Академический Документы
Профессиональный Документы
Культура Документы
0015/ND
Once downloaded this document becomes UNCONTROLLED. Please check the website below for the current version.
2 1 0 REVISION
Technical Policy Board Technical Policy Board Technical Policy Board AUTHORISED BY
www.gl-nobledenton.com
PREFACE
This document has been drawn with care to address what are likely to be the main concerns based on the experience of the GL Noble Denton organisation. This should not, however, be taken to mean that this document deals comprehensively with all of the concerns which will need to be addressed or even, where a particular matter is addressed, that this document sets out the definitive view of the organisation for all situations. In using this document, it should be treated as giving guidelines for sound and prudent practice on which our advice should be based, but guidelines should be reviewed in each particular case by the responsible person in each project to ensure that the particular circumstances of that project are addressed in a way which is adequate and appropriate to ensure that the overall advice given is sound and comprehensive. Whilst great care and reasonable precaution has been taken in the preparation of this document to ensure that the content is correct and error free, no responsibility or liability can be accepted by GL Noble Denton for any damage or loss incurred resulting from the use of the information contained herein.
0015/ND REV 2
Page 2
CONTENTS
SECTION 1 2 PAGE NO. 5 6 6 6 6 6 6 8 8 8 8 8 9 9 9 9 10 10 10 10 10 11 11 12 12 13 14 14 14 14 15 15 15 16 16 16 16 17 17 17 17 18 18 18 19 19 19 19 Page 3 INTRODUCTION DESIGN STORMS 2.1 PURPOSE 2.2 DESIGN STORM FOR CONSTRUCTION AFLOAT 2.3 DESIGN STORM FOR TOWAGE ROUTE 2.4 DESIGN STORM FOR SHORT DURATION OPERATIONS 2.5 DESIGN WIND, WAVE AND CURRENT STRUCTURAL STRENGTH 3.1 LOADCASES 3.2 REINFORCED CONCRETE 3.3 STRUCTURAL STEEL 3.4 COMPRESSED AIR MOTION RESPONSES 4.1 PURPOSE 4.2 MOTION RESPONSE COMPUTER PROGRAMS 4.3 HUMAN LIMIT STABILITY AND FREEBOARD 5.1 INTACT STABILITY FOR BASE SECTION TOW-OUT AND TOWAGE TO CONSTRUCTION SITE 5.2 DAMAGE STABILITY FOR BASE SECTION TOW-OUT AND TOW TO INSHORE CONSTRUCTION SITE 5.3 INTACT STABILITY AND FREEBOARD DURING CONSTRUCTION AFLOAT 5.4 DAMAGE STABILITY DURING CONSTRUCTION AFLOAT 5.5 INTACT STABILITY FOR TOWAGE TO OFFSHORE SITE 5.6 DAMAGE STABILITY FOR TOWAGE TO OFFSHORE SITE 5.7 TOWAGE OF COMPLETED GRAVITY BASE SECTION TO DECK MATING SITE 5.8 INCLINING TESTS BUILDING BASIN FLOAT OUT 7.1 UNDERKEEL CLEARANCE FOR LEAVING BASIN 7.2 SIDE CLEARANCES 7.3 UNDERKEEL CLEARANCE OUTSIDE BASIN INSHORE MOORINGS 8.1 MOORING FORCES 8.2 LOADS IN MOORING SYSTEM 8.3 SYSTEM MANUFACTURE 8.4 REDUNDANCY 8.5 END FITTINGS 8.6 ANCHORS DECK MATING AFLOAT 9.1 MINIMUM FREEBOARD OF SUBSTRUCTURE FOR SHELTERED LOCATIONS 9.2 HORIZONTAL RESTRAINT 9.3 BALLASTING PROCEDURES AND EQUIPMENT TOWAGE TO OFFSHORE SITE 10.1 TOWAGE PHILOSOPHY 10.2 MINIMUM ALLOWABLE CHARTED WATER DEPTH 10.3 USE OF AIR CUSHION TO INCREASE UNDERKEEL CLEARANCE 10.4 USE OF TIDAL RISE TO INCREASE UNDERKEEL CLEARANCE 10.5 CHANNEL WIDTHS IN SHELTERED AREAS 10.6 CHANNEL WIDTHS IN EXPOSED LOCATIONS
6 7
10
0015/ND REV 2
11
0015/ND REV 2
Page 4
1
1.1
INTRODUCTION
These guidelines have been developed by GL Noble Denton for the marine aspects of construction, towage and installation of offshore concrete Gravity Base Structures (GBS) with a deck. They are intended to be applicable to deep draft structures, where much of the construction work is carried out afloat, as well as shallower draft structures where the construction of the GBS can be essentially completed in dry dock. Revision 0 of this report, dated 5 October 1987, superseded Report L6289/NDA/RLJ of 28th February 1978. Revision 1 superseded Revision 0. The principal change was reformatting and removing references to NDI (Noble Denton International). This Revision 2 supersedes Revision 1. The principal changes are: the expansion of the text on design waves in Section 2.5 most of the offshore towage recommendations have been transferred to 0030/ND (Guidelines for Marine Transportations) which takes precedence over these guidelines. rebranding as GL Noble Denton. 2
