Академический Документы
Профессиональный Документы
Культура Документы
Revision 2
Welcome to the second edition of the Australian Means & Methods. These Means and Methods are basically the Australian Rule book for how we build. They have been written to provide a clear and consistent guide to working on Bovis Lend Lease Projects and by following them you will comply with the Bovis Lend Lease Global Rules for building or Global Minimum Requirements (GMRs). Typically, the Means & Methods are in line with relevant Australian Standards and Codes of Practice; however there will be some instances where we have adopted a more rigid approach or rule over and above the standards. Our reasons for doing this are always with the best intentions of providing a workplace free from Incident and Injury and in many cases we have taken a stronger stance due to lessons we have learnt from our own sites, industry or peers. The Means & Methods also show examples of best practice which I would encourage you to always adopt where you can as it is only through a continual pursuit of excellence that we will move the industry and get closer to our vision of being incident and injury Free. We will review these Means & Methods regularly to ensure that they are achievable, buildable and best practice and I welcome your feedback.
Peter Marix-Evans Head of Environment, Health & Safety Bovis Lend Lease - Australia
Hierarchy of controls amended. Amended requirements on handrails for formwork (fixing, guards, engineers signoff and mechanical means of fixing). Amended requirements on exclusions zones where work is performed over head with sign in / out required. Supervision regarding screens requires a rigger to supervise. Vertical elements for formwork require design and sign off for flow rates. Jumpform requirements added. Scaffolding requirements amended (chain wire mesh, working loads, internal access). Penetration covers for vertical elements changed to reflect buildability. Requirements for chariot ladders clarified for stability. Confirmation that ladder permit is not required when using a chariot / podium type ladder. Requirements on Swinging stages. Signoff requirement on roof mesh by roofer prior to handover to other trades. Installation of roof mesh requirements. Masonry walls propping requirements and considerations. Delivery drivers site induction requirements. ATF type fencing requirements, specific sign off and erection. Overhead protection rating requirements. High viz clothing requirements made clear. Unloading / loading requirements as far as fall prevention. Requirement for non ticketed plant. Requirements for sign checks following wet weather. Handrails on equipment for maintenance. Refuelling of plant on site. Concrete Pumping considerations on site. Piling works / piling machinery consideration. Clarification regarding what a dedicated cleaning crew is. Rules regarding no smoking on site in any enclosed area and in the vicinity of amenities. Potholing / hand digging exploration requirements prior to machine excavation. Requirements for site inspections following wet weather. Physical barricade requirement changed from 1m to 1.5m to match relevant codes. Definition of 3rd party inspector clarified. Tower Cranes section added to incorporate global alert. Competency of operators and records requirements. General induction training certification requirements.
GMR 2.1 GMR 2.2 GMR 2.3 GMR 2.4 GMR 2.5 GMR 2.6
GMR 2.7
GMR 4.2
GMR6.1
This section is the BLL Global Requirement that ALL Countries must comply with.
This section shows photos of good and best practice initiatives or where noted unacceptable practice
This section is a check point summary highlighting key components of the Australian rules for this GMR
This section is the Australian rules for how to achieve the GMRs
This notes any templates or tools which will be kept on the Bluebook as a template and any additional resources or suppliers.
CONTENTS
GMR 1 Fall Prevention
GMR 1.1 The Falls Mandate GMR 1.2 Perimeter Protection GMR 1.3 Frame Erection GMR 1.4 Scaffolds, Temporary Works and Working Platforms GMR 1.5 Penetrations, Risers and Shafts GMR 1.6 Ladders GMR 1.7 General Precautions
GMR 2 Logistics
GMR 2.1 Site Access Control GMR 2.2 Fencing GMR 2.3 Public Protection GMR 2.4 Pedestrian & Vehicle Safety GMR 2.5 Operator Competence GMR 2.6 Powered Mobile Equipment GMR 2.7 Housekeeping
GMR 3 Groundworks
GMR 3.1 Pre-planning GMR 3.2 Stability GMR 3.3 Safe Works
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
Standard:
Birdcage scaffold protection used as primary fall protection placed under formwork deck
Perimeter safety screens installed to provide fall protection at the formwork deck edge. Metal fencing installed at project perimeter for public safety
Curtin wall installation scaffold tube & fitting safety rail installed as the primary fall protection. Safety harness and lanyard used as secondary protection
Page 1 of 4
Revision No 2
Page 2 of 4
2 Note a harness permit will need to be completed for all harnesses used as primary fall restraint. NOTE: It should be noted that generally through this document as a minimum metric, we use a 2m fall rule. It is not considered acceptable practice to fall any distance and all actions should be taken to ensure that no person, material or equipment can fall any distance.
1.0
Risk and Opportunity at design (ROAD) During design / bid stage, a risk and opportunity at design (ROAD) session will be carried out. This will have a dedicated section in reducing the risk of falls from height and will endeavour to design out these risks where reasonably practicable and utilising the Hierarchy of control. Novated design must still use the ROAD Process. Project Delivery Plan (PDP) A preconstruction plan (Project Delivery Plan) will be prepared which will include a dedicated section which will focus on planning how work at height activities will be carried out and which will utilise the hierarchy of
Page 3 of 4 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
2.0
Step 1 - Eliminate risky activities where ever possible, if not possible, only then Step 2 - Substitute risks by providing safer products, materials or processes Step 3 - Isolate risks by providing controls to isolate people from hazards/hazards from people Step 4 - Engineer out risks by providing mechanical, designed/engineered controls to prevent injury Step 5 - Administrate controls risks by providing procedures such as Lock Out/Tag Out or Permits Step 6 - Provide Personal Protective Equipment to reduce the likelihood and severity of injury
3.2
Related Information
Harness Permit ROAD Project Delivery Plan
Suppliers / Resources
Page 4 of 4
Revision No 2
2 Perimeter Protection (in or on structures) All open edges to structures under construction or demolition (including the construction/demolition floor) from which persons or materials can fall, must be effectively protected by screens, scaffolds. The means of protection employed must be the most robust form of protection that can be used on the structure, taking into account all relevant parameters, such as nature of construction operations, structural stability, weather conditions, etc. Screens are the preferred option and must be considered before any other option is explored. The protection provided must be of sufficient strength and height to prevent people and materials from falling or being blown off the structure. The level of protection planned for any project will be scrutinised to ensure it meets these requirements as part of the project approval process. Where any works are conducted outside of the perimeter protection which could result in the fall of materials, lanyards should be used to tie-off tools and equipment.
Standard:
Tube and mesh panels guardrail pre installed at the edge of a metal deck
Helmet secured to the safety harness by a lanyard other alternative is a helmet chin strap
Page 1 of 6
Revision No 2
Modular scaffolding installed at all floor levels to arrest the fall of persons and material
Heavy duty metal and mesh screens placed in mechanical voids NOTE: a safe methodology / handrail is required during installation of ductwork
Heavy duty metal and mesh screens inserted over a large void
Scaffold guardrails and metal mesh prior to the metal deck being lifted into position by the tower crane
Voids and gaps to be fully closed in Voids and gaps around screens to be fully closed in
Page 2 of 6
Revision No 2
Loading platforms
Engineered solutions to install faade brackets to prevent dropping material NOTE: exclusion zone or overhead protection still required below
Proprietary handrail
Harness used as secondary restraint. Height of faade panel should take into consideration falls. (ie extend 1m above floor).
Page 3 of 6
Revision No 2
Perimeter Protection
Worker on perimeter
Mesh infills on MEPS where adjacent perimeter or exclusion zone cannot be implemented (ensure wind load is checked)
Page 4 of 6
Revision No 2
Check
Page 5 of 6
Related Information
Suppliers / Resources
Workright Edge Protection Systems P/L Workrightedgeprotection@bigpoind.com Ph: +61 (0) 2 8824 7776
Page 6 of 6
Revision No 2
3 Frame Erection / Formwork Erection Metal frame structures should be erected from Mobile Elevated Work Platforms (MEWPs). Catch decks and guard rail systems shall be used to provide fall protection during metal decking operations. Hierarchy of controls must be considered at all times.
Standard:
Concrete formwork/falsework systems should be proprietary systems and be erected from safe working platforms or MEWPs below the deck level. Edge protection systems should be designed in as part of the frame erection process and should provide protection for following works, e.g. cladding.
Metal deck suspended from tower crane MEWP used to assist with installation
Small MEWPs available for tight areas NOTE: housekeeping needs attention Engineered solutions to provide adequate support to MEWPs
Page 1 of 8
Revision No 2
Page 2 of 8
Revision No 2
NOTE: Formwork erection is to be carried out in such a manner that fall risk is minimised and NEVER more than 2m. This will entail: Erection of formwork from below Catch decks Handrails
It is not acceptable to have leading edges with fall hazards and all fall hazards greater than 2m should be removed completely. Design 1.0 The BLL EH&S system aims to firstly eliminate hazards or if this is not possible minimise the risk. Therefore the first step should be to ensure the formwork design is reviewed in the Risk and Opportunity at Design for opportunities to eliminate the hazards. This could be by the use of pre-cast sections or simply adjusting deck height and design to maximise the use of a formwork system (ie Peri, Boral, table forms) The formwork systems to be adopted are to be approved by BLL Regional Operations Manager and EH&S Manager prior to any commitment being made to a formwork subcontractor and signed off at the project pre-construction as part of the Project Delivery Plan. All falsework / formwork will comply with AS3610 and be fully tested. The formwork system is to be designed by a qualified structural Engineer with 12 months experience in the design of formwork. The formwork systems will preferably be a systemised proprietary type systems. Full shop drawings will be prepared for falsework system and approved prior to any deck commencing. The drawings will clearly indicate permissible loads and loading areas (for stressing coil, bins, reo and the like). The formwork engineer shall also certify the proposed erection procedure prior to the falsework / formwork being erected. A competent qualified structural engineer will also certify falsework, formwork and backpropping as being structurally adequate, immediately (i.e. once installation is complete prior to pouring. Design should take into account live and dead loadings and safe working load (SWL) will be adequately identified where multiple systems are used. Where scaffolding systems are used as falsework (and integrated scaffolding screens) they are to be
GMR 1.3 Frame Erection / Formwork Erection Page 3 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Preconstruction 2.0
3.0
Erecting Frame Formwork Adopt methods to reduce the risk of injury/falling when erecting single frame formwork/false work; The use of formwork systems (Peri, Boral, etc) that utilise placement of soffit decks from the deck below to manufactures specification and BLL requirements; Erection of U heads, bearers, joists, etc from a fully decked Work Platform no higher than 2m from the ground/deck or a MEWP or suitable work platform; where work has to be performed on the soffit / form deck then the catch platform shall be not less than 2m below and extends a 1 in 1 distance (ie 3m) horizontally. Note lazy joists are not an acceptable method of fall prevention (except where approved by EHS manager as a last resort); Base plates will be used under all frames (no matter what foundation) and all U heads will be centred and secured. The planking out or protection of starter bars or bending bars over and protruding hazards. Where frames are used above 2 frames in lieu of birdcage scaffold Operations Manager and or EHS Manager approval is required. Preference should be given to pouring columns up. Note: (Generally the intent is to prevent falling, therefore it stands to reason that the use of netts is not a preferred method of fall prevention. Where netts are utilised, they should be provided as close as possible to the working deck and be of sufficient tension and strength to support a load close to the work area (i.e. catch the person or material close to the working deck). Note: net installation to be certified by an engineer.
