Академический Документы
Профессиональный Документы
Культура Документы
Introduction
Currently, untreated sewage regularly overflows into the River Thames from Londons Victorian sewerage system via combined sewer overflows (CSOs). The proposed Thames Tunnel would intercept these overflows through the use of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. The sewage flow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reduction in untreated sewage entering the River Thames would bring long-term benefits for the environment and users of the River Thames. In order to deliver the project we need a number of sites along the route and this document identifies our current preferred site at Albert Embankment Foreshore.
Key facts
Local authority: CSO names: CSO spill volume in an average year: Site type: Duration of main construction works: Lambeth Clapham Storm Relief and Brixton Storm Relief 280,000m (equivalent to approximately 112 Olympic swimming pools) CSO site Approximately three and a half years.
Thames Tunnel
1
Introduction
CITY OF WESTMINSTER
Tintagel House Camelford House Brixton Storm Relief CSO Lacks Dock
Albert Embankme n
an i ll b M
Grosv eno r Ro ad
Vauxhall Bridge
MI6/SIS
Spring Gardens
WANDSWORTH
Figure 1A: Albert Embankment Foreshore location plan
Vauxhall Station
Related documents:
Q&A
Construction
Section 2: Construction
Construction activities
Construction activities are required to intercept the CSOs. We would construct interception chambers to intercept the CSOs. Connection culverts would link the interception chambers to a drop shaft (approximately 47m deep), through which flows would pass down to a short connection tunnel. This would then join to the main tunnel. Figure 2A illustrates the below ground infrastructure proposed. As the construction works would take place within the foreshore of the River Thames, permanent structures extending into the foreshore are required. These activities would take place within the area indicated by the red line in Figure 1A, in five main phases, lasting approximately three and a half years in total. The main construction activities associated with these phases are set out in Table 2.1.
Connection culvert
Construction
Interception chambers
Valve chamber
Drop shaft
Main tunnel
Site setup
Figure reference
Typical working hours Utilities connected Site cleared
Varies
Figure 2C
Standard
Temporary works in the River Thames constructed Site facilities and access set up Drop shaft excavated and built Tunnel boring machine delivered to site and assembled Short connection tunnel excavated and built Above and below ground structures constructed Mechanical and electrical equipment installed Temporary works in the River Thames removed Site restored and landscaped Temporary site facilities removed
Our typical working hours are expected to be: Standard: 8am-6pm weekdays, 8am-1pm Saturday* Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays Continuous: 24 hours a day, seven days a week** Varies: Working hours for advanced works will depend on the nature of the works and will be agreed with the local authority
* Standard working hours would also include, subject to agreement with the local authority: a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site. equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday. ** The main activities taking place 24 hours a day are below ground or within an enclosure.
Construction
Phase 3 Tunnelling
Figure 2D
Continuous
Related documents: Build Managing construction
Figure 2B: Construction timeline showing approximate duration of works in phases (P)
Advance works
Construction
Maximum extent of construction site for phase 1 Site hoarding Cofferdam Barges Local authority boundary Site support/welfare Thames Path diversion Internal site road Jack up barge servicing piling operations Site access Existing Thames Path Thames Path diversion
CITY OF WESTMINSTER
Va u
xh
all
Br
idg
LAMBETH N
Figure 2C: Illustrative phase 1 construction plan
Maximum extent of construction site for phases 2 and 3 Site hoarding Cofferdam Local authority boundary Crane Drop shaft Site support/welfare Excavated material storage and processing Maintenance workshop and storage Construction support
CITY OF WESTMINSTER
Va u
xh
all
Br
idg
Crane
LAMBETH
10
Construction
Maximum extent of construction site for phase 4 Site hoarding Cofferdam Local authority boundary
Site support/welfare Excavated material storage and processing Maintenance workshop and storage
CITY OF WESTMINSTER
Va u
xh
all
Br
idg
Crane
LAMBETH
11
When
Type of works
Installation of equipment to monitor environmental matters such as noise, vibration and dust. Protection works to third party structures (such as buildings, bridges and tunnels). Temporary connection to utilities (such as water, sewer, phone and electricity supply). Dredging. Protection of the river bed.
What we would do
The locations of monitoring equipment would be agreed with the local authority and relevant landowners. We would undertake studies to identify any effects our construction work may have on third party structures. The studies may recommend particular construction methods or, in very limited instances, protection works. We expect to connect to utilities in Albert Embankment (A3036). There is a possibility that as the detailed design is developed we may need to undertake dredging to allow barges to get to and from our site. We may need to carry out works to strengthen the river bed to avoid scour. Due to particular requirements at this site, an off-site vehicle marshalling facility would be used to regulate construction vehicles entering the site. We anticipate that this holding area would be within a 10-15 minute drive from the site. We expect to connect to utilities in Albert Embankment (A3036).
Permanent connection to utilities (such as water, phone and power supply) for the operational tunnel.