1.5
As each platform will probably differ in design, building location and destination, detailed recommendations will apply to individual cases. However, this document is submitted for general guidance during project development and it is emphasised that discussions with this office at an early stage would be desirable. The general philosophy is that the unit and associated equipment should survive in extreme seasonal 100 year return conditions for long operations such as construction afloat, and in seasonal 10 year return conditions for towages. For short operations that need favourable weather, the unit should be able to achieve a safe condition within the period of a suitable weather forecast. These guidelines are intended to lead to an approval by GL Noble Denton. Such approval does not imply that approval by designers, regulatory bodies, harbour authorities and/or any other parties would be given.
1.6
1.7
0015/ND REV 2
Page 5
2
2.1
2.1.1
DESIGN STORMS
PURPOSE
Design storms shall be defined for construction afloat, for towages and for short duration operations, to provide a basis for determination of responses of the unit, for computation of loadings on the structure and superstructure, for the design of moorings and to determine stability requirements.
2.2
2.2.1
2.3
2.3.1
2.3.2 2.3.3
2.4
2.4.1
2.5
2.5.1 2.5.2 2.5.3
2.5.4
2.5.5
0015/ND REV 2
Page 6
2.5.7
2.5.8
Constant K 22 23 24 25 26 27 28 29 30
2.5.9
The design current shall be the rate at mean spring tides, taking account of variations with depth and increases caused by the design storm and storm surge.
0015/ND REV 2
Page 7
3
3.1
3.1.1
STRUCTURAL STRENGTH
LOADCASES
Loadcases shall be derived by the addition of fluctuating loads resulting from wind, wind heel, wave action and the effect of towline pull to the static forces resulting from gravity and hydrostatic loads. Specific loadcases shall be agreed with GL Noble Denton. The unit shall also be able to withstand the static and dynamic loads caused by the flooding of any one compartment in a 25 metres/second wind and associated waves, or a static heel angle of 10 degrees, whichever is greater. This would be regarded as an extreme condition.
3.1.2
3.2
3.2.1
REINFORCED CONCRETE
The strength of each unit during construction afloat and towage shall comply with a recognised code such as the FIP "Recommendations for the Design and Construction of Concrete Sea Structures" (Fourth Edition 1985) or equivalent.
3.3
3.3.1
STRUCTURAL STEEL
Stresses in structural steelwork shall not exceed those allowed in a recognised code such as AISC "Manual of Steel Construction" (Eighth Edition), NS 3742 or equivalent. Increases in allowable stresses for extreme environmental conditions may be used for events having a probability of occurrence of less than once in 10 years.
3.4
3.4.1
COMPRESSED AIR
The use of compressed air as a basic structural member in the design, for resisting hydrostatic head on internal or external walls during ballasting, or for reducing overall bending moments by an air cushion, is not recommended, except to increase structural safety factors under well controlled conditions.
0015/ND REV 2
Page 8
4
4.1
MOTION RESPONSES
PURPOSE
The behaviour of the unit shall be determined by means of computer calculations or model tank testing, in order to determine the response to environmental loadings for construction, towage and installation, as appropriate. In particular, the responses should be determined, or shown to be negligible, for the following conditions; a. b. c. d. e. For departure from building basin, and towage to floating construction site. For all stages of construction afloat. For deck mating operations. For towage to offshore site, at all likely towage drafts. For installation at final location.
4.2
4.3
HUMAN LIMIT
To enable personnel to go about their duties efficiently, care be should taken to avoid accelerations in excess of 0.2g except for occasional short periods.