4.0
Deck / Soffit To reduce the risk of injury when working on the deck or soffit: Progressively provide handrails to each work area, midrails and kickboards around completed deck (note consideration should be given to erecting handrails on the ground beforehand); Note: no person can be exposed to a fall during this work. No other trades (ie electricians, steel fixers, etc) allowed on the deck until completely secured by fall protection; All formwork penetrations will be adequately covered and secured. The cover will be highlighted to ensure persons are aware of the penetration below (i.e. secured painted reo / mesh (ie F81) or painted ply white, signage, as per GMR means and methods 1.5 is penetrations etc) Note: Final slab penetrations will include cast in mesh; All loose materials and equipment on the formwork deck must be secured against windy conditions; Ensure all off cuts, sawdust and materials are cleared regularly so no trip / slip hazards are present. (Note consider icy or wet decks and slips); Where timber handrails are used they will be joined & fixed via mechanical means (not just scew
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 4 of 8
6.0
7.0
8.0
10.0 Jumpform 10.1 In design: A separate ROAD (or section of the project ROAD) should be dedicated to the jumpform, with particular consideration given to issues including: height of pour, access, ladders, trapdoors, emergency evacuation, and temporary structure used for assembly, internal work platforms. Design a methodology to safely assemble, jump, disassemble and remove the jumpform system at end of use (including removal of cladding; position of splice plates etc). Wherever possible design out the need to use drop shutters and minimise use where no other option is practical. Use of Drop shutters to be approved by EHSM / Ops Manager. 10.2 Assembly of jumpform system: A Safe Work Method Statement (SWMS) must be developed based on engineer advice and manufacturers instructions. Consideration/hold points may need to be included in the SWMS for other trades that may need to undertake work (ie electrician) on the jump while under erection to ensure a safe system and environment is implemented. Engineer advice / signoff for the temporary support used for fabrication of the grid matrix. Engineers signoff and BLL hold point for the lifting and positioning of the grid matrix. The Engineer will finally certify the jump form is in accordance with the design requirements and is safe for other trades to commence. Note: Project teams should consider engaging a third party engineer to provide these inspection and signoff of the jumpform system after initial assembly. 10.3 Use of jumpform system A suitably competent qualified and experienced jumpform supervisor (ie trained and assessed by the supplier, minimum 1 year working under a jumpform supervisor) shall be in charge of the system, and conduct daily checks of the jumpform. Operators competency log to be completed by the employer. The jumpform supervisor in conjunction with the BLL Foreman is responsible for ensuring hold points and permits in the process are completed as required by the SWMS. A system of pre-jump checklists / permits must be used (number and detail of permits will vary depending on the size and complexity of the system). Examples attached. Advanced rigger present on site to oversee and inspect rigging methods prior to stripping / jumping. After jumping the system, a checklist must be completed by the jumpform supervisor and BLL Foreman to ensure the system is safe to be re-entered by workers. All workers involved to conduct daily pre-start meeting / toolbox talk. Use 2 lifting attachments on drop shutters ensuring 100% redundancy should one lifting attachment fail. Where chain block or hoisting mechanisms are used on individual shutters Drop shutters to be re attached to threaded rods on grid beams before climbing the system.
GMR 1.3 Frame Erection / Formwork Erection Page 6 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 7 of 8
Associated Documents
Pre-pour Checklist Project Delivery Plan Jumpform checklist sample
Resources / Suppliers
Australian Standard 3610 (and suppliers), www.standards.com.au (other relevant standards AS 1820, AS 1576, AS 1577, AS 4576) NSW, Code of Practice for Formwork, www.workcover.nsw.gov.au Victoria, Formwork & Concrete Checklist for Builders, www.workcover.vic.gov.au ACT OH&S Act 1989. ACT OH&S General Regulations 2007 www.workcover.act.gov.au Queensland formwork www.deir.qld.gov.au/workplace/law/ Workright Edge Protection Systems P/L Ph: +61 (0) 2 8824 7776
Page 8 of 8
Revision No 2
4 Scaffolds, Temporary Works and Working Platforms Effective measures must be put in place to ensure the safe erection and use of all scaffolds, temporary works and working platforms (including tower scaffolds). They shall be: Planned by a competent person to ensure the right design and equipment is used for the specific situation. Erected, altered or dismantled by competent workers. Inspected by a competent person when first constructed, after any alteration and on a weekly basis and be clearly marked as safe or unsafe to use. The following criteria should be used to judge if scaffolds and working platforms are safe to use: All structural members are free from visible defects, structure is plumb and adequate cross-bracing is provided. All scaffolds are stable for use with sound footings, wheels locked (where fitted) and tied into structure where base/height ratio is greater than 1:3. Safe ladder access is provided, Working platforms are fully planked, free from defective or damaged planks and debris. Guard rails, mid-rails, and toe boards are installed on all open sides of platforms from which people or materials may fall. Where there is a risk of materials falling over toe boards, means of preventing materials falling must be provided (e.g. netting or fencing). No person is permitted to remain on a scaffold tower platform while it is moved. Means and Methods:
Standard:
Page 1 of 9
Revision No 2
False work with a full deck to allow installation of form work from below. NOTE: This will require full decks at 2m for installation
Brick guards and handrails in Brickies A Frames Brick guards and handrails in Brickies A Frames
Page 2 of 9
Revision No 2
Page 3 of 9
Revision No 2
Install handrails from below on a platform ladder. Then planks installed from below.
Page 4 of 9
Revision No 2
NOTE: 3 times the minimum width base is the maximum height before outriggers are required. (as a rule of thumb) and BLL 1 m rule still applies to mobiles - assembly.
Page 5 of 9
Revision No 2
Scaffolding Fixed 1. Introduction A range of Country/State/Territory Legislation and A/NZ Standards, Codes of Practice and Guides, some of which are referenced at the end of this document, cover scaffolding erection. In some instances the Legislation or Codes may require more than the requirements in this guide. In developing Safe Work Method Statements for the safe erection of scaffolding, the relevant supervisors and scaffolders should be consulted and industry guidelines reviewed. A scaffold certification (eg Scaff tag) tag system should be used on all scaffolds and must be used over 3m high.This system will provide a fit for use confirmation by a competent person on a weekly basis as a minimum or as the situation changes. NOTE: Scaffolding Systems should be kept separate. Mixing of different scaffold systems needs to be signed off by a qualified person. 2. At Design The BLL EH&S system aims to eliminate hazards or if this is not possible, to minimise the risk. Therefore the first step should be to ensure the scaffolding design is reviewed in the Risk and Opportunity at Design for opportunities to eliminate the potential hazards. Where the risks cannot be eliminated the team should consider re-assessing it in the project risk assessment. Qualified persons (ie Structural Engineer) with knowledge/experience in scaffolding must design and certify special class scaffolding eg: cantilevered and counterbalanced scaffolding, scaffolding lifted into position, drop scaffolding, scaffolding sheeted with mesh or signage, any special load conditions, etc. NOTE: Once designed, a competent qualified scaffolder is able to certify that the installation is in accordance with the design and safe for use. 3. Erecting and Dismantling A Scaffolding Certificate of Competency from the relevant Authority is required, if the working platform for scaffolding is where persons could fall a distance greater than 3.0 metres, or near a stairway or on a ramp with
GMR 1.4 Scaffolds, temporary works and working platforms Page 6 of 9 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Associated Documents
Resources / suppliers
Australian Standard (and Attachments), www.standards.com.au (other relevant standards AS 4576 Guide for Scaffolders, AS 1576 Scaffolding, AS 1576.1 Scaffolding - General Requirements, AS 1576.2 Scaffolding - Couplers and Accessories, AS 1576.3 Scaffolding - Prefabricated and Tube-and-Coupler Scaffolding and AS 1576.4 Scaffolding - Suspended Scaffolding) NSW Workcover policy paper on scaffolds
Page 9 of 9
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
5 Penetrations, Risers and Shafts Effective measures must be put in place to prevent falls of persons or materials down penetrations, risers and shafts. All lift/elevator shafts shall be constructed in such a way so as to protect both those carrying out the construction and those below carrying out the lift installation. Safe working platforms should be provided for all those working in lift shafts. Openings to lift shafts must be fully protected with a secure, full height system which prevents unauthorised entry and prevents the risk of falls of people or materials. Lift shaft opening protection must not be removed unless a safe working platform is provided or the lift doors are in place. Penetrations and risers should be limited in size and number as far as practicable and have mesh cast in during construction or be fitted with other robust protection such as metal guard rails or covers, which prevent falls through them. All floor openings must be protected with robust, securely fixed (screwed or bolted not nailed) and clearly marked (e.g. Hole below - do not remove) covers to prevent the fall of materials or persons through them. Covers should be constructed so that they do not present a tripping hazard. Protective measures may only be removed when work is actually taking place in or around the opening and effective safety measures employed to prevent falls of those working on them. Protective measures must be replaced as soon as practical and be regularly inspected (at least weekly).
Standard:
Heavy duty metal cover installed at riser shaft NOTE: Needs to have handrail installed where deck is not trafficable.
