Delegation of Power
‘L’ stands for Lakh
Director GGM GM Incharge
Operation *
Approving authority of
proposal and for inviting
Tender
Full Power Up to Rs. Up to Rs. 20L Up to Rs. 5L
Open Tender With concurrence of Finance
100L
Full Power Full Power Full Power Up to Rs. 1L With concurrence of Finance
Short Tender
Up to Rs. 50L Up to Rs. 10L Up to Rs. 1L With concurrence of Finance
Limited Tender Up to Rs.
100L
Up to Rs. 5L Up to Rs. 1L
Single Tender Up to Rs. 20L With recorded justification &
concurrence of Finance
Tender acceptance /
approval authority
Up to Rs. Up to Rs. 80L Up to Rs. 10L
Open tender (excluding
300L
single offer)
Up to Rs. 5L Up to Rs. 3L Up to Rs. 1L
Short tender (excluding
single offer)
Up to Rs. 50L Up to Rs. 20L Up to Rs. 3L
Limited Tender (excluding
single offer)
Up to Rs. 10L Up to Rs. 3L
Single Tender & single offer
against Open / Short / LTE
Director GGM GM Incharge
Operation *
Approval for Extension
Full Power Full Power Full Power
Time extension or Vetting by Finance required for
amendment of terms & change in commercial terms &
condition without any direct condition.
financial impact
upto 40% of upto 30% of upto 20% of
Quantity increase resulting Original contract not on STE or
original original original
enhancement in value other than L1 basis. To be
contract or contract or contract or
exercised with concurrence of
Rs.10 Lakh Rs.5 Lakh Rs.1 Lakh
Finance.
which ever which ever which ever
less. less. less.
Up to 10% of Up to 7% of Up to 5% of
Approval for extra work To be exercised with
Original Original Original
concurrence of Finance.
Contract value Contract value Contract
or Rs. 2 Lakh or Rs. 1 Lakh value or Rs.
whichever is whichever is 50,000
less. less. whichever is
less.
* Operation / Production incharge in case of Operation; Depending on area of application it may be interpreted as
Incharge Marketing, Incharge Project Division, Chief of Township etc.
Annex – 1
Delegation of Power
The following matters will need Board’s approval as per the prevailing office
orders / arrangements:
Performance of Contractor