0015/ND REV 2
Page 9
5
5.1
5.1.1 5.1.2
5.1.3
The wind used for overturning moment calculations shall be the design wind for the tow-out and towage operations, as defined in Sections 2.4 and 2.5.1.
5.2
5.2.1
DAMAGE STABILITY FOR BASE SECTION TOW-OUT AND TOW TO INSHORE CONSTRUCTION SITE
The base section shall have one compartment damage stability. After damage, when subjected to a wind of 25 metres per second, or the design wind for the operation if less, a freeboard of not less than 1 metre above the crest of the maximum design wave shall remain.
5.3
5.3.1
5.3.2
5.3.3
The initial metacentric height (GM) shall be positive, and shall be such that the inclination of the unit in the design storm shall not exceed 5 degrees, taking into account the effect of mooring line tensions where appropriate. The area under the righting moment curve shall be not less than 140 percent of the area under the overturning moment curve. Both curves shall be bounded by the least of; a. the second intercept of the righting and overturning moment curves, b. c. the angle of downflooding or the angle which would cause any part of the unit to reach maximum allowable stresses.
5.3.4
The wind used for overturning moment calculations shall be the design wind for construction, as defined in Sections 2.2 and 2.5.1.
5.4
5.4.1 5.4.2
0015/ND REV 2
Page 10
5.5
5.5.1
shall not exceed 5 degrees. 5.5.2 The maximum inclination of the unit in the design storm conditions (), computed as the sum of the following: a. Maximum amplitude of motion in the design seastate, with an assumed duration of 3 hours, plus b. 5.5.3 Inclination due to the design wind speed, corrected for height as appropriate, shall not exceed 5 degrees. The static inclination in still water when subjected to 50 percent of TPR shall not exceed 2 degrees. Differential ballasting may normally be used to reduce by up to 50 percent the static angle of heel resulting from towline pull only. The static range of stability shall not be less than (20 + 0.8) degrees, where is the angle computed in Section 5.5.2. The area under the righting moment curve shall be not less than 140 percent of the area under the overturning moment curve. Both curves shall be bounded by the least of; a. the second intercept of the righting and overturning moment curves, or b. c. the angle of downflooding, or the angle which would cause any part of the unit to exceed maximum allowable stresses.
5.5.4 5.5.5
The wind used for overturning moment calculations shall be the design wind for towage, as defined in Sections 2.3 and 2.5.1.
5.6
5.6.1
5.6.2
0015/ND REV 2
Page 11
5.7
5.7.1
5.8
5.8.1
INCLINING TESTS
The metacentric height (GM) shall be established before deck emplacement and also before the start of any towage. Normally two and possibly more inclining experiments may be needed, dependent on procedure and scatter of results.
0015/ND REV 2
Page 12
6
6.1.1 6.1.2
BUILDING BASIN
The surrounding walls of the construction basin shall be properly designed in accordance with accepted civil and geotechnical engineering practice. Where materials are used whose stability characteristics can be affected by a change in pore water pressure, suitable monitoring devices shall be installed and the retrieved data analysed by competent geotechnical engineers to ensure continuing stability of the wall throughout the period of the platform construction. In particular, consideration shall be given to the design of the basin walls, including but not limited to the following; a. The integrity of the walls shall remain stable when subjected to: b. c. d. The highest astronomical tide, plus 10 year return storm surge, plus 10 year return maximum wave crest height, corrected for shoaling if applicable.
6.1.3
The walls shall be of adequate height to prevent overtopping, except by spray, in the above conditions. Walls shall be protected against the effects of collision, propeller scour and wave action. The effects of ice loading shall be considered if appropriate.
6.1.4
Pumping capacity shall be adequate for maximum seepage, rainfall and spray overtopping.
0015/ND REV 2
Page 13
7
7.1
7.1.1
FLOAT OUT
UNDERKEEL CLEARANCE FOR LEAVING BASIN
When leaving the building basin, the unit shall have a minimum underkeel clearance, using tidal rise if necessary, of at least 0.5 metres for the duration of an adequate period for float out, including contingencies. This would normally be of the order of 3 hours before, to 3 hours after high water. Compressed air may be used to reduce draft if required, subject to the requirements of Section 10.3. A tide gauge shall be installed on site to check that actual tidal levels correspond to those predicted.