Steel cage handrail installed to provide fall protection at column opening in formwork ( Column cage being lowered into place)
Page 1 of 11
Revision No 2
Peno Cover
Page 2 of 11
Revision No 2
Purpose made handrails to allow removal of penetration covers for installation of column cages.
Page 3 of 11
Revision No 2
A permit to drill / cut penetration will be used for any penetration larger than 50mm diameter and for all wet coring and saw cutting works or where substrate may contain electricity, gas, water or stressing tendons. All SWMS for drilling into new or existing slabs to take into consideration all known & unknown services.
Page 4 of 11
Revision No 2
Penetrations in Horizontal Element To 150mm formed To 150mm cut/cored 200x 200 to 600x600mm formed or cut 600x 600 to 1000x1000mm formed or cut
1000mm and above formed or cut Penetrations in Vertical shafts and walls (other than windows and doors) with no approved edge protection To 400mm 400 to 2150mm 2150mm and above Other Penetrations Column penetration (deck formwork) Pier hole (in ground) to 250mm to 1m Pier hole (in ground) above 250mm to 1m
NOTE: Use (floor to ceiling) mesh with kickboards if you need to work near the edge of the penetration and there is a potential for falling.
WARNING
PERSONS WORKING ABOVE
Barricade the area on the same floor: at least 1.0m from the edge of the penetration or enough space to perform the work; and place sign(s) e.g
WARNING
ACCESS ONLY TO AUTHORISED PERSONNEL
1.3.
If there is the need to cut the mesh by 250mm square or more, provide: (in order of preference) protection/barrier to prevent a person falling 2m or more; or
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 5 of 11
Only remove enough timbering and mesh required to do the work. Replace any timbering removed for inspection. Seal around fitting(s) (eg: service pipes, service ducts, doorframes, etc.) going through or placed in the penetration.
2.0 Use floor to ceiling mesh with kick boards (as shown below) if you need to work near the edge of the penetration and there is a potential for falling.
"X"
Page 6 of 11
Revision No 2
Do not store/ move material or equ ip ment over these p enetration protections w ithou t the d esign and certificate from an engineer (a). Formed or Cut Penetrations
12mm Dynabolt or screw fix 100 (min)
Examp le of Sign where required 18m m H DPE or 100 painted ply or Metal Plate (m in)
Floor Slab
(m in) (m in)
Floor Slab
.......
200 mm to 600m m
Floor Slab
12mm Dynabolt or screw
100 (min)
..............
Floor Slab
600mm to 1000m m
100 (m in) 12mm Dynabolts 1 lot secures the mesh, the other secures the timbering 100 (m in) 12mm Dynabolts or screw s
Floor Slab
50 x 50 x 5 mesh - 150m m min. larger all arou nd than the p enetration. Secure sep arately
Page 7 of 11
Revision No 2
(a). If access is not possible from the underside use this method
Example of Warning sign Wall DANGER PENETRATION BELOW
SWL where required
..............
. . . . . . . . . . . Slab
150mm into the concrete for formed penetrations Note cast in 3 sides
Secure cover timber to slab 18mm HDPE or Painted Plywood or metal Plate
100mm min
............... .. . . ... .. . . .
12mm dynabolt to secure mesh
Slab
150mm into the concrete for formed penetrations Note cast in 3 sides
Page 8 of 11
Revision No 2
100 m in
50 x 50m m Mesh - 150m m larger all around and secured separately or plyw ood min (18<mm )
NOTE: Where mesh only is used on lift entry / stair well penetrations, then minimum 1200mm high ply is to be fixed horizontally across opening to act as kickboard and extra strength & support.
Page 9 of 11
Revision No 2
A Structural Engineer must design the size and spacing of timbers steel and bolts (they vary with opening size). Note: SWL to be determined onsite based on spans and manufactures recommendations.
N ote: cover should be replaced w ith mesh d uring installation of column bars or temporary hand rail system
. . . . . . . . . . . . . .
Pier hole
Ground
Ground
Page 10 of 11
Revision No 2
Pier Hole
Agreed Min. distance for Soil Type (Consult with Geotech Eng.)
Do not remove mesh panels until pier hole is filled with concrete
Pier Hole
Ground
Above 250mm
Ground
Related Information
Permit to drill / cut Harness Permit
Suppliers / Resources
Page 11 of 11
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
6 Ladders The use of all types of ladders should be minimised as far as reasonably practicable by effective work planning and employing safer means of working at height, e.g. by using equipment such as scissor lifts, scaffold towers and podium steps. All ladders should be:
Standard:
Structurally sound, safely installed and used only as a means of access (unless three points of contact can be maintained during works). Secured top and bottom or footed to prevent movement and extend at least 36 inches (1m) above landing or work platform. Step ladders should not be used unless approved under risk assessment by the general foreman / site manager.
Small ladder platform allows the worker to stand on a platform incorporated into the ladder. Ladder platforms come in various sizes.
Page 1 of 4
Revision No 2
Page 2 of 4
Revision No 2
6. Ladders should never be used on balconies or slab edges where fall prevention is not provided.
Page 3 of 4
Revision No 2
Related Information:
Mobile Equipment Tag
Suppliers / Resources
Page 4 of 4
Revision No 2
7 General Precautions / Work on roofs All construction materials that might be blown or swept off of roofs, exposed floors or scaffolds must be effectively secured when work has ceased and/or high winds are predicted. Protected walkways should be constructed over any access ways where there is a risk of materials falling into them. Where there is a risk of injury from persons, plant and/or materials falling into excavations, pits and holes or from the collapse of the excavation sides, barriers or edge protection should be provided or the edges sloped to gradients, which prevent falls, and/or a suitably designed trench support system should be introduced. Where water is present, additional measures should be taken to prevent drowning. All loading platforms must be assessed before installation and be fitted with guard rails to all sides where people or materials may fall (see Global Safety Alert on Loading Platforms). All mechanical access systems used for work at heights should be adequately assessed for use, have not been adapted without manufacturers approval and be used by suitably competent and trained personnel under managed guidelines. Guarding should be robust and fit for purpose. Restraining harnesses must be worn and secured by persons working in MEWPS with articulated booms. Regular inspections are needed to ensure continued suitability for safe use. Rubbish chutes and skips/dumpsters used for rubbish disposal (from upper floors) must be located and/or fenced off so as to prevent danger to the public and workers. All persons working on suspended access equipment (bosuns chairs/cradles/gondolas/swing stages) must carry out a risk assessment tio ensure additional levels of protection including where possible use of appropriate fall prevention equipment to effectively protect them at all times from any failure of any part of the equipment and its suspension system (i.e. independent of suspension line or the access equipment). Access to general work floors should be provided by the full permanent solution where ever possible. Where this is not possible, temporary staircases of adequate width and complete with handrails should be provided. The permanent solution should be no more than two floors behind the progress of the construction. Any temporary structure should be structurally sound and designed for the specific purpose it is put to.
Standard:
Page 1 of 9
Revision No 2
Page 2 of 9
Revision No 2
Secured materials
Page 3 of 9
Revision No 2
2. Overhead Protection Particular care taken to ensure overhead protection or exclusion zones are installed in any location where works are occurring above or there is risk of materials or persons falling. This includes scaffolds over loading dock entries. 3. Securing Materials All external areas of sites and scaffolds are to be inspected daily for loose materials that can be blown or swept off roofs and scaffold. All timber and sheet material on any scaffold to be nailed down or restrained.
4. Access equipment In line with manufacturers requirements, harnesses must be worn and secured at all times when working in MEWPs. Log books shall be checked regularly and at least weekly for currency of maintenance and safety checks. Access equipment should have a MET (mobile equipment tag) to validate that it is approved to be used on site. 5. Swinging Stages: Persons working in bosuns chairs, swinging stages and the like are to have alternate means of fall arrest in redundancy to the equipment (swinging stage etc) where this is appropriate and where it does not introduce unnecessary risks (i.e. not for long drops where lines may become entangled). The use of Swinging stages must include: Roof rig / cantilever design must be carried out and certified by a qualified Engineer. Initial installation of the stage, must be signed off by a qualified Engineer. Hold down bolts or counterweights MUST be locked in place with tamper proof means.
Page 4 of 9 Issue date 1 July 2008 Last amendment date 1 July 2009 Revision No 2
NOTE: abseiling (twin rope access system) and rope access is a last resort and where possible, this should be designed out through the use of BMUs, walkways or the like. NOTE: consideration should be given to enclosing the MEWP basket with wire and mesh (wind load needs to be considered) to : Ensure that material or equipment can not fall out and; Ensure that personnel can not stand on midrail or toeboard for extra height. 6. Drugs and Alcohol: Persons working on site are not to be under the influence of drugs or alcohol at any time during work hours. 7. Work on Roofs 7.1 Access: Only approved and certified scaffold stair access are to be installed as the means of access/egress for roofs on BLL projects where there is no permanent stairs. Scaffold stair access must include external protective wire mesh secured at ground level and a lockable access door. The door is to have appropriate Authorised Persons Only Passed This Point signage or similar and the relevant area foremans phone contact details clearly displayed. The location and duration of stair access we be determined by BLL site management. NB. Where single stair is provided, then provision for emergency retrieval of injured workers is to be included in the Safe Work Method Statement provided by the subcontractor that is working on the roof. 7.2 Guardrails: It is the responsibility of the roofing sub contractor to have approved guardrails fitted by appropriately trained personnel on all roofs where metal roofing is to be installed. The installation of the guardrails should include the following: Toe boards or mesh infill to prevent tools, material and debris falling from the roof, unless a No Go Zone is established below the area where roofing works are being carried out and the slope of the roof is less than 15 degrees. An additional mid-rail to ensure the nominal clear distance between rails does not exceed 450mm, and A third rail or in-fill panel where the distance through which a person may fall between the work surface and the mid-rall exceeds 250mm. The temporary guardrail is to remain in place to the perimeter of the roof until a roof access system that compiles with AS/NZS 1891 has been installed and certified. A Harness Permit must be sought and obtained from BLL Site Management prior to using any roof access system. All cappings, flashings, gutters to be installed (where possible) prior to removing the guardrail. NOTE: competent roofer to sign off that roof mesh has been installed and completed prior to workers accessing the area.
