledge,
• The geographical distribution of the programme. A Project to
ideas, tools and techniques
Project
further possible difference between programmes re-
Greater senior management visibility
lates to the geographical distribution of the staff
working within them. Evaristo and Fenema [1] More coherent communication

describe the following programme scenarios: (a) co-


Better up front definition of projects
located programme, where multiple concurrent Projects to
projects are all in a single geographical location; (b) Business
More effective ongoing alignment with
multiple traditional projects, where concurrent pro- business drivers, goals and strategy

jects are based at a different geographical location;


and (c) multiple distributed projects, where each pro-
Fig. 2. Key programme management relationships and goals.
ject encompasses several sites either at overlapping
locations or else at discrete locations.
• Strength of programme mandate. The choice of pro-
gramme management approach depends not only tionships to the fundamental goals of programme
on desirability but also equally on feasibility [14]. management.
Often, it will be the case that the design of a pro- In attempting to direct programme management re-
gramme may not be entirely within the programme search, the principal observations that stem from this
managerÕs control given political constraints of the work are that programme management should be per-
context, which either force or preclude particular ap- ceived as:
proaches. The programme managerÕs ability to • Contextual. Appropriate programme structure, pro-
choose the optimal approach for the context will cesses and organisation are strongly dependent on
thus depends on the strength of their mandate. In factors such as the degree to which the projects are in-
turn, this will depend on the standing of the pro- terrelated, the characteristics of the constituent pro-
gramme management discipline within the wider or- jects and the nature of the wider organisation.
ganisation as well as the perceived authority of line • Variable and concurrent in practice. Programme man-
organisation to which the programme manager re- agement may operate on several levels simulta-
ports. Since the overall programme is seen as being neously. For example, small groupings of projects
owned the business, this may limit the flexibility may be managed together in one type of programme
for defining the reporting structures of the pro- whilst another type of programme may simulta-
gramme organisation. neously extend across the entire organisation.
• Evolutionary in sophistication. It is unrealistic to ex-
pect that the programme approach can be introduced
4.3. Conceptual and practical implications in a Ôbig bangÕ fashion due to the level of organisa-
tional change mandated by its introduction. Conse-
Reflection on the review presented above suggests a quently, it is more fruitful to accept that
number of important implications for programme organisational sophistication in programme manage-
management, which are currently poorly represented in ment will evolve and that it will not be possible to ap-
both in research and practice. The primary implication ply some of the more advanced features of
for both research and practice is that the ÔrationalÕ basis programme management unless appropriate founda-
of programme management (e.g., the lifecycles and ac- tions exist.
tivities) represents only part of the equation and needs Accounting for each of the three points above, it is
to be strongly supplemented with competence(s) related clear that an approach to programme management is
to the understanding and management of relationships. required that is scaleable, flexible and appropriate both
Key relationships have been argued to be those: (a) to the organisational context as well as the capabilities
between programme management and project manage- of those applying it. The points related to context and
ment, (b) individual project managers within a pro- variation account for the emergent nature of the
gramme and (c) individual projects and the goals and strategies on which programmes are to deliver along-
drivers of the wider business. Fig. 2, ties these rela- side the changing context of programme delivery
M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299 297

Fig. 3. Typical programme management lifecycle [15].

[11,18]. The point on adaptability in the context of a ronment, it is of vital importance to ensure an ade-
changing environment is proposed as one of the key quate ongoing connection between the projects
benefits of the programme management approach, within the programme and the wider organisation if
though research on the practicalities of adaptability is projects are to remain aligned with the overall drivers
scant. and strategic direction of the organisation. Equally, it
Whilst ongoing research is required for the develop- is important part of the programme management role
ment, adoption and institutionalisation of the findings to facilitate effective relationships between the indi-
of this programme management review, practical guid- vidual project managers within the programme in or-
ance can be drawn from the research as follows: der to ensure that they work together effectively and
• Programme management is more than just a named remain collectively focused on the achievement of
role. Given a range of contexts in which programme overall business benefit.
management can benefit an organisation, individuals • Effective programme management needs to take into ac-
with a variety of different official role titles may prac- count power dynamics. Programme management is not
tise the discipline of programme management. Broad always recognised as being in the best interests individ-
ranging communications and training are thus re- uals in positions of power. It is important to anticipate
quired in order to leverage the full benefit of the potential issues related to the perceived power dynamic
approach. between project sponsors, project managers the pro-
• Effective programme management is relationship- gramme manager and manage the relationships ac-
based. Programme management should focus on cre- cordingly. In particular, it is important to be aware
ating a context that enables project managers to be that goals defined at the programme level may become
successful, facilitating the stakeholder relationships incompatible as they translate into objectives at the
that support this. In the context of a changing envi- project level. The paradox of goal deconstruction
298 M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299