7.1.2 7.1.3
7.2
7.2.1
SIDE CLEARANCES
Depending on the positional control of the unit during the exit of the basin, the channel width at full depth shall not be less than: 1.2 x B when inside the basin, and 2 x B when out of the basin, where B = maximum beam, after allowance for any likely yaw of the unit. Channel width may be reduced if the unit is winched out along a fendered guide.
7.3
7.3.1 7.3.2
0015/ND REV 2
Page 14
8
8.1
8.1.1
INSHORE MOORINGS
MOORING FORCES
In establishing the design wind loading, the effects of shielding and interaction should preferably be obtained from wind tunnel test data. For the shafts of a gravity based unit, the mean 2-dimensional drag coefficient may be obtained from an appropriate theoretical source such as ESDU items 80025 and 81017, provided the higher tolerance (uncertainty) limits are adopted. This coefficient may be reduced for 3-dimensional flow where no deck is present. The wind gradient should be determined from a code of practice agreed with the relevant GL Noble Denton office. It should allow for the effects where the platform is exposed to winds over roughened terrain. For large gravity structures having long response periods, the design of the mooring system may be based on quasi-static methods. For exposures in excess of 8 weeks, the mooring forces shall include the environmental loadings due to: The design wind, plus Mean wave drift forces from the design seastate, plus The design current.
8.1.2
8.1.3 8.1.4
8.1.5
For exposures less than 8 weeks, the forces may be determined for the following return periods: Total exposure Return period Up to 2 weeks 2 to 8 weeks 10 year seasonal 20 year seasonal
8.1.6
Mooring forces shall be modified as appropriate for; a. Sheltered directions, b. c. d. Changed mooring geometry after excursion under load, Changes in exposed wind areas if the draft is changed to adopt a survival mode, Changes in exposed wind areas caused by inclination of the unit.
8.2
8.2.1
8.2.2 8.2.3
For a wire rope, the maximum tension shall not exceed 60 percent of the minimum breaking load. For lines containing new synthetic material the maximum tension in the synthetic material shall not exceed 33 percent of the minimum breaking load. This factor may be reduced for long exposures, depending on the material ageing properties.
0015/ND REV 2
Page 15
8.3
8.3.1
SYSTEM MANUFACTURE
All components in a mooring system shall be manufactured within an approved QA/QC system, and to a suitable current standard.
8.4
8.4.1
REDUNDANCY
For all moorings it shall be demonstrated that failure of any one line will not result in any of the following: a. Serious hazard to personnel. b. c. Significant damage to the unit, nearby craft or facilities. Progressive failure of remaining lines or attachments. For this purpose it is recommended that the maximum tensions in the remaining intact lines should not exceed the allowable intact value from Section 8.2 increased by one third.
8.4.2
Measures to obtain an equivalent level of safety by means other than redundancy by, for example, using very low material utilisation factors in the intact case, may be considered.
8.5
8.5.1
END FITTINGS
All wire and synthetic ropes shall have hard eyes or other approved end fittings.
8.6
8.6.1
ANCHORS
The holding capacity at the intended site, and strength (using standard design codes) of any anchor, winch or connection to the unit shall exceed the extreme storm loading on it including the effect of one line failure if considered in Section 8.4. Also the ultimate strength of all connections to the unit and anchorages shall be not less than the breaking load of the wire rope or chain in use.
0015/ND REV 2
Page 16
9
9.1
9.1.1
9.1.2 9.1.3
9.1.4
9.1.5
The time at the maximum draft, when reserve buoyancy is at a minimum, should be as short as possible. The maximum allowable duration of immersion should be established in relation to the structural stability of the unit, and deck emplacement procedures planned accordingly. Additional freeboard will be required to allow for the response of the unit, unless pitch, roll and heave can be shown to be negligible under the conditions expected. The substructure without the deck shall be able to deballast to a freeboard at which the unit has damage stability within 24 hours. An initial deballasting capability of not less than 2 metres per hour is recommended. It should be possible to deballast the deck off the barges within a good weather forecast period. If this is not practicable then the substructure/deck/barge combination shall be able to survive a 10 year return period seasonal storm at an intermediate condition. Provision shall be made for detection of any likely movements of fresh water (freshets) that could cause significant draft changes. The unit shall always be able to deballast if necessary to maintain freeboard.