Page 5 of 9
Revision No 2
Roof Purlin
Transverse wires
NB: ACCESS STAIR(s), GUARDRAILS & SAFETY MESH MUST BE INSTALLED BY COMPETENT PERSONS AND BE IN PLACE PRIOR TO ANY PERSONS BEING PERMITTED TO ACCESS THE ROOF AREAS. 7.4 Edge protection & roof layout:
Position first load as close as possible to access tower and portal frame
Page 6 of 9
Revision No 2
Fresh winds
Page 7 of 9
Revision No 2
Examples of bracing, all bracing to be specified by the structural Engineer Core Filler and stiffeners: C Blocks or clean out blocks will be used for core filled walls to ensure that core fillings is carried out satisfactorily. Core filling shall be carried out progressively as specified by the structural engineer (generally never more that 1.5m in height at a time.)
Suppliers / Resources
AS/NZS 4389: 1996 Safety Mesh AS 1657: 1992 Fixed platforms, walkways, stairways & ladders AS/NZS 1576.1:1995 Scaffolding General Requirements AS/NZS 4576: 1995 Guidelines for Scaffolding Issue date 1 July 2008 Last amendment date 1 July 2009 Revision No 2
Page 8 of 9
NSW;
OHS Regulation 2001 Code of Practice Safe Work on Roofs Part 1-Commercial and Industrial Buildings Safe Working at Heights Guide 2006
Page 9 of 9
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
Standard:
All locations shall effectively control access to the site/premises to prevent unauthorised persons entering and to record all persons (workers and visitors) entering and leaving the location for accounting purposes in emergency situations.
Page 1 of 6
Revision No 2
Turnstiles
Secure Perimeter
Page 2 of 6
Revision No 2
Turnstile reader
Page 3 of 6
Revision No 2
Check
Page 4 of 6
1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15
1.16
2.0
Site induction is to be face to face and should be carried out by a BLL senior team member.
Page 5 of 6
Revision No 2
Related Info
Visitor register Vehicle Entry Permit / Tag
Suppliers
www.blueglue.com.au
Page 6 of 6
Revision No 2
2 Fencing All construction works in the vicinity of members of the public must be fenced off to prevent unauthorised access. All works lasting more than a few hours should erect suitable fencing or hoardings to prevent unauthorised access. Access points and site rules should be clearly signed. Hoardings and signage should follow the Corporate Brand Style Guide and where possible be constructed from sustainable materials ie; recycled or sustainably harvested.
Standard:
Consideration to dust control and sealed haul roads for longer duration temporary roads.
Page 1 of 3
Revision No 2
Transportable segregation
Page 2 of 3
Revision No 2
It is suggested that any and all materials used in hoardings and fencing are of the highest quality. Any anti graffiti system attached to the hoarding must not introduce any new risks. All temporary wire fencing (ATF type) must be installed and signed off as erected to the manufactures specifications. Short term barricading around small short term work areas is permissible where full height fencing is not achievable. All fencing and hoardings are to conform to the BLL Global branding guidelines, unless an agreement with the client prohibits this.
NOTE: Remember any fencing on a project is highly visual and gives the public or subcontractors and visitors an impression of BLL, this should be of a high standard. Consideration of new materials should be given to high impact public areas. 2.0 Segregation It is the intent at all times to provide vehicle and pedestrian segregation. Ensure planning and site layout addresses this issue.
Related Information
Bovis Lend Lease Site Signage and Branding Guidelines for internal Users.
Suppliers / Resources
Page 3 of 3
Revision No 2
Weekly (or more often if deemed necessary due to location or risk assessment) inspections of all perimeter security must be completed and documented. NOTE: Temporary fence is to be inspected daily. 6 monthly engineers inspection is required on A+B class hoardings.
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
3 Public Protection All practical means shall be employed to protect the public from any hazards arising from our undertakings, including falling materials and the movement of vehicles into/out of our sites/premises. Projects must: provide robust protection to all public areas which could be negatively impacted by our undertakings; take effective measures to protect the public during lifting operations and vehicle movements; keep public walkways and roadways clean and free of construction-related hazards or materials at all times (except for cordoned-off areas); establish safe pathways whenever public access ways are blocked off due to construction activities; and employ effective dust, noise and vibration control measures.
Standard:
Page 1 of 4
Revision No 2
Consideration to additional lighting to make sure the area is very well lit
Overhead protection
10Kpa overhead protection where ever any lifting is carried out overhead
Page 2 of 4
Revision No 2
Page 3 of 4
Revision No 2
Related Information
Suppliers / Resources
Page 4 of 4
Revision No 2
4 Pedestrian and Vehicle Safety All locations must assess the risks presented by the movement of pedestrians, materials and vehicles around the site and implement effective safety measures to eliminate or minimise these risks. Separate site entrance points for pedestrians and vehicles should be established to keep them apart. Barriers, guard rails, etc. should be used to form pedestrian routes around the site where vehicles operate in close proximity. Pedestrian crossing points should be provided across vehicle routes to access main work areas. Adequate signs, lights, fences and barricades must be used to inform drivers and pedestrians of hazards and precautions. Parking areas should be established for different kinds of vehicles, e.g. trucks and private vehicles. Delivery procedures and storage arrangements should be detailed, including crane loading areas. Reversing operations should be eliminated as far as possible by the use of oneway systems or be effectively controlled to prevent risk by establishing pedestrian exclusion zones, using traffic signallers to direct drivers or visibility aids on vehicles, e.g. Closed Circuit Television (CCTV). Trained traffic signallers must be used to control vehicle movements in confined or congested areas.
Standard:
Note where water filled barriers are used, check that they comply with local traffic regulations
Page 1 of 5
Revision No 2
Pedestrian routes
Page 2 of 5
Revision No 2
Pedestrian segregation
Pedestrian segregation
Page 3 of 5
Revision No 2
Vehicle entry permit clealry shows map fo site and emergency egress
1.0 General 1.1 Initial site layout to identify the need to have exclusive segregated access for all persons entering our sites. 1.2 Site layout to stipulate vehicle entry and exit points. 1.3 Sites to develop site specific traffic management plans, methods to follow the hierarchy of control. 1.4 Correct plant/pedestrian signage to be erected at points where both are required to enter and exit. 1.5 Where persons and plant will interconnect, barriers/safe zones are to be erected. Where there will be a large volume of pedestrian traffic, a pedestrian crossing will be marked, correct signage will be erected, lighting will be considered, flashing lights will be posted either side of the crossing, a map of the crossing points will be given to all drivers as part of their induction. 2.0 Deliveries 2.1 Each site will have strict delivery times. Restriction of vehicles to be enforced. Only plant and machinery necessary of actual works are to be allowed on to site. No storing or parking of vehicles or plant to be allowed. Strict enforcement is required. (no delivery out of hours unless BLL staff are present). Where practical all delivery vehicles will enter from a single point, proceed through a well marked and sign posted route to a drop point, lay down area on the site. They will exit the site from a separate gate from the entrance.(one way traffic system). A portable road plan to be sent to the contractors for delivery purposes prior to commencement or works and a laminated site road plan be given to the driven at arrival as part of the vehicle entry permit/
2.2
2.3
Page 4 of 5
Revision No 2
On site, clear, defined and maintained permanent and semi permanent walk access structures are to be erected. A clearly defined distance is to be maintained from pedestrian walkways and trafficable roads. All persons on site to wear hi viz clothing when working in and around plant, clothing as per the global PPE policy. Note: High viz clothing should as a minimum be: - Fluorescent - Have high visibility reflective strips (yellow king gee type cotton shirts that are not fluorescent do not comply) 2.4 All vehicles to have an identification card / sticker (or alternate method of tracking entry) as part of the vehicle entry permit which when viewed will confirm areas, that vehicle can access. All vehicles, must have as a minimum, flashing lights, reversing beepers (utes excepted) as appropriate, and be fit for use when entering any site construction zone. When drawing site crane position plans, consideration to be given to allocating specific loading zones, and where practical, an exclusion zone diagram for overhead lifting should be introduced. Revision dates and times and methods of evidence for traffic/access egress, pedestrian etc management are to be recorded and added to the site safety plan, these to include traffic plan, all vehicles access egress points, pedestrian walkways. Etc. They are to be updated and changes communicated to all site personal as the situations change. Designated loading / unloading zones should also provide adequate fall prevention from when access vehicles / trucks to sling. 2.5 Delivery drivers are to have correct PPE (gloves, glasses, hard hats, high vis and steel caps) or stay in cab. Where possible vehicle access to site will be restricted. Parking areas will be well signposted and preferably offsite. A safe system of unloading will be provided. No person shall place themselves at risk from falling from the back of a truck.
Suppliers / Resources
Page 5 of 5
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
5 Operator Competence All vehicle operators must be competent (certified/licensed) to operate the plant and vehicles they are assigned to and be briefed on their use and particular hazards associated with the site. Checks must be made to ensure the competence of drivers (link to Global Alert on Quick Hitch Systems).
Standard:
All operators must follow the manufacturers instructions and site rules - while operating, seatbelts must be worn and mobile phones turned off. Vehicles must be braked/stabilized during loading/unloading and checks made to ensure loads are adequately secured before leaving the site.
1.
All sites to verify all competency based tickets. Where practical, a copy of their drivers licence or photo ID should be included as proof the person presenting the plant ticket is the same as the person on the licence. This should be attached to their induction sheet (where copies are taken). This will be recorded on the site safety passport. The contractor must supply a list of all competency based ticket holders to the site prior to works. This can be cross referenced against the induction records. Daily pre start sheets will be maintained by all operators of all plant while on site, this to be in accordance with any and all requirements set out in the operators manual and manufactures/hirers requirements. i.e.;
Page 1 of 2 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
2.
4. 5. 6.
7. 8.
9.
10. Drugs and alcohol (including being under the influence) will not be tolerated at any time whilst on site. 11. Random Alcohol and drug testing may be carried out at BLLs discretion on BLL sites.
Related Information
Suppliers / Resources
Page 2 of 2
Revision No 2
6 Powered Mobile Equipment All powered mobile equipment and vehicles must be suitable by design and adequately maintained to enable them to conduct their assigned tasks safely. Regular checks by competent persons must be carried out and recorded to ensure all mobile equipment and vehicles are maintained in a safe condition following the manufacturers instructions (link to Global Safety Alert on Quick Hitch Systems).