arises in spite of the fact that each individual activity re- • Missed opportunities in terms facilitating genuinely
mains connected to the same set of high-level goals and effective co-operation and shared learning between
often leads to conflicting priorities and dysfunctional project managers.
relationships. Programme management must thus fa- In terms of the mechanical components of the
cilitate the adjustment of specific project objectives in standard programme management approaches, these
order to ensure that individual projects contribute in issues can be related to the insistence on a rigid pro-
a coherent way to the achievement of the overall pro- gramme hierarchy; the assumption of a linear pro-
gramme goals and benefits. gramme lifecycle; and utilisation of a set of tools and
• Effective programme management enables adaptability techniques that are functionally indistinct from their
in the context of a changing business environment. Pro- project management equivalents. It is our contention
grammes often develop incrementally rather than by that what is required to address these issues is pro-
design, which requires a dynamic and flexible view gramme management research and practice that fo-
of the programme lifecycle and overall definition of cuses on the management of relationships and enables
the programme. By mapping the constituents of a the incremental development of a programme over
programme against a series of high-level lifecycle time.
states and monitoring and controlling the transitions
between those states a focus on the high level under-
standing of the overall goals and direction of the pro-
gramme can be maintained as well as a focus on how References
individual component projects contribute towards
this. A programme lifecycle must provide a clear sep- [1] Evaristo R, van Fenema PC. A typology of project management:
aration between the justification of individual pro- emergence and the evolution of new forms. Int J Project Manage
jects within the programme and the justification of 1999;17(5):271–81.
[2] Van Der Merwe AP. Multi-project management – organisational
the programme as a whole. Individual projects may control. Int J Project Manage 1997;15(4):223–223.
derive a proportion of their benefits case based on [3] Senior B. Organisational change. Harlow, UK: Prentice-Hall;
their contribution to a programme; the programme 1997.
as a whole is justified on the basis of the cumulative [4] Kerzner H, Cleland DI. Project/matrix management policy and
benefits case of its confirmed component projects. strategy. New York: Van Nostrand Rheinhold; 1985.
[5] Payne JH. Management of multiple simultaneous projects: a state-
Whilst change control is applied at the individual of-the-art review. Int J Project Manage 1995;17(1):55–9.
project level, the focus at the programme level should [6] Platje A, Seidel H. Breakthrough in multiproject management:
be on strategic alignment and business change how to escape the vicious circle of planning and control. Int J
management. Project Manage 1993;11(4):209–13.
[7] Pellegrini S. Programme Management: organising project based
change. Int J Project Manage 1997;15(3):141–9.
[8] OGC. Managing successful programmes. Office of Government
Commerce; 1999.
5. Conclusions [9] McElroy W. Implementing strategic change through projects. Int
J Project Manage 1996;14(6):325–9.
This paper has argued that programme manage- [10] Pellegrini S, Bowman C. Implementing strategy through projects.
Long Range Planning 1994;27(4):125–32.
ment is far more than just the management of large [11] Grundy T. Strategy implementation and project management. Int
projects. Through a critical review of the literature, it J Project Manage 1998;16(1):43–50.
was recognised that a unique perspective and ap- [12] Cooper KG, Lyneis JM, Bryant B. Learning to learn, from past to
proach is required in order to address the cultural, future. Int J Project Manage 2002;20(1):213–9.
political and organisational challenges at the pro- [13] Cooke Davies T. The ÔrealÕ success factors on projects. Int J
Project Manage 2002;20(3):185–90.
gramme level. The paper has noted that the weak- [14] Gray RJ. Alternative approaches to programme management. Int
nesses of standard programme management techniques J Project Manage 1998;15(1):5–9.
can be traced back to two erroneous assumptions, [15] Haughey D. A perspective on programme management. Project
namely that: (a) project management and programme Smart Website; 2001.
management are essentially equivalent; and (b) that a [16] Strange G. Programme management in IBM. The Programme
Management Group; 2001.
single standard approach to programme management [17] Partington D. The project management of organisational change.
is applicable in all circumstances. Specific issues that Int J Project Manage 1996;14(1):13–21.
arise as a result of these flawed assumptions include: [18] Thiry M. Combining value and programme management into an
• A dysfunctional and bureaucratic mode of pro- effective programme management model. Int J Project Manage
gramme management due to an excessive control 2002;20(3):221–7.
[19] Gray RJ, Bamford PJ. Issues in programme integration. Int J
focus. Project Manage 1999;17(6):361–6.
• Ineffective alignment between programmes and an [20] Reiss G. Programme management demystified: managing multiple
evolving business context. projects successfully. London: E&FN Spon; 1996.
M. Lycett et al. / International Journal of Project Management 22 (2004) 289–299 299

[21] Levene RJ, Braganza A. Controlling the work-scope in organi- [26] Moss-Kanter R. When giants learn to dance. London: Unwin
sational transformation: a programme management approach. Int Paperbacks; 1989.
J Project Manage 1996;14(6):331–9. [27] Frame JD. Managing projects in organisations. San Francisco:
[22] Mintzberg H, Waters JA. Of strategies, deliberate and emergent. Jossey-Bass; 1995.
Strategic Manage J 1985;6(3):257–72. [28] Gareis R. May the PMBOK Guide be challenged by the new
[23] Eskerod P. Meaning and action in multi-project environment: programme management paradigm? In Proceedings of the 30th
understanding a multi-project environment by means of meta- PMI seminars and symposium. Newton Square, PA: PMI HQ
phors and basic assumptions. Int J Project Manage 1996;14(2):61– Publishing; 1999.
5. [29] Sharad D. Management by projects, an ideological breakthrough.
[24] Lord A. Implementing strategy through project management. Project Manage J 1986;(March):61–3.
Long Range Planning 1993;26(1):76–85. [30] Payne JH, Turner JR. Company-wide project management: the
[25] Halachami A, Holtzer M. Merit pay, performance, targeting and planning and control of programmes of projects of different type.
productivity. Rev Personnel Admin 1987;7:80–91. Int J Project Manage 1998;17(1):55–9.

Вам также может понравиться