9.2
9.2.1 9.2.2
HORIZONTAL RESTRAINT
Horizontal restraint shall be provided between the deck and the substructure to absorb any shock load during mating and to prevent lateral movement of the deck after initial engagement of the two parts. The horizontal restraint shall, within the period of the weather forecast for deck mating, be made capable of taking the loads resulting from the inclination due to the design storm, or an inclination of 5 degrees, whichever is the greater, at any applicable draft.
9.3
9.3.1 9.3.2
0015/ND REV 2
Page 17
10
10.1
10.1.1 10.1.2 10.1.3 10.1.4
10.2
10.2.1
10.2.2
The maximum static draft shall be the actual measured draft at the deepest point with allowances for the effects of the following: a. Errors in measurement, b. c. Initial trim, Water density changes.
10.2.3
The motion allowance shall be the maximum increase in draft due to the effects of any or all of the following: a. Towline pull, b. c. d. e. Wind heel or trim, Roll or pitch, Heave, Squat.
10.2.4 10.2.5
For any tow, except for towage out of a building basin, the underkeel clearance shall be not less than 2 metres, or 10 percent of maximum static draft, whichever is the lesser. Provided the underkeel clearance is 2 metres or more, no further allowance for negative surge need be made.
0015/ND REV 2
Page 18
10.3.2
10.4
10.4.1
10.5
10.5.1
10.6
10.6.1
10.7
10.7.1
SURVEY REQUIREMENTS
Tow routes shall be covered by modern surveys, including sidescan sonar where possible. Open water passages in charted water depths of less than 200 metres should have surveyed channels at least 5 kilometres wide. Current surveys should be made in restricted parts of the route and at the final location.
10.7.2
10.8
10.8.1
10.8.2
10.8.3 10.8.4
0015/ND REV 2
Page 19
10.9
10.9.1
10.9.2
Recovery arrangements shall be available for each bridle or pennant, for reconnection. Where a leg of a vertical bridle is only needed for manoeuvring at one end of a passage, and is slack at other times, the breaking load of that leg should be at least twice the maximum static resolved load. Adequate connecting points shall be fitted to allow attachment of positioning tugs during emplacement on location. At least one spare connection, with pennant should be fitted for towing forward, unless the loss of any one tug or its connection to the unit would not reduce the available towing force to less than 80 percent of that required by Section 10.8.
10.10
10.10.1
GUARDSHIP
It is recommended that each unit be accompanied by a "Guardship" whilst under tow to reduce the possibility of the tow being approached, hampered or jeopardised by unauthorised traffic.
0015/ND REV 2
Page 20
11
11.1
11.1.1 11.1.2
11.2
11.2.1 11.2.2
REDUNDANCY
The design of the ballasting system shall be such that the failure of any one valve to open or close, or the fracture of any pipe, will not cause flooding of the unit, or failure to flood when required. All remotely controlled valves shall be capable of operation by a secondary, preferably manual system. Any automatic or radio controlled system shall have a manual override system.
11.3
11.3.1 11.3.2
INLETS
All internal and external inlets shall be adequately protected to prevent damage by entering debris and cables. All internal compartments must be cleaned of debris before immersion or towage starts. For deep immersion each opening shall be blanked with a double flange or a system of comparable integrity. The inner flange, in many cases, may be removed for towage provided the seal has been pressure and suction tested and can withstand likely wave action. PIPEWORK All essential pipework shall be of permanent-type construction and hydrostatically tested to a minimum of 1.3 times the design pressure. Temporary flexible hoses are not permitted.
11.3.3
11.3.4
UMBILICALS If umbilicals are necessary to provide power and/or hydraulic services during immersion, adequate back-up capability shall be provided, and fail-safe systems shall be incorporated into critical valve controls. INSTRUMENTATION Adequate instrumentation shall be installed to measure the water level in each compartment.
11.3.5
0015/ND REV 2
Page 21
AIR CUSHION
The following recommendations will apply to the use of underskirt compressed air: All piping shall be secure, protected and of adequate capacity and strength. Supply lines shall have non-return valves. Back-ups shall be provided for all critical valves and piping. Adequate reserve compressors shall be onboard. A venting system shall be provided to guarantee that all air is removed after use to ensure no residual free surface remains. Sufficient water seal (bottom of air cushion above bottom of skirt) shall be available to prevent air escaping. A reliable method of measuring the water seal shall be provided.
0015/ND REV 2
Page 22