Вы находитесь на странице: 1из 7

294 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO.

2, MAY 2001

Reactive Power as an Ancillary Service


Kankar Bhattacharya and Jin Zhong

Abstract—This paper addresses the problem of reactive power with NGC and are paid for both the capability and utilization
procurement by an independent system operator (ISO) in dereg- components [1].
ulated electricity markets. A reactive bid structure is proposed In the New York system, the ISO (NYISO) is responsible
in the context of a reactive power market. Based on the reactive
power price offers and technical constraints involved in reactive for procuring reactive power support service, and the service is
power planning, a two-tier approach is developed to determine provided at embedded cost-based prices. Generating resources,
the most beneficial reactive power contracts for the ISO. The which operate within their capability limits, are directed by the
reactive capability of a generator and therefore the opportunity ISO to produce or absorb reactive power to maintain voltages
costs in providing reactive power is also included in the model. within limits [3]. Further, the NYISO also provides for com-
Uncertainty in reactive demand and in reactive bids of partici-
pating parties is incorporated through Monte Carlo simulations pensation to generators in case of revenue lost due to increased
and the expected reactive power procurement plan for the ISO is reactive power generation requests. If the ISO dispatches or di-
hence determined. The CIGRÉ 32-bus network, approximately rects a generator to reduce its real power output the generator
representing the Swedish system, is used for the studies. receives a Lost Opportunity Cost (LOC) for the amount of rev-
Index Terms—Ancillary services, deregulation, independent enue it loses from the lost generation and energy sell.
system operator (ISO), Monte Carlo simulation, reactive power. The Australian electricity market and its ISO (NEMCO) also
recognizes reactive power as an ancillary service and financial
compensation is provided to generators and synchronous com-
I. INTRODUCTION
pensators for their service provisions [4]. All reactive support

I N A DEREGULATED power system, the basic responsi-


bility of the Independent System Operator (ISO) is to main-
tain system reliability and security by providing for ancillary
providers are eligible for the availability payment component-
for their preparedness to provide the service when called for.
Synchronous compensators also receive the enabling payment
services such as reactive power support, spinning reserves, en- component- paid when their service is activated by the ISO for
ergy balancing and frequency regulation. use. On the other hand a generator receives the compensation
Sufficient reactive power support need to be provided in payment component- which is based on its opportunity cost and
the system in order to maintain the power flow limits on paid when it has been constrained from operating according to
transmission lines and voltage limits at bus bars. Also, since it its market decisions. For example if a generator has to provide
is not desirable to transport reactive power over the network, reactive power where it has to reduce its real power generation
it should be procured at different locations in the system in order to operate within the unit’s field and armature winding
depending upon perceived demand conditions, mix of the heating limits, the generator will be compensated for its lost
load and availability of reactive support devices. Such devices real power generation. This payment component is similar to
however, have different characteristics for example, generators the LOC payment made in NYISO.
are fast acting reactive support devices with high operating and These developments in the deregulated electricity markets in-
opportunity costs, while capacitors are slow devices with lower dicate the trend toward treating reactive power as ancillary ser-
installation and operating costs. vices and creating financial compensation schemes for reactive
Many of the deregulated markets are yet to establish a mech- power providers.
anism for financial compensation for reactive power ancillary In the same context therefore, it is also important that the
services e.g., the Nordic countries. On the other hand, some ISO identifies its reactive power requirements and device ap-
markets do have schemes for payment for reactive support ser- propriate criteria for selecting the reactive power provider. For
vices. In UK, the National Grid Company, which carries out the example, procurement of reactive power involves payments to
functions of the ISO, invites tenders for reactive support ser- be made by the ISO. Thus the ISO could seek those providers
vices. The generators can bid for reactive power support through which minimize its total payments. Although this is a seemingly
bids composed of capacity components (price per MVAr and fair enough objective, this criterion could result in increased re-
quantity on offer) and an utilization component (MVAr-h price active flows on the network and hence increased energy losses
curve). The selected bidders get into annual bilateral contracts in the system or even require curtailment of contracted trades.
Increased energy loss will require the ISO to procure loss com-
pensation services thus involving additional payments, which is
Manuscript received September 11, 2000. This work was supported by the undesirable.
Sydkraft Research Foundation, Sweden, for the research project on ancillary Complexities also arise when the ISO procures reactive power
ervices pricing. from independent generators, which are business entities. If the
The authors are with the Department of Electric Power Engineering Chalmers
University of Technology S-41296 Gothenburg, Sweden. ISO requires such a generator to increase its reactive power, de-
Publisher Item Identifier S 0885-8950(01)03795-6. pending upon the operating point, it might have to reduce its real
0885–8950/01$10.00 © 2001 IEEE
BHATTACHARYA AND ZHONG: REACTIVE POWER AS AN ANCILLARY SERVICE 295

