You represent Acme Technology and are hiring a subcontractor to assist you in
installing a network with desktop computers, monitors, printers, servers, cabling
and software in an office building.
This is the culmination of the term project. In this final assignment, you will take
the information that you entered in Part 3 of the term project and create a
project network diagram showing the schedule in a graphic format, using the
Activity-on-Node method.
Activity C
Duration: Activity B
18 days Duration:
(17, 35) lgth of proj.
[82, 100] (0, 295)
Activity H [0, 295]
Duration:
Activity D 38 days
Duration: (201, 239)
83 days [201, 239]
Activity A (17, 100) Activity G Activity J Activity K
Duration: [17, 100] Duration: Duration: Duration:
17 days 101 days 18 days 38 days
(0, 17) (100, 201) (239, 257) (257, 295)
[0, 17] Activity E [100, 201] [239, 257] [257,295]
Duration: Activity I
78 days Duration:
(17, 95) 38 days
[22, 100] (201, 239)
[201, 239]
Activity F
Duration:
18 days
(17, 35)
[82, 100]
* in TermProj3 I gave the duration as a high/low number, for simplicity’s sake I used the average of
that time frame rounded up