Standard:
All powered vehicles (excluding MEWPs and other work equipment not designed for use on public highways) must be in good condition fitted with effective brakes, horn, lights, reflectors, seat belts, visibility aids (e.g. mirrors or CCTV) and visual or audible warning systems (lights or alarms).
Handrails plant
Page 1 of 8
Revision No 2
Mesh infills on MEWPs where adjacent perimieter or exclusion zone can not be implemented (ensure wind load is checked)
Ensure adequate sole boards and adequate stable substrate (check location of large pits and pipes) Warning decals are legible and easily read
Blow cut head and ball catcher for concrete pump clean out.
Page 2 of 8
Revision No 2
1.0
1.9
1.10 All equipment will have adequate handrails / fall prevention system for maintenance, refuelling etc. Note best practice will entail machinery having their own purpose made handrails and access. 2.0 2.1 Prior to plant and equipment arriving / used on site Subcontractor and / or supplier to provide documentation to certify the compliance of the plant and equipment to relevant standards, legislation and / or Manufacturers specification and safe to use. This certification to be carried out by a qualified person such as a plant mechanic, fitter, mechanical engineer, motor trades person In some instances an item of plant and equipment may require a number of certification by different qualified persons (eg a crane or hoist may require plant mechanic, electrician and rigger to certify different components or specific configuration to be used.)
2.2
The operator of the plant or equipment shall be sufficiently trained to be able to operate it competently and safely. Where required by legislation, the operator shall hold an appropriate certificate of competency. Where no certification is required by legislation, the subcontractor must supply training records which identify the specific type of plant and equipment the person has been trained in (eg sheepsfoot roller, x brand semi automatic quickhitch).
Page 3 of 8
Revision No 2
1.8
Protect all edges (suspended slabs etc) around where equipment is being used to prevent driving off that edge. i.e.: barricades must be suitable.(wheel stop or angle etc)
2.4
3.0 Ongoing use and maintenance of plant and equipment on site 3.1 The Operator or Competent person shall undertake daily documented inspections of the plant using a logbook or checklist which is relevant to the type of plant and equipment and the installed safety devices (ie dont use a checklist designed to check a piling rig for a crawler crane, ensure specific safety alarms and limit devices where installed, are inspected and tested daily). Where the same items of plant and equipment are used for different shifts, each shift operator must conduct a documented inspection, as above (a separate second logbook / checklist may be required, or subsequent Operators need to countersign the first daily logbook / checklist entry). The subcontractor / owner of the plant and equipment should provide evidence of the manufacturers specification detailing the ongoing service requirements (ie monthly, 200hrs, yearly, 10 yearly etc.). Where no manufacturers specification are received, BLL will request evidence of service on a monthly basis, unless another timeframe is specified by legislation or standards. (Use current BLL Plant and equipment ITP as a guide to determine these other timeframes). All subcontractors to supply BLL monthly with evidence verifying that the plant and equipment on site has been maintained and serviced to the manufacturers specification by a QUALIFIED person (ie plant mechanic, fitter, motor trades person, mechanical engineer etc). As the BLL project team member designated responsible for the management of EHS the Site Manager (or their delegate, eg areas foreman) must conduct EHS inspections of the plant and equipment to verify these service records, on a monthly basis. BLL foreman to regularly verify subcontractor daily checks are conducted by a competent person (usually the Operator), and documents this review (eg BLL foreman diaries, EHS Self-assessment checklist etc.) on a minimum monthly basis. BLL site manager to verify BLL foremen check on plant and equipment and documents this review (can be noted as part of the weekly EHS committee inspection, or site manager review of foremen diaries), on a minimum monthly basis. Construction Manager to verify Physical GMR No. 2.5 conditions are met (ie cranes and hoists, aerial platforms and scissor lifts must have a competent driver, and certified and serviced by a qualified person, and documents this review (eg monthly GMR inspection of plant with Regional EHS Manager, review of site manager inspections foremens diary) on a minimum monthly basis.
3.2
3.3
3.4
3.5
4.0 Quick hitches 4.1 4.2 All semi automatic quick hitches shall be supplied with a safety pin to prevent inadvertent disengagement of the quick hitch / bucket / attachment. AS 4772 requires: All quick hitches shall be fitted with a safety system (this can be either a pin manually inserted, automatic key control, etc) that ensures retention of the attachment to the quick hitch by mechanical and positive means in the event of failure of the primary retention system. Means of verifying the engagement of the safety system shall be available from the operators position. This means shall be stated in the operation sand maintenance manual supplied by manufacturer.
Page 4 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
4.3 4.4
The standard requires quick hitches to be maintained regularly, therefore this should be carried out on a monthly basis by a qualified person, and inspected as part of the daily inspection by the operator. Persons / subcontractors operating plant with quick hitches need to provide evidence that the operators have been instructed on its safe operation and use.
5.0 Mobile Elevated Working Platform (MEWP) A National Certificate of Competency WP is required to operate Boom type MEWPs over 11 metres. For other types of MEWPs some proof of competency / training record is to be provided. Yellow cards as issued by or on behalf of the Elevated Work Platform Association of Australia are acceptable. Refer to section 2.5 Means and Methods. 5.1 The operation of MEWPs is to be documented in a Risk Assessment / SWMS taking into account any overhead projections / power lines. Travelling with the work platform elevated should not be undertaken unless inline with the manufacturers specifications and that the operator has clear view of the base structure which is a firm level surface free of undulations, obstructions, potholes step-downs etc. Wheel stops to be implemented when operating on suspended slabs. The machines log book is to be completed at the beginning of each shift. Suspended slabs will need to be verified and signed off by an appropriately qualified person i.e Structural Engineer and similarly certain ground conditions may need verification of the maximum allowable ground bearing pressure by a Geotechnical Engineer. MEWPs are to be equipped with an audible warning device and/or a flashing light which indicates that the machine is in operation. Self-propelled MEWPs are to be fitted with an alarm or other warning device that activates when the machines base is out of level. All controls must be clearly marked with legible decals to show their functions. The SWL, number of permitted persons, wind rating are to be clearly displayed on the machine. Full body Safety Harnesses to be worn at all times in boom lifts and the lanyard connected to the designated anchor point. Persons shall stand on the floor of the MEWP only which is to be kept clear of trip/slip hazards. Access onto and egress from the work platform, shall only be at designated positions unless the MEWP is in a breakdown or emergency situation. Where applicable, a procedure shall be developed to allow safe access to the work platform where the MEWP is at a location other than its designated landing position. This can only occur if all the requirements of Clause 5.9 AS 2550.10 are satisfied. OPS Manager and EHS Managers approval is required. If working in close proximity to other workers or a situation where there is a possibility of tools/materials falling from the MEWP platform, then the area below (including slew area) is to be barricaded (parrawebbing as a minimum) and appropriate signage displayed thereby establishing an exclusion zone. The use of a spotter may also have to be considered. Tools and materials must be adequately secured on MEWP and wrist lanyards may need to be used on tools. A suitably sized mesh material should be considered for fixing around the inside of the work platform to prevent persons standing on the toe boards / midrails and any loose materials/tools falling out. Where mesh material is used, consideration is to be given to potentially increased wind loading on the machine particularly when elevated and manufacturer / suppliers advice shall be obtained.
Page 5 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
5.2
5.3
5.4
5.5
5.6
5.7
5.9
5.10 Where gas cylinders are to be carried on a MEWP, the cylinders are to be adequately secured and only the minimum quantity of gas sufficient to carry out the work should be transported. Fusible plugs shall be directed away from the platform and a fire extinguisher carried. Gas cylinders shall not be carried inside platforms that could trap an accumulation of gas. 5.11 MEWP should not to be used as a crane/hoist. All lifting is to be undertaken within the machines safe working loads and applicable standards i.e. long loads should not be supported on the handrails of the MEWP unless designed for the application. Lifting operations involving more than one MEWP should not be undertaken. If such lifting operations are necessary, the lifts shall be treated as a designed lift in accordance with AS 2550.1 5.12 A MET tag/sticker is to be issued by BLL and displayed on the MEWP and machine details entered on to the BLL Project Plant Register. 6.0 REFUELLING OF PLANT ONSITE 6.1 6.2 6.3 The Project Impacts and Hazards Risk Assessment shall assess using the hierarchy of controls all refuelling activities onsite and Operations will aim to minimise the need bulk for storage on site of fuels. Ensure the Projects Emergency Response Plan includes procedures/requirements to respond with spillage of fuels on site. A Safe Work Method Statement will be developed for all refuelling activities. The SWMS should include procedures into emergency spills response and all persons responsible (ie Supervisor, Plant Operator, Mini tank driver, etc) will be trained into the SWMS and spill response. Refuelling of onsite plant should be undertaken where possible in a bunded area of sufficient size so as not to put the environment at risk. Any bunding facility will be designed to ensure a storage capacity of 110% of the actual product storage container. Sufficient spill kits (min 5 bags of Dryzsorb) of sufficient size will be readily available when refuelling by mini-tanker. The spill kit shall be included in the weekly inspection to ensure it is operational in an emergency All spillage on site will be collected using spill kit materials with all waste generated to be disposed to an approved facility and the area remediated to the satisfaction of the DEC. Records of disposal and cleanup measures are to be maintained with site records. Maintenance and cleaning done in appropriately designed and designated areas. Plant and equipment checklist to be completed weekly by operators and repairs undertaken if required. Adequate Fire Fighting Equipment to be kept in designated areas.