Fig. 2. Generator’s expectation of financial compensation.

will hence incur revenue loss (RL), which needs to be compen-


Fig. 1. Synchronous generator capability curve.
sated net of its cost savings from reduced generation, expressed
as follows:
power generation in order to adhere to the field current limits in
the rotor. With this backing down of generation, the generator RL (3)
will not be able to fulfill the contracted trades.
where, is the real power price, and is the generation cost
In this paper we attempt to determine an appropriate scheme
as a function of production.
applicable to the ISO for procurement of reactive support from
If the operating point lies inside the limiting curve, say at
independent providers.
( ) then the unit can increase its reactive generation
from up to without incurring any additional cost, rev-
II. GENERATOR REACTIVE POWER CAPABILITY enue loss or real power generation shift.
The power output of a generator is usually limited to a value
within the MVA rating by the capability of its prime mover. III. REACTIVE BID STRUCTURE
When real power and terminal voltage is fixed, its armature and In many deregulated markets, the ISO has a limited access
field winding heating limits restrict the reactive power genera- to information on generators and hence may not be able to de-
tion from the generator. The armature heating limit is a circle termine a generator’s revenue loss, which requires information
with radius , centered on the origin , and on real power price (sometimes bilaterally fixed) and generator
given by, cost function. An appropriate option in such markets is to call
for reactive bids from generators.
(1) We discussed regions on the reactive power coordinate in the
previous section, which are now explicitly defined here to for-
The field heating limit is also a circle, centered at mulate the generator’s expectation of payment function. From a
, radius and given by (2) knowledge of generators expectation of payment, the ISO can
(Fig. 1) [5] call for reactive bids from all parties.
Region-I: : Reactive power
output in this range is used by the generator to meet its own
(2) requirements such as in boiler feed pump motors, circulating
water system pump motors, ID fan and FD fan motors, step-up
is the voltage at the generator terminal bus, is the steady- transformers, etc. The generator is not entitled to receive any
state armature current, is the excitation voltage and is payment for reactive power generation in this range.
the synchronous reactance. and are real and reactive power Region-II: : This region denotes
generation from the machine, respectively. The machine rating the reactive power that a generator provides over without
in MVA, is the point of intersection of the two circles (“ ” in rescheduling its real power output. Though there is no increased
Fig. 1). The corresponding real power generation is denoted by cost due to the additional reactive output, the generator expects a
. When the limit on reactive power is imposed by payment for making available its service. This payment is made
the generator’s field heating limit (2) while, when at a constant rate on a per MVAr basis, and analogous to the
the armature heating limit (1) imposes restricts the generators capacity charge.
reactive power output. There is also an under-excitation limit, Region-III: : This region denotes
, to restrict the unit operation in under-excited mode due the reactive power which a generator supplies, at the expense
to localized heating in the end region of the armature. of reducing its real power output. The generator stands to lose
Consider the operating point ( ) on the limiting revenue from loss of power sell. The payment that the generator
curve defined by (2). If more reactive power is required from the expects from the ISO for this reactive support service will be
unit, say , the operating point requires shifting back along proportional to the amount of reactive support it provides and at
the curve to point ( ), where . This signifies a rate determined by its revenue loses as given by (3).
that the unit has to reduce its real power generation to adhere to A typical expectation of financial compensation function can
field heating limits when higher reactive power is demanded. It accordingly be shown as in Fig. 2. As seen from Fig. 2, the
296 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO. 2, MAY 2001

financial compensation and vis-á-vis the reactive bids called for, Subject to the Following Constraints:
by the ISO, will require being in two parts, a constant term and Load Flow Equations:
one proportional to reactive power.
This can be expressed mathematically as follows: (6)

(7)