12
Construction
Phase 3 Tunnelling
29 lorries 7 barges
4 lorries none
Table 2.3: Average daily lorry and barge visits during the peak months
13
CITY OF WESTMINSTER
Albert Embankment
LAMBETH
WANDSWORTH
Figure 2F: Proposed access route to the site from the nearest major road
Albert Embankment
N Draft limit of land to be acquired or used Internal site road Site access Local authority boundary Transport for London (TfL) road network 14
Construction
15
Our response
As part of the Environmental Impact Assessment, we would undertake a preliminary site-based archaeological assessment, which would enable a more targeted and precise strategy to address potential effects to be developed for the site post-consent and in advance of construction. Further work, which is likely to comprise archaeological excavation and recording, would be carried out in accordance with a scope of works (Written Scheme of Investigation), which would be agreed with English Heritage, London Borough of Lambeth and other key stakeholders prior to the commencement of construction. We would manage our works in order to maintain safe access for London Duck Tours during construction. This includes construction of a separate access road to our site and management of the shared access onto Albert Embankment (A3036) through the traffic management plan. We have undertaken modelling to test the effect that the structure has on the flow of the river. The modelling has shown the proposed structure to be satisfactory and the Port of London Authority and other key stakeholders are satisfied the permanent works have a minimum effect on river navigation. A full navigational risk assessment will be undertaken for the temporary and permanent works. The Thames Path would be temporarily diverted via a safe alternative route to the east of the construction site, along Albert Embankment (A3036). Since phase one consultation, we have relocated the construction site access via Lacks Dock to reduce effects on the nearest residential properties. The contractor would be required to implement noise and vibration control measures at the worksite, which will be set out in the CoCP. Continuous tunnelling would only be undertaken for a short period of time to construct a connection tunnel from the drop shaft to the main tunnel.
Possible effect of foreshore construction activities on river navigation and river users, including London Duck Tours who operate from Lacks Dock.
Preliminary findings indicate that while there is the potential for dust nuisance effects, Possible effects on local air there are unlikely to be any significant local air quality effects at any of the sites. The quality and dust nuisance contractor would put in place air and dust control measures at the worksite, which will be in neighbouring areas. set out in the CoCP.
16
Construction
Issue
Our response
Since phase one consultation, we have reduced the extent of temporary works in the foreshore of the River Thames by relocating the construction site access via Lacks Dock. Possible effects on Ecological surveys of the River Thames and foreshore are being undertaken to identify foreshore habitat and river possible effects arising from construction activities. The contractor would put in place wildlife. various control measures at the worksite to minimise these effects as far as possible. These will be set out in the CoCP. Possible effects of construction activities on adjacent structures, which may cause settlement. Possible effects on river and tidal flow, causing erosion. We will undertake a detailed assessment of potential ground movement caused by our construction works and ensure that there is no damage to any structures located close to our works. We will undertake detailed river scour assessments once river bed samples have been taken. The foreshore and river structures would be monitored before construction starts and throughout the construction period.
17
Design
Since phase one consultation we have progressed the design for the permanent use and appearance of the structures at Albert Embankment Foreshore. The design of the permanent proposals follows our scheme-wide principles and takes into account comments made and ongoing engagement with the London Borough of Lambeth and other technical consultees.
18
Future use
Issue
Effects on river navigation and hydraulics.
Our response
Preliminary modelling has indicated that the proposed design is acceptable in terms of flow and scour of the river. A more detailed investigation is underway. The proposals have been discussed with the Port of London Authority and other key stakeholders to develop a layout that has a minimal effect on river navigation. Since phase one consultation, the drop shaft has increased in diameter as a result of detailed modelling. Our proposals for the permanent layout and design of the site have however sought to reduce the extent of the permanent works within the foreshore of the River Thames to minimise effects on water ecology as far as possible. Ecological surveys of the River Thames and foreshore are being undertaken to identify possible effects, and design measures would be incorporated where required. Construction of the tunnel would deliver river-wide improvements to local water quality, which would result in positive effects on river ecology, including habitat improvements and reduced fish kills. We have taken a contemporary approach to the design of the proposed structure adjacent to Vauxhall Bridge. We consider this design takes its reference from the monumental architecture of the MI6/SIS building (circular turrets and clean detailing) and would not detract from the setting of the Grade II* listed Vauxhall Bridge. The design of the above ground structure has sought to reduce the bulk of the permanent extension to the embankment and to minimise the potential effects on views of Vauxhall Bridge. The Thames Path would be restored after our works are complete and would be enhanced with a new landscaped public area where people can enjoy the views along the River Thames. The ventilation columns, in common with the scheme-wide ventilation strategy, are thinner and shorter than proposed at phase one consultation. We require two operational electrical and control kiosks at ground level and these would be designed to be unobtrusive with one located beneath Vauxhall Bridge and the other on the back edge of the proposed new public area in front of Camelford House. Future use
Effect on the setting of the Grade II* listed Vauxhall Bridge, and historic views along the River Thames.