6.4
6.5
6.6
7.0 Concrete Pumping 7.1 The siting of the pump is to be reviewed in consultation with the pump operator for suitability and any potential hazards/ risks that may exist prior to pumping operations beginning. Outriggers / stabilisers shall be fully extended unless the manufacturer specifies otherwise. Suspended slabs will need to be verified and signed off by an appropriately qualified person i.e Structural Engineer and similarly certain ground conditions may need verification of the maximum allowable ground bearing pressure by a Geotechnical Engineer. All pump operators to be experienced (Operator Log to be completed by the Employer refer to 2.5) and Boom pump operators to be holders of the National Certificate of Competency PB. Refer section
Page 6 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
7.2
7.3
7.6
7.7 7.8
7.9
7.11 All quick release clamps/couplings must be fitted with safety clips prior to pumping to prevent accidental release. 7.12 Spotters must be used to back concrete agitator trucks on to the hopper of the pump. Hopper grates must be down during pumping and NEVER ALLOW ANY ONE TO STAND ON THE HOPPER GRATE. 7.13 Hearing protection is to be worn by persons in close proximity of an operating pump /discharging concrete agitator trucks. A suitable communications system is to be used where the pump operator does not have line of sight with the delivery hose and/or linesman or is too far away. 7.14 A documented pipeline purging/cleaning procedure is to be developed with preference given to using water rather than air (where possible). Where purging is carried out using air, unless discharged into a correctly designed receptacle, an appropriate catch basket shall be securely attached to the discharge end of the pipeline prior to purging operations commencing. Appropriately experienced personnel shall only undertake this task. 8.0 Piling Works 8.1 8.2 A comprehensive SWMS will be in developed from a risk assessment prior to any work with a drilling/piling rig being undertaken. Unguarded/open pier holes are not permitted. Guardrails or screens will be installed and secured prior to pier holes being excavated. The guardrail/screen system should not allow removal to pour
Page 7 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
7.10 Fixed/Static pipelines are to be adequately secured and supported to the building or structure with particular attention given to reaction forces, which may be considerable where high pump pressures are involved. Pipelines are not to be fixed to scaffolding, hoists, crane towers, formwork etc. Minimum fixing requirements:
8.10 BLL to provide geo-tech compaction test results to the Piling contractor confirming that the working platform(s) where the rig will be sited is sufficient to take the load. 8.11 Ensure BLL permit to excavate in place prior to any works commencing, (Do not rely solely on the information gained from a Dial Before You Dig, Minimum services scan of the area required). 8.12 Ensure piling/drilling rig is well clear of overhead services (ie electrical).
Related Information Plant and equipment register Vehicle entry permit / tag
Suppliers / Resources
Page 8 of 8
Revision No 2
7 House Keeping Housekeeping must be effectively managed on all projects to maintain a clean and tidy work site, e.g. by having dedicated service gangs and/or a system for dealing with poor performing contractors (contra-charging). All main access ways, emergency routes and passage ways must be clearly lit, marked and kept free from obstructions and debris to reduce the risk of trips and slips. Temporary electrical supply cables should be located so as not to present tripping hazards (off the floor or away from access routes as far as possible). All materials must be safely stacked, away from fences and hoardings, and located to minimize re-handling and reduce transport distances.
Standard:
Combustibles, flammables and other dangerous materials must be stored safely and clearly identified, e.g. highly flammables must be kept in fire resistant containers. Risks of cuts and punctures from sharp objects should be assessed and controlled, e.g. needle handing, safety knives, gloves, removal of protruding nails, protection or curving of reinforcement bars, use of safety glass, etc. Signs are posted where necessary to provide clear instructions - No Smoking, No Entry, Personal Protective Equipment (PPE), etc. Waste must be effectively managed by minimisation, segregation and recycling, and performance monitored and recorded.
Provide adequate rubbish bins at workface. Ensure that they are suitably engineered for crane lifting if appropriate.
Page 1 of 5
Revision No 2
Page 2 of 5
Revision No 2
Good housekeeping includes making safe and PT bars with safety caps
Page 3 of 5
Revision No 2
1.0 General 1.1 1.2 1.3 1.4 1.5 1.6 1.7 Clearly define access ways & ensuring that no materials are stored within these areas. Ensure subcontractors have allowed for a daily clean of work area and it is included in the contract. Monitor & Plan deliveries to ensure materials are only delivered on a just in time basis. Provide designated storage areas for hazardous substances, Plant & equipment & materials. Develop a site management plan clearly outlining the following loading zones, access & egress, materials storage, site offices, first aid stations. Consideration should be given to waste segregation and recycling areas. Each site must have dedicated full time cleaning crews controlled by a BLL supervisor (as a package). Sites must be maintained clean and clear of trip hazards at all times. These crews can be subcontract or BLL attendant labour. They are to be responsible and accountable for the cleanliness of the site. This is over and above the trade subcontractors own clean up which is also daily. The supervisor or leading hand of the cleaning crew is to report to the general foreman. Access ways are NEVER to be blocked by materials stacked, stored or rubbish and debris (this includes firestairs etc). Access ways and all areas where work can be carried out and accessed are to have a suitable level of lighting to provide safe access. This means all rooms, corridors, stairs, plant rooms etc must have temporary lighting for access. This is over and above the trade subcontractors task lighting. (refer to GMR
Issue date 1 July 2008 Last amendment date 1 July 2009 Revision No 2
1.8
Page 4 of 5
3.3 4.1
4.0 Smoking
Suppliers / Resources
Page 5 of 5
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
1 Pre-planning All proposed ground works should be assessed and the safest practicable methods employed to carry them out, e.g. micro-tunnelling, directional drilling, pipe-relining, etc.
Standard:
All underground services (electricity, gas, etc.) must be located and marked before excavation works commence as part of a permit to conduct ground works process. Checks should be made to ensure the structural integrity of temporary works.
Page 1 of 3
Revision No 2
2.0 Noise, Dust and Vibration 2.1 Consideration should be given to providing monitoring. This will allow both reporting and better control over conditions. All benched excavation should include for ongoing full time dust control such as water trucks or pva sprays etc. 2.2 It is recommended to provide existing background monitoring prior to construction so that full impact of construction can be assessed. 3.0 Services Search 3.1 Prior to the start of any ground works, projects must have undertaken an in-ground services survey and where possible consulted all relevant authorities. Test pits should be dug carefully to confirm location of services. 3.2 The locations of all underground services are to be marked on a site plan and communicated to all relevant contractors (where appropriate these should be identified on site drawings for relevant trade packages). 3.3 All high risk underground services (e.g. high voltage cables) shall be clearly signed and their locations easily identifiable in the field (refer project risk assessment and in ground services drawing). Placing temporary site services underground should be avoided so as to minimise any further risk of hitting hidden services. This is to be achieved only where practicable and where locating the services in an alternate manner presents an increase in risk. 4.0 Adjacent Properties / Dilapidation 4.1 Prior to any excavation adjacent to structures or buildings, ensure that a dilapidation report is carried out. This should include photos and or video as a minimum. 4.2 Consideration must be given to stability of adjacent to structures in the risk assessment for the groundwork and appropriate shoring or measures introduced. 5.0 Access & Egress
GM 3.1 Pre-planning
Page 2 of 3
Revision No 2
Related Information
Permit to excavate
Suppliers / Resources
Page 3 of 3
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
2 Stability Excavations should be assessed by a competent person and be shored or battered back/sloped to a safe angle as determined. Adjacent structures, roads and sidewalks must be supported or protected where necessary to prevent collapse.
Standard:
Materials and equipment must be placed at a safe distance from the edge of excavations. Water ingress into excavations must be controlled to ensure safety. Excavations must be inspected daily by a competent person prior to use and after every rainstorm.
Whaling to be signed off by an engineer (note access not shown) Sheeting and piling must be engineered
Page 1 of 4
Revision No 2
Progressive reinforcement
Craneable Stairs
GM 3.2 Stability
Page 2 of 4
Revision No 2
When planning earthworks and excavation, particular attention should be given to stability, type of foundation material and how the material will change with the addition of vibration and or water. 1.0 General Considerations 1.1 All sides of excavation to have either shoring or benching levels at 1:1. The angle of repose should always be observed for collapse and no materials stacked within the same distance as the depth (and never closer than 1m to a trench or excavation. Regular checks (as advised by geo tech) by a Geo tech expert particularly where large excavations or trenches are exposed for greater than 48 hrs and after significant rain periods. Egress / Access. 2 means of access to be assessed to trenches or excavations deeper than 1.5m. Consider stair access over ladders a good practice. Stability of surface on bench for plant and equipment needs to be assessed and hardstand or working platforms provided. (note: benched levels and working platforms need to be certified for load capabilities). Storm water ingress from adjacent properties needs to be considered including means for treating SW before pumping out. Plant, material or spoil heaps should not be stored at the edge or head of excavations causing possible falls into the excavation or a surcharge on the ground. As a guide, spoil pile shall be placed at least 2 metres away from the edge of the excavation. The protection of excavations adjacent to public highways is of particular importance, such that bulk timbers and fencing must be provided to a minimum height of 2m. In addition, adequate lighting and warning notices must be provided. Ground works must be subject to daily inspections to ensure that materials are not placed at the edge of excavation such that they will fall and hit workers in the excavations. Workers are not to work alone or in isolation in any area so that their safety is always monitored.
1.5
2.2
2.3 2.4
3.0 Dewatering 3.1 A de-watering procedure is to be developed with adequate pumps etc available on site for expected conditions. 3.2 Following all rain events and/or flooding, all permits for excavations and trenching shall be suspended pending review of conditions. Only when an area has been inspected and deemed safe can the permit be re-issued.
Page 3 of 4
Revision No 2
3.4
4.0 Safe Work Method Statement (SWMS) / Job Safety Analysis (JSA) At a minimum, the following items need to be assessed: 4.1 4.2 4.3 4.4 4.5 Checking of underground utilities Method of excavation (as directed by the Engineer) e.g. battering back sides of excavation to a suitable angle, to include the minimum distance for spoil and material placement Type and certification of shoring to be used, eg. timber framing, horizontal sheeting, sheet piling, trench box, drag box, hydraulic shoring system. Access methods Dewatering methods Removal of spoil - spoil storage, re-use, removal to off site tip Certification/ Authority Approval (where required) Permit to Excavate Inspection Routine
Related Information
Permit to excavate
Supplier / Resources
GM 3.2 Stability
Page 4 of 4
Revision No 2
3 Safe Works Adequate signage, barriers and lighting must be provided to prevent falls into excavations adjacent to thoroughfares. Temporary stairs should be installed to provide safe access into trenches or excavations, unless they are very short duration ground works when ladders may be used; Exclusion zones must be established and maintained around operating earth moving machines to prevent workers being struck by either the machine or any tool due to the failure of any quick hitch system. The requirements of the Global Safety Alert on Quick Hitch Systems must be followed to control the risks associated with the use of excavators fitted with semi-automatic quick hitches.