gen (4)
Contracted real power generation at bus , p.u.
is the bid-price from an independent generator , is Actual real power transaction between load at bus
the fixed component of bid price in $/MVAr and is the and generators, gen
variable price proportional to reactive support provided in Reactive power support at bus , p.u
$/MVAr/MVAr. It is to be noted that unlike the usual two-part Reactive power demand at bus , p.u
tariff structures, the above bid structure is different since the Element of network and admittance matrix, p.u
variable component payment is applicable only after complete Angle associated with , radians
utilization of reactive capacity from the constant price bid Bus Voltage Limits:
component.
(8)
IV. REACTIVE POWER PROCUREMENT
Limit on Bilateral Transactions:
With a reactive bid structure established, the ISO requires a
proper criterion to determine the best offers and hence formulate (9)
its reactive power procurement plan.
Unlike real power markets where bids are selected in is the contracted real power transactions by a load at
ascending order of prices, reactive power markets need to bus with a generator .
incorporate the location aspects also. For example, a low priced The bilateral transactions are modeled using the method dis-
reactive bid at a bus remotely located, is not an attractive cussed in [6].
option for the ISO. Such a reactive support may prove to be Reactive Power Capability Limit of Generators:
detrimental for the system while also increasing transmission
losses.
(10a)
Therefore the ISO needs to consider both the technical
aspects involved in reactive support allocation as well as the
(10b)
bid price offers from parties and arrive at an optimal contract,
best suited to the system. A two step approach proposed and Equation (10a) is applicable when the field heating limit acts as
presented below to address this problem: the upper limit (i.e., for ) and (10b) when the armature
Step-I: The ISO determines the marginal benefit of each heating limit is applicable (i.e., for ).
reactive bid with regard to system losses. The ISO Lower Limits on Reactive Power Generation: As mentioned
shall seek to minimize losses lest, it would require in Section II, the under-excitation limit, , is fixed a priori
to procure higher loss compensation services (also and hence the lower limit of reactive power generation is gov-
involving payments). erned by the constraint,
Step-II: With the marginal benefit of each reactive bid
known to the ISO, it seeks to maximize a societal (11)
advantage function (SAF) formulated by incorpo-
rating the price bid offers at this stage. 1) Duals Associated with Reactive Power Constraints: For
the modified OPF described by equations (5)–(11), we use
A. Marginal Benefit from a Reactive Support Service three sets of lagrange multipliers associated with the three
The marginal benefit to the system from one unit of reactive reactive power constraints (7), (10), (11) to derive important
support at a bus from a reactive bid can be determined from conclusions.
the duals of the system constraints applied to appropriate OPF a) : Dual of Reactive Balance Constraint: This param-
models representing the grid. Consider the following modified eter is obtained from the dual of the reactive power balance (7)
OPF: and denotes the sensitivity of the system loss parameter to reac-
Minimize: System transmission losses given by, tive demand changes at a bus.
is in units of MW/MVAr denoting the change in MW loss
(5) per MVAr change in reactive demand. is multiplied with a cost
parameter (in $/MW) denoting the valuation of reduced loss,
to obtain the marginal benefit. Thus the marginal benefit to the
is the conductance of line , p.u. ISO from a change in reactive demand at a bus is given by,
bus voltage, p.u.
voltage angle, radians. MB in /MVAr (12)
BHATTACHARYA AND ZHONG: REACTIVE POWER AS AN ANCILLARY SERVICE 297

b) : Dual of Generator Reactive Capability Con- Reactive Power Generation Limits: In Section IV-A we con-
straint: When the generator is operating at its reactive sidered that the upper limit on reactive power is constrained by
capability limits, it is of interest to know how the system will the field or armature heating limits. Now we consider that the
benefit if it chooses to increase its reactive generation beyond generator is willing to reduce its real power output from to
this point. The dual of the constraint (10a) and (10b) obtained (refer Fig. 1) in order to provide higher reactive power (for
while minimizing system loss provides important information a price). The constraint (16) states that the maximum reactive
on these lines. support available from a generator is for an operating point,
Thus, indicates by how much the system loss will
change for a unit change in generator reactive power capability.
indicates that the reactive power generation is below (16)
that specified by the field/armature current limits (i.e., if
, ). If , it indicates that the system Reactive Power Generation Limits: According to the three
losses will reduce if reactive generation at the bus is increased regions on the reactive power domain, discussed in Section III,
(i.e., ), which is only possible by reducing real the reactive power output from a generator can be classified
power generation. If , it indicates that the system losses in any of the three components: , or , to represent re-
will increase if reactive generation is increased It is then not gions I, II or III, respectively. The governing algebraic relations
desirable to provide additional reactive power by reducing real between them can be written as follows
power generation.
(17)
The marginal benefit to the ISO from a generator supplying
reactive power at its field/armature winding heating limit is
given by,
(18)
MB /MVAr (13)
(19)
c) : Dual of Reactive Power Constraint on Lower
Limit: This parameter is the dual associated with reactive , and are binary variables for the discrete selection
constraint (11) applicable to reactive lower limits. Therefore, of a reactive component from any of the three regions. Ac-
cording to (19) only one of the binary variables can be selected.
MB /MVAr (14) This automatically restricts that can be in only one of the bid-
ding areas shown in Fig. 2.
B. Societal Advantage Function of the ISO
V. RESULTS AND DISCUSSIONS
Marginal benefit (MB) for reactive support at each bus, and
bid parameters and for each reactive power provider, is The Swedish 32-bus test system [7] (Fig. 3) is used in this
now available to the ISO. Then, we can define the composite work to evaluate the optimal reactive power procurement plan
advantage function for the ISO as follows: for the ISO. The system consists of four major areas:
• North—with basically hydro generation and some load.
SAF • Central—with a large amount of load and rather large
thermal power generation.
• Southwest—with a few thermal units and some load.
• External—connected to the North. It has a mix of genera-
(15) tion and load.

