Академический Документы
Профессиональный Документы
Культура Документы
Abstract: A rule-based expert system with a coloured Petri net (CPN) algorithm is developed for
load balancing of distribution systems. CPN models of the distribution components such as four-
way line switches are proposed to derive the proper switching operations. In this way, the loads on
transformers and feeders will become more balanced. Heuristic rules based on the standard load
transfer operation procedures of the Taipower distribution system are included in the best first
search of the CPN to obtain the desired switching operations for load balancing. For the overload
contingency during the summer peak season, load shedding is also considered in the CPN models
to provide service to as many key customers and loads as possible. The priority indices of each
feeder and service zone are determined in advance according to the key customers within the service
territory. A Taipower distribution system with 68 feeders is selected for computer simulation to
demonstrate the effectiveness of the proposed methodology. It is found that load balancing of the
distribution system can be obtained very efficiently and the risk of overloads can be reduced by
applying the proposed CPN model to determine the optimal switchmg operation.
pad-mounted
transformer
pad-mounted
to serve the load r
x1
mold joinf
4
N.
under 31A
customew 4 -
3149A
SGi"
318
noninterruptible load transfer, the DS has to be enabled substation
after the PS to maintain the open loop Configuration of the
distribution systems.
To comply with the distribution system's operating
regulations during switching, the following rules are
exploited in the PS process:
Rule I: Select the relief feeder for load transfer. For the
transformers and feeders under study, find the one with the
largest value of LBIx or LBIh in ( I ) and (2). Load transfer
of the most heavily loaded transformer or feeder is given the
highest priority.
Rule 2 If the element with the largest load unbalance index
is a transformer T, without overloading, select the feeder5
-~.. with the smallest LBI. among the feeders supplied by
sectionalising switch
transformer Ti and designate this feeder as the relief feeder 0 :normally open
for load transfer. On the other hand. if the main lour-way tie switch
transformer is overloaded, then select the feeder with
the largest LBIh as the relief feeder for load transfer. Fig. 3 Circulation cuirenr in rhe rmin loop when open fir swirch i.9
closed
Rule 3: If the element with the largest load unbalance index
is a fceder .h, or the feeder supplied by an unbalanced
loading transformer as in rule 2 , it is designated as the relief open tie switch in Fig. 3, the circulation current can be
feeder for the load transfer. Select the burden feeder for estimated as [9]
load transfer by checking all feeders connected to the relicf
feeder with an open tie switch. The candidate feeder with
the smallest value of LBIh is selected as the burden feeder.
2. The system voltage drop after a switching operation has where Vmw,h>Vww,, is the new node voltages of the burden
-i -j
to be less than 10%.
feeder i and the relief feeder;: V,,,, Vou,r are the original
3. To avoid circulation current after closing the open tie node voltages of the burden feeder i and the relief feeder;:
switching for noninterruptible load transfer: first, the phase -i -j
sequences must be the same; secondly, the difference in I,,,b, I , , : , are the new current flows of service section of
terminal voltage magnitudes and phase angles between both -i -j
sides of the open tie switch must be less than 10% and lo", the burden feeder i and the relief feeder j: I &,,, I is the
respectively. When the loop is constructed by closing the origmal current flows of service section of the burden feeder
ICE Prui:-Gener. T w m n Dirtrih.. Vol. 150. A b 3, Moy ZH13 319
- Tablel: Colour settings of distribution system compo
i and the relief feeder j , 4 Y is the change of the node
-- ne&
voltages due to the switching operation: 4 I : I , is the
current transfer from the relief feederj to the burden feeder Components Colours
Ai -j
i; and Z , , Z , are the line section impedances of the burden Circuit breaker close open lock
feeder i and the relief feeder j , respectively. Switch close open lock
Transformer E DE 0
4 CPN model for switching operation Branch zone s1 52 0
Service zone s1 s2
In this paper, the high-level CPN model is used to
determine the switching to achieve the load balancing of Load s1 s2
the distribution feeders and main transformers. The CPN E energized, DE de-energized. 0 overload
model used in [lo] has been applied in this paper. For the S1 power supplied from source 1
CPN model, the place (PL) nodes represent conditions and S2 power supplied from source 2
transition (TR) nodes represent switching events for the
state transitions in the distribution system configuration.
The CPN inference is performed by the tokens and colours
passing from the system’s initial state to find the solution
state. The TR node is enabled when at least one of the PL
nodes receives a token and satisfies the StdtUS for each
transition mode. The TR node is activated if the guard
function of the enabled TR node is evaluated to be true for
taking action. The tokens are then passed from their entry
places to their outgoing places. In the CPN inference
mechanism, many tokens and colours may exist and several
TR nodes may be activated simultaneously. Therefore,
these tokens and colours can be processed efficiently with
the parallel-like inference mechanism. Fig. 4 Proposed CPN model
4.1 The CPN Petri net model Mode 1 has been selected as an example to illustrate the
The colour settings of the distribution system components processing of colours and tokens in Fig. 4 and Table 2. To
for load balancing are defined in Table 1. BeCduSe the close the tie switch in Fig. 4, the TR node TI has to be
power demands of the branch zone, service zone and load enabled by three pre-action colour settings: first, the power
can be transferred from the burden feeder to the relief feeder of zone 1 is supplied from source 1 and receives a token (i.e.