Standard:
Page 1 of 4
Revision No 2
1.0 Access 1.1 Safe access shall be provided via temporary stairs, steps, or ramps for trenches / excavations deeper than 1.0m. Sufficient numbers shall be provided (eg for trenches, ensure that no worker is further than 8m from an access). Note Stairs should be considered over ladders as best practice. Safe access for short duration excavations less than 1.0m deep may be provided by suitable benching or slopes Where ladders are selected as the chosen means of access to trenches or excavations due to short duration of the task, the following shall apply: Extend 1m above the original surface of the ground. Adequately secured top and bottom to prevent movement. Only place between shields (shoring) that are no more than 750mm apart. A safe walkway that presents no risk of fall must be provided to ladders giving access within shoring. Ladder must be of industrial grade, inspected and verified to be in good condition.
1.2 1.3
2.0 Fall Protection 2.1 Physical barricades (i.e. tube and fitting or similar construction) shall be provided to mitigate risk of fall into trenches / excavations deeper than 1.5m that are required to remain open for an extended period of time. Where space permits the barricade shall be located a minimum 1.0 metre back from the edge and be covered with safety mesh / parawebbing or other means of physical barrier with high visibility identification (installation must be under a safe system of work that does not present risk to the installer). Where the depth of trench or excavation is greater than 1.5 m the following shall apply: Progressively protected by physical barricading and / or parawebbing / safety mesh for areas left open (e.g. behind pipe laying etc). Backfilling to occur as soon as is reasonably practicable. The distance of barricading from the edge shall be based on a risk assessment and included in the SWMS (as a minimum this should be 1m back from the edge). Where site constraints dictate and this is not achievable, a full risk assessment must be undertaken and other suitable controls documented in the SWMS. Progressive barricading shall be installed 1.5m back from the edge for excavations deeper than 1.5m (where workers are required between the barricade and the edge). Where site constraints dictate and this is not achievable, a full risk assessment must be undertaken and other suitable controls documented in the SWMS.
2.2
Page 2 of 4
Revision No 2
2.3
When laying pipe etc the gap between the excavator and the works may not always be barricaded, in these cases there must be full time competent supervision (spotter) to ensure that no persons enter the area. All pits are to be protected with the permanent cover or a secured temporary pit cover of solid construction. Personnel must not stand on the edge of shoring systems, manhole forms or pre-cast manhole. All excavation and trenching work is to be controlled by a Permit to excavate system. There must be no lifting of material over personnel in the trench / excavation. All lifting operations are to be undertaken by competent personnel. Shoring systems used for ground stability control may be considered adequate edge protection for materials if at least 300mm proud, and for fall protection, at least 1m proud of the ground. For all trenches and excavations, a suitable site based risk assessment shall be undertaken with required fall protection and access requirements documented in the SWMS. When approaching shoring system to attach hooks, to enter the trench/excavation, pour or strip a manhole, the following can be applied: Backfill between the shoring system and trench wall to at least 1m below ground level. Walkways, ramps, or bridges with standard guardrails could be provided. The crossing structure will be made of tightly secured and uniformly sized planking or other material. Alternatively, trenches can be battered back to allow for a bench for personnel to work safely.
4.0 General 4.1 All shoring systems shall be certified. 4.2 4.3 4.4
Exclusion zones shall be set up at areas where excavation work activities are conducted. Clear signs and barriers must be installed to ensure that only trained / competent workers are allowed into the work area. Where excavators and trucks are required in proximity to edges of excavations / trenches and
Page 3 of 4 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Related Information
Permit to excavate
Suppliers / Resources
Page 4 of 4
Revision No 2
Effective measures must be taken to prevent cranes coming into contact with power lines, other cranes or structures. All crane erection, climbing and dismantling operations must follow the requirements of the Global Safety Alert on Crane Erection, Climbing and Dismantling. All lifting equipment must be fit for purpose, marked with a means of identification and safe working load. All lifting equipment must be examined before first use, regularly inspected, and certificated at least annually as safe to use by a competent person, including cranes, hoists, chains, hooks, slings, etc. Rubbish removal skips must be structurally sound and designed for lifting (with lifting points and SWL), must not be filled above their top edge and should be covered to prevent debris falling out while they are being lifted.
Standard:
Page 1 of 12
Revision No 2
Cranes and other lifting equipment must only be used within their safe operating limits (e.g. loadings and weather conditions).
Page 2 of 12
Revision No 2
Page 3 of 12
Revision No 2
Earth moving equipment where used as a crane (i.e a freely suspended load) must have Burst protection (also known as Anti-Drop V fitted to the boom and dipper arm.
Page 4 of 12
How to Comply with the Standard: GMR 4.1 Cranes and Lifting Equipment 1 2 3 4 5 All lifting equipment has been placed on a plant register and certified by a competent person. Permit to erect or climb a tower crane has been completed where relevant. Slings and lifting equipment are suitably tagged and tested. Mobile equipment is only operated when stabilised within manufacturers specifications. Working from a crane box is a last resort and Operations Manager or EHS Manager approval is required. Check
1.0 Definitions 1.1 Competency The specific knowledge, skills and behaviours and the application of that knowledge, skill and behaviour to the standards of performance required in the workplace, as expressed in the relevant endorsed industry/enterprise competency standards or the learning outcomes of an accredited course. People can be deemed competent against the defined standards by the processes of either Competency Based Assessment or Training. Where no certification, qualification or endorsed competency standards exist, verification of the assessment of a persons skills and competency for the plant and equipment will need to be provided by the employer. 1.2 Major Plant: includes mobile and static cranes, load shifting equipment, elevated work platforms and any associated machinery, equipment (including scaffolding) appliance, implemented or tool and or component or fittings or accessories to them. Qualified Person: a person who is the holder of a qualification ie Plant Mechanic, Plant Engineer, Motor Trades Person, Fitter Trades person etc to undertake the prescribed maintenance and service work on the plant and equipment . 3rd Party Inspector: Structural Engineer with 12 months experience in the design and inspection of tower cranes. Competent Person: a person who is the holder of a certificate of competency in the operation of the plant or equipment. Where no certification, qualification or endorsed competency standards exist, verification of the assessment of a persons skills and competency for the plant and equipment will need to be provided by the employer.
1.3
1.4 1.5
2.0 General 2.1 The use of all plant and equipment on the project shall be included in the Impacts and Hazards Risk Assessment to ensure all EH&S aspects are assessed to control and minimise hazards onsite. The assessment should include (but limited to):
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 5 of 12
2.5
2.6
2.7
2.9
2.10 A Lifting Plan (including but not limited to assessment of impacts and risks, exclusion zones, lifting radius, permits) will be developed for loads over 20t or of a high risk nature (ie multi-crane lifts). 2.11 All loads shall be slung and directed to good industry practice. Loads should not be cradled and waste bins shall be slung using a minimum of 4 lifting points. 2.12 Load lifting shall be limited to one slung load unless undertaken as part of a rigging erection sequence or an assessment of impacts and hazards are undertaken to reduce the risks of injury to those undertaking the operation. 2.13 Plant and equipment inspections should be carried out to a scheduled Inspection Test Plan with all plant and equipment operated on site entered in a site plant register. These BLL documents should be used where BLL hire plant and equipment for use on site or where the subcontractors do not have suitable documentation. The choice of documentation should be selected following a detailed assessment impacts and risks. Further examples of Inspection documentation can be also found relevant Australian Standards and/or in the Subby Pack. 2.14 NOTE: Any person slinging materials or equipment for lifting by mechanical means will be a qualified dogman. 3.0 Tower Cranes 3.1 All cranes must be thoroughly inspected by an independent, certified 3rd Party Inspector before use, after any significant alteration and at regular intervals (at least every 12 months) in compliance with manufacturers and legal requirements. Cranes with key parts (cab, slewing ring, and winch) that are more than ten years old must be subject to 3rd party inspections) every 12 months (immediate 3rd party inspections are required for such cranes in current use, unless they have had such inspection within the last six months). All 3rd party visual inspections should be inclusive of both the crane as assembled and the integrity of the cranes parts (weld integrity, section and bolt compatibility, cable soundness, pulleys, controls, etc). Where any potential serious defect is noted during visual inspections, the crane must be taken out of service and a full examination of the part(s) must be conducted (eg using Non Destructive
Page 6 of 12 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
3.3
3.4
3.5
3.6
3.7
3.8
4.10 Monthly documented inspections of all lifting gear that accompanies the crane to be undertaken by a competent person and listed on a Lifting Gear Register and accompany the crane. 4.11 Cranes to be operated only by the appropriately certified personnel. Dogman to also be appropriately certified. 4.12 Suspended slabs will need to be verified and signed off by the appropriately qualified person i.e. Structural Engineer and similarly certain ground conditions may need verification of the maximum allowable ground bearing pressure by a Geotechnical Engineer prior to starting. 4.13 The following manuals are to be supplied with the crane: The operators manual Service records (logbook) 5.0 Telehandlers, Forklifts and Electric Pallet Jacks with Crane Jibs / attachments 5.1 Crane jibs & attachments can alter the dynamic and operating characteristics of telehandlers, forklifts and electric pallet jacks. When fitted, it may be necessary to down rate the machines rated lifting capacity, therefore advice and information must be sought from both manufactures of machine and attachment and written confirmation supplied stating that machine and jib /attachment are compatible. Where this is not possible, then a suitably qualified engineer should be consulted and the compatibility determined and relevant documentation submitted. The following must also be undertaken: Separate rated capacity charts / data plate shall be provided for each attachment and be displayed in a prominent position where the operator can see it All lifting gear to have annual 3rd party inspections undertaken by a NATA registered organisation and be available. Monthly documented inspections of all lifting gear that accompanies the machine to be undertaken by a competent person and listed on a Lifting Gear Register. All removable attachments shall be marked permanently and legibly with the following minimum information: a. Name of the attachment manufacturer or authorised importer b. Model or type c. Serial number and year of manufacture
GMR 4.1 Cranes & Lifting Equipment Page 8 of 12 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
5.5
6.0 Earth moving equipment used as a crane: 6.1 Where earth moving equipment is to be utilised as a crane, the following should be considered: 6.2 Any person slinging a load shall be a qualified dogman. Loads less than 3t can be slung by a competent person and the use of excavator is appropriate. Loads over 3t must be slung by dogmen and the use of excavator must be ascertained by risk assessment.