and represent regions II and III mentioned in A. Step-I: Obtain MB from Reactive Support at a Bus
Section III, respectively. SAF in (15) represents the ISOs The marginal benefit from reactive power support at a
viewpoint, seeking contribution to system performance (in bus is obtained by solving the modified OPF discussed in
terms of loss reduction) from reactive power providers with Section IV-A. The model is a nonlinear programming problem
lowest possible cost. and is solved using the high-level programming platform
GAMS and nonlinear programming solver MINOS-5 [8].
C. SAF Maximization: Reactive Power Procurement , and associated with each generator’s reactive power
Once the ISOs composite advantage function is constructed constraint, and discussed earlier in Section IV-A-1, is listed in
as in (15), the optimal reactive power procurement plan can be Table I. The corresponding marginal benefits are determined
obtained from a second level model constructed using the infor- from , and and (12)–(14), assuming /MW.
mation now available. The optimum reactive support, , which evolves from the
Maximize: Societal Advantage Function given by (15). model solution, is also shown. Either the field or armature
Subject to the Following Constraints: winding heating limit, according to the operating condition,
Load Flow Equations: [Equations (6) and (7)] specifies the upper limit while the lower limit is
Bus Voltage Limits: [Equation (8)] fixed apriori. Accordingly, either or assume a nonzero
Limit on Bilateral Transaction: [Equation (9)] value if touches the upper or lower limit, respectively. The
298 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO. 2, MAY 2001

TABLE II
REACTIVE POWER PROCUREMENT PLAN AFTER FINAL OPTIMIZATION

B. Step-II: Final Optimization


The second stage of optimization therefore seeks to find a
compromise between the technically best and a financially safe
solution for the ISO. Marginal benefits and offered bid prices
are used in the final optimization that seeks to maximize the
SAF (15). This problem (stated in Section IV-C) is a mixed-
integer nonlinear programming problem and is solved using the
GAMS/DICOPT solver. GAMS/MINOS5 and GAMS/XA are
invoked by DICOPT as the nonlinear programming and integer
programming solvers, respectively.
The optimal reactive power procurement plan obtained after
Fig. 3. CIGRÉ-32 bus test system network configuration. the second step is listed in Table II. Note that now the reac-
tive power plan at certain buses exceeds (at buses 4071,
TABLE I 4062, 1012 and 1022). These generators will require reducing
MARGINAL VALUES AND OPTIMAL REACTIVE POWER SCHEME
their real power output to provide the additional reactive power,
and will be compensated as per the bid price. When falls in
region-III (ref. Section III), we desegregate in two compo-
nents, and . denotes how much it provides within the
reactive limits, and shows how much it provides above its
reactive limits (by reducing real output).
The solution yields a positive and fairly high societal
advantage for ISO. As expected, the system bears a higher
transmission loss from this reactive power procurement plan
since this plan is financially safe for the ISO.

C. Uncertainty in Reactive Demand and Bid Price: Monte


Carlo Simulation
The solution obtained in Section V-B assumes a particular
load condition and a given set of reactive bid prices. Understand-
ably, the solution obtained is a biased solution depending on the
nature of input information.
Monte Carlo simulation is used to model the uncertainty
associated with the demand and bid prices. If the distribution
form of uncertain parameters is known, the expected behavior
Lagrange multipliers are zero if lies between the range of of the system can be studied by averaging the outcomes of
and . Therefore, the reactive power support plan different simulation cases. Among the advantages of Monte
which evolves in Table I adheres to the field/armature heating Carlo simulation is its conceptual simplicity i.e., each simula-
limits. tion exercise (or sampling) can be viewed as a possible state of
The ISO achieves a minimum transmission loss with the system operation.
above reactive power procurement plan. However, if the The reactive demand and bid prices have been assigned a
associated bid price of respective reactive power support is range of variation, a normal distribution for the former and an
accounted for, we see that the ISO ends up with a very high and uniform distribution for the later. Simulations are carried out
negative societal advantage value from the above plan. This is over the range of uncertainties and the expected outcome is eval-
not desirable from the ISO’s viewpoint in deregulated markets. uated by averaging over the entire simulation samples.
BHATTACHARYA AND ZHONG: REACTIVE POWER AS AN ANCILLARY SERVICE 299

TABLE III TABLE IV


OPTIMAL SOLUTION WITH UNCERTAINTY IN REACTIVE DEMAND OPTIMAL SOLUTION WITH UNCERTAINTY IN BID PRICE

Fig. 5. Expected reactive power on bus 4072 with uncertain bid prices.
Fig. 4. Expected reactive power on bus 4072 with uncertain reactive demand.