Table 3.1: Site specific issues that have influenced our permanent design
19
Figure 3A: Photo of the site before the works (north of Vauxhall Bridge)
20
Future use
Figure 3B: Artists impression of the site after the works are completed (north of Vauxhall Bridge)
21
Figure 3C: Photo of the site before the works (south of Vauxhall Bridge)
22
Future use
Figure 3D: Artists impression of the site after the works are completed (south of Vauxhall Bridge)
23
Figure 3E: Aerial view of the completed works (north of Vauxhall Bridge)
24
Future use
Figure 3F: Aerial view of the completed works (south of Vauxhall Bridge)
25
Timber seating Ventilation columns Electrical and control kiosk Vauxhall Bridge deck omitted for clarity
Electrical and control kiosk beneath Vauxhall Bridge Floodable terraces over Clapham Storm Relief CSO connection pipe
Alb
ert
Em
Ventilation columns
ban
km e
nt
N Foreshore interception structure for Clapham Storm Relief CSO Maintenance vehicle access via existing Lacks Dock accessway
Figure 3G: Layout of the site once construction works are complete
26
Future use
Issue
Possible odour effects during the operation of the tunnel.
Our response
Odour effects at this site are expected to be negligible because we have developed an Air management plan to minimise possible odour and air quality effects arising from the operation of the tunnel. The technology we are proposing to use at this site includes the use of passive below ground carbon filters that will remove possible odour before air leaves the ventilation equipment Permanent access would be required for maintenance and servicing purposes to the shaft and ventilation equipment. Any planned maintenance visits would be undertaken during normal working hours and all visits managed to avoid disruption to local residents, businesses and users of affected public areas as far as possible.
27
Further information
This section sets out documents which may be of particular interest. Further information on our proposals can be found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre on 0800 0721 086).
Q&A
Consultation
Design
Environment
Managing construction
Odour
Sets out our Air management plan and how it will work.
Options
28
Sets out the preferred route of the main tunnel and the reasons for our preference.
Sets out the process we followed to find and select our preferred sites. Contains information on the different transport options we have considered for delivering and removing materials from our sites.
Transport
29
Further information
Technical reports
Theme Phase one consultation Icon Title Report on phase one consultation: summary report Details Provides a summary of the comments made at phase one consultation and our responses.
SUMMARY
Code of construction practice Part A: Sets out control measures to be adopted during the project General requirements construction period. (CoCP) Air management plan Outlines the methods which we will use to manage odour from the main tunnel at all our preferred sites. Contains initial assessments on the environmental effects of the Thames Tunnel project based on information collected to date. Please refer to volume 19 of the non-technical summary and volume 19 of the PEIR for more information on this site. Provides a general overview of how the scheme design at each site has evolved to date. Please refer to chapter 16 for more information on this site. Provides an overview of the development of the Thames Tunnel project and how each site was chosen. Please refer to Appendix N for more information on this site.
30
Site glossary
Term
Carbon filters Cofferdam Combined sewer Combined sewer overflow (CSO) Connection tunnel Conservation area Draft limit of land to be acquired or used Drop shaft Foreshore Interception chamber Main tunnel Operational phase Scour Thames Tunnel project Transport for London Road Network (TLRN) Tunnel boring machine (TBM)
Definition
Filters that remove odours before the air is released from the tunnel. A wall that is constructed within the river around the outside of the working area and then pumped dry. The inside of the cofferdam can then be filled to create a safe working area. A single sewer system that takes both rainwater and domestic and industrial wastewater. A structure, or series of structures, that allows sewers to overflow into the river when they are full as a result of increased rainfall. Without the overflows, the sewers would back up and cause flooding in streets or houses. A tunnel connecting a drop shaft to the main tunnel. An area designated by the local authority or English Heritage as having special architectural or historical interest. The extent of land that we may need to use or acquire, or over which rights may be needed to carry out works that are essential to the project. A vertical circular concrete structure, used to drop flows from the high level of the CSO to the low level of the main tunnel. It would also be used to provide access to construct the connection tunnels. Ground uncovered by the river when the tide is low. A structure, built on an existing combined sewer, which diverts stormwater overflow into the main tunnel. The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station. After the completion of the construction work, when the main tunnel is in use. Movement of the riverbed materials due to the force of the water. The Thames Tunnel project comprises a storage and transfer tunnel, from west London to Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the Thames Tideway. The network of roads managed by Transport for London. These are the major or strategic roads, which have high capacity. A machine used to excavate tunnels through a variety of conditions, with a circular cross-section.
31
For further information or to comment on our proposals see our website: www.thamestunnelconsultation.co.uk
It is very important that you understand the information we have provided. If you need further information in another language, braille, large print or audio format please contact us on 0800 0721 086.
32