The SWL shall be clearly marked legibly and indelibly on the dipper arm. All loads greater than 3t should be managed by dogger and Major Plant should be used for the intended purpose, where the plant is proposed to be used for other purposes ie load shifting equipment used as a crane then this shall be undertaken insert darren Where it is impractical to use the appropriate plant, a full assessment of impacts and risks of the operations is undertaken Loads shall not be suspended from bucket teeth or adaptors The lifting point shall form a closed eye and be arranged that accidental unhooking of a load cannot occur. The earth moving equipment shall be travelled only with arm and boom retracted to the minimum practicable radius. Where a quickhitch is fitted, loads shall only be suspended from the manufacturers designated lifting point on the quick hitch unless a designated lifting attachment is used. Host machine load rating charts shall allow for the additional mass of the quickhitch Earth moving equipment where used as a crane (i.e a freely suspended load) must have Burst protection (also known as Anti-Drop Valves) fitted to the boom and dipper arm.
7.0 Quickhitches Refer to GMR 2.7 8.0 Lifting equipment 8.1 Rubbish/material bins, Lifting cages, pipe boxes, duct cradles, man boxes first aid cages, kibbles etc to be engineer designed and certified by a Structural Engineer and inspected monthly by a competent person and documented. All items shall be marked legibly and indelibly with the following information:
Page 9 of 12
Revision No 2
9.0 Duct hoist / Lifters 9.1 All Duct hoists must incorporate safety gear so that they are fail safe in the event of a sudden failure of the hoisting rope under load. Outriggers should also be attached and form part of the hoist to provide increased stability, where fitted. The following must also be undertaken: Each hoist is to have identification number and SWL shall both be marked legibly and indelibly. A visual inspection of the entire length of the hoisting rope is to be undertaken by a competent person as part of a general weekly inspection. Duct hoists to be listed on Lifting gear registers Only proprietary fork extensions / attachments are to be used and only then in strict accordance with the manufactures instructions.
10.0 Chain, Wire & Electric Winches 10.1 Some intended anchorage points may need to be verified and signed off by an appropriately qualified person i.e. Structural Engineer prior to use. Evidence to be provided by Employer that persons using winches are appropriately trained. Each chain hoist shall be permanently and legibly marked with the following information: Model type identification. Serial or batch number. Details of load chain as follows. Nominal size. Grade (quality). Rated capacity hoisting. Name or identification mark of the manufacturer of the chain hoist.
10.2 Wire and Electric winches shall have motion limits Model type identification. Serial number. Details of load chain as follows. Nominal size. Grade (quality). Classification of mechanism of the chain hoist. Rated capacity hoisting. Name or identification mark of the manufacturer of the chain hoist. Power requirements.
11.0 Access to flat beds and Delivery Vehicles 11.1 Access to flat beds, semis and delivery vehicles must only be via a safe stair or ladder access system. Personnel slinging / un-slinging etc or accessing these areas must be protected from falling off the load / back of the truck at all times.
GMR 4.1 Cranes & Lifting Equipment Page 10 of 12 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
The operator of the plant or equipment shall be sufficiently trained to be able to operate it competently and safely Where required by legislation, the operator shall hold an appropriate certificate of competency. Where no certification is required by legislation, the subcontractor must supply training records which identify the specific type of plant and equipment the person has been trained in (e.g. sheepsfoot roller, x brand semi-automatic quickhitch).
As the BLL Project team member designated responsible for the Management of EHS, the Site Manager (or their delegate, e.g. Area Foreman) will verify the above documentation has been received, and confirm the general condition and type of plant and equipment by a visual inspection, prior to the equipment being used on site. The BLL Site Manager (or delegate) is to ensure that the plant and equipment is listed on the BLL Plant and Equipment Register. 12.3 Ongoing use and maintenance of plant and equipment on site The Operator or Competent person shall undertake daily documented inspections of the plant using a logbook or checklist which is relevant to the type of plant and equipment and the installed safety devices (i.e. dont use a checklist designed to check a piling rig for a crawler crane, ensure specific safety alarms and limit devices, where installed, are inspected and tested daily) Where the same items of plant and equipment are used for different shifts, each shift Operator must conduct a documented inspection, as above (a separate second logbook/checklist may be required, or subsequent Operators need to countersign the first daily logbook/checklist entry). The subcontractor/owner of the plant and equipment should provide evidence of the manufacturers specifications detailing the ongoing service requirements (i.e. monthly, 200hrs-250hrs, yearly, 10 yearly etc.). Where no manufacturers specifications are received, BLL will request evidence of service on a monthly basis, unless another timeframe is specified by legislation or standards. (Use current BLL Plant and Equipment ITP as a guide to determine these other timeframes). All subcontractors to supply BLL monthly with evidence verifying that the plant and equipment on site has been maintained and serviced to the manufacturers specifications by a QUALIFIED person (i.e.
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 11 of 12
13.0 Concrete Pumps 13.1 The siting of the pump is to be reviewed in consultation with the pump operator for suitability and any potential hazards/ risks that may exist prior to pumping operations beginning. Outriggers / stabilisers shall be fully extended unless the manufacturer specifies otherwise. Suspended slabs will need to be verified and signed off by an appropriately qualified person i.e Structural Engineer and similarly certain ground conditions may need verification of the maximum allowable ground bearing pressure by a Geotechnical Engineer. 13.2 All pump operators to be experienced and Boom pump operators to be holders of the National Certificate of Competency PB. Refer section 2.5 of the Means and Methods. A Certificate of Registration from a Statutory Authority is required for truck mounted concrete placing booms. Daily operators logbook to is to be completed prior to commencement of pours. 13.3 Concrete pour rates are to be taken into consideration when pouring vertical elements such as Jump/Slip forms, shear walls, columns etc with engineers advice being sought prior to pouring. 13.4 A concrete placing boom shall not to be used as a hoisting crane (e.g. picking up helicopters, extra lengths of rubber hose etc) and all warning and safety decals/stickers are to be in good order and legible. 13.5 Pipes and other equipment should be tested inline with the manufacturers recommendations and/or a minimum of monthly. Ultrasonic testing may not be suitable for twin wall pipes. Other suitable testing methods should be adopted such as the use of thickness testing callipers, increased inspection and increased monitoring of use, in terms of volume and type of concrete pumped. Piping which has a wall thickness, less than the manufacturers specified thickness for the pumping design pressure shall not be used. Rubber delivery hoses and tail end fittings are to be inspected for suitability for continued service at frequent intervals, based on the severity of use of the equipment. Rubber delivery hose should not to be kinked. 13.6 Each individual pipe section, bend, reducer is to be indelibly and legibly marked (e.g. numbered) so it can be readily identified against the record of test results in the logbook. Related Information Suppliers / Resources Test Plan Site Plant Register Global Alert on Crane erection and dismantling
Page 12 of 12
Revision No 2
Adequate numbers of competent operatives (riggers/slingers) must be provided to safely plan and conduct all lifting operations. All crane operators and slingers must provide proof of competence.
Standard:
All loads must be safely slung by a competent person, within safe working limits of the lifting equipment, using hooks with safety catches, netting loose loads and attaching tie lines. Daily lifting coordination meetings must be held where more than one crane is in use. Means and Methods: How to Comply with the Standard:
GMR 4.2 Competent Persons 1 2 3 4 All legislative and BLL minimum induction and training requirements will be met. All certificates and licenses have been checked and copies taken or verified. Lifting schedules are prepared and lifts over 20t have a safety review. All high risk activities have specific lifting plan.
Check
1.0 Definitions 1.1 Competency The specific knowledge, skills and behaviours and the application of that knowledge, skill and behaviour to the standards of performance required in the workplace, as expressed in the relevant endorsed industry/enterprise competency standards or the learning outcomes of an accredited course. People can be deemed competent against the defined standards by the processes of either Competency Based Assessment or Training. Where no certification, qualification or endorsed competency standards exist, verification of the assessment of a persons skills and competency for the plant and equipment will need to be provided by the employer. 1.2 Qualified Person: a person who is the holder of a qualification ie Plant Mechanic, Plant Engineer, Motor Trades Person, Fitter Trades person etc to undertake the prescribed maintenance and service work on the plant and equipment . 3rd Party Inspector: Structural Engineer with 12 months experience in the design and inspection of tower cranes. Competent Person: a person who is the holder of a certificate of competency in the operation of the plant or equipment, or an endorsed national competency standard (e.g. first aid, scaffolding, rigging etc).
1.3 1.4
2.0 Minimum Induction Training requirements 2.1 BLL are responsible to:
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 1 of 5
Clear communications must be provided and maintained between crane operators and signallers.
2.2
Construction Industry General Induction Training All people responsible for construction work and all people carrying out construction work should hold the current Construction Industry General Induction Training certification. The following table provides further guidance on who should hold an industry induction card, and who is excluded from the requirements as per the draft National Code of Practice for Induction Training for Construction Work. INDUSTRY INDUCTION TRAINING REQUIRED Construction Workers employees, labour hire, self employed, work experience students, concrete placement and/or laying activities, operation of concrete pump. Construction supervisors foremen, engineers, leading hands, superintendents Professional BLL staff (project managers, site managers, construction managers, EHS coordinators or managers, Ops managers), and professional consultants/contractors (eg architects, designers, surveyors, preparatory works engineers) who spend time on a site unaccompanied and who are responsible for elements of construction eg inspections, audits, which require direct and active interaction with the construction process Cleaners who work on construction sites Fit out, shopfitting, carpetlaying, curtain and blind installation etc Delivery work involving the movement of mobile plant on site (other than delivery vehicles), drop off and assemble/install INDUSTRY INDUCTION TRAINING NOT REQUIRED Visitors, couriers, student/careers/community groups observing work, food van employees under escort of supervision (must be accompanied at all times) Government inspectors (WorkCover, Local Government/Council), emergency personnel, or people authorised under right of entry legislation BLL staff and consultants, contractors (eg interior designers, trainers, estimators) observing but not carrying out construction work (must be accompanied at all times)
People undertaking minor maintenance in existing buildings where there is no construction work being undertaken. Off site manufacturing Delivery work involving only drop off or pick up to designated area.
Page 2 of 5
Revision No 2
3.0 Crane Operators qualifications & experience 3.1 All crane operators are required to prove their qualification by producing a valid certificate of competency which covers the size and type of crane that they intend to operate on site. