Академический Документы
Профессиональный Документы
Культура Документы
0-7803-8237-4/04/$17.00020041EEE
529
2004 EEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
a Y connection with their middle point not grounded voltages on the busbar side of the capacitor switch and
(Refer to Fig.2). The capacitor banks can be connected or VcR, Vcy, and VcB are the capacitor side voltages. (Refer
removed from the busbar by the closing and opening of a to Fig. 2) Theoretically, for this case, the inrush current
capacitor switch. For the simulation, the capacitor bank would be small because there is no rapid voltage
labeled C2 in Fig. 1 is already connected (SW2 closed) to fluctuation generated between the terminals of the
the busbar. The capacitor switch SWI is then closed to capacitors.
connect the capacitor bank C l to the busbar. If the time when the voltage difference on each phase
F=50Hz becomes zero is considered based on the phase voltage
Y Y then the timing is as follows[3]:
I Main bansfarmer 1 Main transformer 2
The 1st phase closing: 0 degrees electric phase angle
Sub tranrfamcr The 2nd phase closing: 30 degrees electric phase angle
The 3rd phase closina: 120 deerees electric phase angle
Fig. 3 shows the busbar side phase voltages VR, VU, VB,
and time of closing of the capacitor switch. Since the
capacitor side voltage of R phase is the first OV if the first
phase closing is determined to be R phase, it is clear that
the time which VR=O is the time when the voltage
difference across contacts becomes zero. Then this time
is defined as the 0 electric phase angle.
Pole R Pole B Pole Y
Closed Closed Closed
c1 I- CZ
I
-
3811 FlPhase
Fig. 1. Simulation model o f a MV pawer distribution system
To busbar
R Y B T i m (ms)
Fig. 3. Closing timing an synchronous controlled switching
530
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
b k V
20 -L "
- m
(c)
B2
0
-20
:-
t , 1 20 30 40 50
20
%me (ms)
40 sa
Time (ms)
Fig. 4. Simulation rcsult of the case that 3 poles of CB closcd
simultaneously (conventional CB) Fig. 6 . Simulation result of the case that Closing timing has Im delay
(synchronous contmlled CB)
I
53 1
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRF'TZOM) April 2004 Hong Kong
CPU.Ce"ValPmCBIIing unn
AID : Analag/Digilal convener
110 : lnp"VO"1p"I Interface
Fig. 7. Consrmction of synchronous controller
The voltage zero is forecasted by the CPU as Fig. 9. Zcra point detcminatian alganthm for synchronouscontrol
mentioned above, however it is not appropriate at the
sampled time because the circuit breaker has a closing
time delay - there is some time required between receiving IV. SYNCHRONOUSLY CONTROLLED SWITCHING
the closing signal and the time the breaker' s contacts are EXPERIMENT USING A VACUUM CIRCUIT
completely closed. Therefore it is necessaly to include BREAKER WITH ELECTROMAGNETIC OPERATION
this breaker closing time (delay) when calculating the MECHANISM
voltage zero point as shown in Fig. 8. The CPU The synchronous controlled switching experiment of a
determines the zero on the forecasted voltage waveform circuit breaker, with individual closing, was performed
and sends the closing signal to the breaker when it using a controller with the algorithm described in the
receives an external closing command. previous section. A commonly available digital signal
Tamel lor CB Closing Completion (Voltage Zero polnI1 processor (DSP) with a I50MHz operation clock was
used as the CPU of the synchronous controller
implementing the algorithm. The frequency of the
voltage sampling was 8 ldiz and the quantization bit of
the AD converter was 12 bits. The AD converter had a
conversion delay time of 2.125 msec, which was also
included in the determination of the forecasted voltage
waveform.
A vacuum circuit breaker with electromagnetic
operation mechanism manufactured by Mitsubishi Electric
Corporation was used. This breaker was found to be the
most suitable for the required application as the breaker
Voltage Zero Point on Estimated'Waveform has sufficiently low mechanical error margins. It is
=Signal Dispatch Tiining
Fig. 8. Voltage zero point estimation considered that gas circuit breakers' (GCBs) opening and
closing time error margins are high because GCBs contain
Fig.9 shows the algorithm for zero point determination. many mechanical parts that drive heavy structures
First, the voltage is sampled and saved in the memory. (namely the puffer) to compress and inhale the insulating
Next, the amplitude A, phase cp and DC shift B are gas during opening and closing. As vacuum circuit
calculated from the maximum and minimum times and breakers (VCBs) do not have to drive heavy structures as
values obtained from data of the previous cycle sampled. they utilize light contacts in vacuum, a more stable and
If the frequency f is fixed at 50Hz, the voltage can be steady operation is guaranteed.
forecasted as V=Asin(Zaff+cp) +B at the closing time T. Fig. 10 shows the construction of the circuit breaker
A closing signal is sent to the breaker if this voltage V with electromagnetic operation mechanism used in the
becomes V=O if an extemal closing command has been experiment. It is a direct driven type (without the link
issued. If no external closing signal has been received, the mechanism between the contact and actuator) and is
controller retums to the beginning of the voltage sampling driven by the electromagnetic force of the coil. Without
and continuously loops. This algorithm allows the closing the requirement of linkages of the mechanism required by
signal to be sent so that the breaker contacts are closed conventional spring operated VCBs, the electromagnetic
precisely at the instant V=O. mechanism does not have the error in operation time
Since the algorithm used is simplified, the accuracy may associated with the linkages. Additionally, the number of
be improved by using a more advanced processing parts required for the electromagnetic operation
technique that includes the complex and higher harmonic mechanism is much less than spring operating
wave elements from the voltage waveform. However, the mechanisms, the probability of failures is greatly reduced
532
2004 IEEE InternationalConference on Electric Utility Deregulation, Restmcturing and Power Technologies (DRF'T2004) April 2004 Hong Kong
and changes to the operating characteristics due to ageing synchronously controlled switching was a success. The
.;2bTF7-q
are very small throughout its service life. For the reasons coil current and the travel curve kept on changing after
mentioned above the mechanical error margin of vacuum the contact was closed due to contact suring compression.
circuit breakers with electromagnetic mechanisms is Voltage waveform applied : ~
.+F-,,
Ch.>"l: .~ ~
eommandewhh ; I :
............. . . . : . . / j ~
oirning
command .*>CCh , . .
.
;..........~....I.
,
.? p
.
. . ... . .
. . ; \
.; .I ',
. . .. ..
Tam1 curve
I"",
. . .. ., . ... .
>*?m,S
%war
I
Closing command Closing time 26.Zms
("mYaJ *W"Cnmg)
533
2004 IEEE Intemational Conference o n Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 H o n g K o n g
I B.S.,
1970
’ and
’
ahd Ph.D. degrees in electrical
engineering from Kyoto University, in 1968,
1990. ~ ~ S D C E ~ ~ Y C I Y .
534