by a switching operation, two kinds of colour settings (SI the colour setting of PI is Sl(T)); secondly, the power of
and S2) are defined for each branch zone, service zone and zone 2 is supplied from source 2 (i.e. the colour setting of P2
load, respectively. The proposed CPN model of the is S2); finally, SWI is an open tie switch and receives a
distribution system components is illustrated in Fig. 4. token (i.e. the colour setting of P3 is O(T)). The TR node is
There are three PL nodes (PI_P2 and P3) and one TR node activated if the PS processing of the heuristic rules described
VI). The PL nodes represent the colour settings (status) of in Section 3 is evaluated to be true. The colour settings are
the components of the distribution system. The TR node is then transferred to update the postaction colour settings for
the operation rule for the status transfer of PI-P3. The three PL nodes and the tokens are then transferred to the
inference mechanism of the CPN model for the transition PL node P2 which could enable other TR nodes.
node and place nodes is illustrated in Table 2. The inference
of mode I is to close an open tie switch to form the closed
loop configuration of the distribution system on a 4.2 CPN inference model of four-way line
temporary basis. The inference o f mode 2 is applied for switches
all line switches between the original open tie switch and Fig. 5 shows a four-way line switch used in the underground
the normally closed switch to be opened. Mode 3 is the distribution systems. The open/closed status of two main
inference to open a normally closed switch to restore the switches (SWI and SW2) is retrieved by the SCADA system
open loop configuration of the system. and the topology process is executed to determine the
Table 2 Inference of the transition node and place nodes for load transfer
load1 load2
Fig. 8 Partial one-line diagrum ofrlre s)'stem and lhe 18 switch-pairs to be operuled
2000 -HH1 -GS3 --GVl +HJl --HJ3 2000 -HH1 - - G S 3 -GVl -HJ1 -~HJ3
1400
4I
1200
1000
2 800
600
400 400
200 200
0 0
1 3 5 7 9 11 13 15 17 19 21 23 1 3 5 7 9 11 13 15 17 19 21 23
lime. h lime, h
Fig. 9 Daily loadprufles of H H l and supporliny transfirmers Fig. 10 Lvudprofles ufer sivifching operatioris and loud slieiliny
10 sulae ouerlood contingency
6 Conclusions 7 References
A rule-based expert system and the associated CPN I WU. J.S., LIU. C.C., LIOU, K.L., and CHU, R.F.: 'A petri
inference model are proposed to solve the load balancing net alganthm for scheduling of generic restoration BC~IOIIB'. IEEE
Tmnr Power S)>sl.,1997. 12, (1). pp. by-75
and overload problems of a distribution system. The rules 2 wu. J.s.: 'A peti.net algorithm for multiple contingencies of
for load transfer in Taipower have been included in the distnbution system operation', IEEE Trum Power Sysl.. IWX, 13,
(3), pp. l l M l 1 7 1
CPN model and the inference mechanism SO that the 3 YANG. C.L.. and YOKOYAMA, A.: 'Fault section estimation of
switching plan derived can comply with the operational power system using colour time pet" nets'. Procadings of 4th
regulations. With the integration of these operational rules Symposium on Expert system application to power systems,
Melbourne. Australia, Jan. 1993, pp. 321-326
and the parallel-like inference capability, the switchng plan 4 TO~~SOV,,-, K.: . ~ ~ rule~based
~ ~ proceedings
lsystms,. ~ ~ i lSt~
of ~
for load balancing of the main transformers and feeders of Symposium on Expert system application to power systems, Stock-
the distribution systems is solved effectively. halm, Sweden, Aug. 1988, pp. 2.1-2.3
5 JENKINS, L., and KHINCHA, H.P.: 'Deterministic and stochastic
To demonstrate the effectiveness of the proposed lxtri net models of Drotection schemes'. IEEE Trols, Pmwr Delia..
methodology, a practical Taipower distribution system i B 2 . 7, (I),pp. 84-40
6 WANC. F., and TANG, J.: 'Modeling of a transmission line
consisting of 68 feeders was selected for computer protation relaying scheme using petri nets'. IEEE Tram Power
simulation. The CPN model of the distribution system Dcliu. 1997. 12, (3), pp. 1052-1063
was created and the inference mechanism was then applied 7 CHEN, C.S., KANG, M.S., HWANG, J.C.. and HUANG, C.W.:
'Temperature effcct to distnbution system load profiles and fmler
to find the optimal switching to enhance system efficiency IOEVI'
, 1EEFTron.r
~
Pmurr
~.... .Siirl .7...0, 1 16
.-, 14)
,.,, nn
rr. 4 t h 9,-.
..- 71
with the change of season. Fir the overload contingency of 8 CHEN. C.S., LIN, C.H., and TSAI, H.Y.: 'A rule-based expert
system with coloured petri net models for distribution system service -
the distribution systems. the problem can also be solved by restoration', IEEE Trunr Power S y x . 2002. 17. (4), pp. 1073-1080
load transfer among the main transformers and distribution 9 NARA. K.. SATOH. T.. AOKI, K., and KITACAWA, M.: 'A first
feeders with the proposed CPN model. For the case study, expansion planning algoithm for large a l e distribution systems'.
Prennted at the 8th CEPSI, Singpore, Nov. 1990
when sufficient capacity reserve " I o t be provided by the 10 JENSEN, K.: 'coloured pCtnnetS - basic concepts, methods
supporting main transformer/feeders, load shedding is then and practice use', (Spinger-Vcrlag. &din, Germany. 1992). Vol. 1