1) Uncertainty in Reactive Power Demand, : A normal reactive demand uncertainty. The large sample size with Monte
distribution is considered for simulating the reactive demand Carlo simulations smoothens the otherwise biased single input
uncertainty. Bid prices are held at their nominal values during and introduces a fairness in the solution.
this case. The optimal solution is obtained for each Monte
Carlo simulation sample using the two-step approach discussed VI. CONCLUSION
in Section IV and shown in Sections V-A and V-B. Procurement of various ancillary services is a complex issue
The expected reactive power procurement plan is given in for the independent system operator in deregulated electricity
Table III while Fig. 4 shows the solution convergence to the markets. Among various factors that need to be considered, are
expected value with increasing sample size of Monte Carlo the benefit to the system from a particular service-in terms of
simulation. The reactive power procurement at bus “4072” system security, economics and reliability, and the cost of the
converges to 0.49 p.u.MVAr in a Monte Carlo simulation with service in terms of payments to be made to the service providers.
200 samples. In this paper we discuss the procurement of reactive power sup-
The expectations in Table III are somewhat different from port. The benefit from reactive support at a bus is determined
the single simulation solution shown in Table II. The expected using the dual of the reactive power constraints. It is seen that
system loss is less and the expected societal advantage is more the ISO tends to procure reactive power support from those
than the single simulation case. This indicates that the single providers, which provide the best societal advantage, i.e., have
simulation case was a typically high reactive demand case sim- high marginal benefit from the service with price bids within
ulated. Over a range of reactive demand, the solution converges acceptable ranges. Understandably, as the bid prices reduce, the
around the expectation values, shown in Table III. reactive power selection plan changes. Similarly, the marginal
2) Uncertainty in Bid Price Parameters, and : The benefit function also has a role in deciding the reactive power
uncertainty in and is assumed to be uniformly distributed procurement plan.
over a range. The expected optimal solution is given in Table IV
and Fig. 5 shows the solution convergence to the expected REFERENCES
value with increasing sample size of Monte Carlo simulation.
[1] The National Grid Company, plc., “NGC Reactive Market Report,”,
Reactive power procurement at bus “4072” converges to Nov. 1999.
0.29 p.u.MVAr with a sample size of 400. [2] S. Ahmed and G. Strbac, “A method for simulation and analysis of re-
The expectations in Table IV are somewhat different from the active power market,” in Proceedings of Power Industry Computer Ap-
plications Conference 1999, 1999, pp. 337–341.
single sample solution of Table II. However, the solution is quite [3] New York Independent System Operator, NYISO Ancillary Services
close to the Monte Carlo simulation solution in Table III with Manual, 1999.
300 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO. 2, MAY 2001

[4] National Electricity Market Management Company (Australia), “Na- Kankar Bhattacharya received the Ph.D.degree from I.I.T. New Delhi in 1993.
tional electricity market ancillary services,”, Nov. 1999. During 1993–1998, he was in the faculty of IGIDR, Bombay. Since 1998, he is
[5] A. E. Fitzgerald, C. Kingsley, and S. D. Umans, Electric Machinery, with Chalmers University of Technology, Sweden. His interests are in power
Fifth ed: McGraw-Hill Book Company, 1992. system dynamics, economic operations and deregulation issues.
[6] J. Zhong and K. Bhattacharya, “Optimum Var support procurement for
maintenance of contracted transactions,” Proc. Intl. Conf. on Electric
Utility Deregulation, Restructuring and Power Technologies, 2000.
[7] K. Walve, “Nordic 32A—A Cigré test system for simulation of transient Jin Zhong received the B.Sc. degree (Eng) from Tsinghua University, China in
stability and long term dynamics,” Svenska Kraftnat, Sweden, 1993. 1995 and the M.Sc. degree (Eng) from Electric Power Research Institute, China
[8] GAMS Release 2.50, “A user’s guide,” GAMS Development Corpora- in 1998, where she continued as a Researcher till 1999. Currently, she is a Ph.D.
tion, 1999. student in Chalmers University of Technology.

Вам также может понравиться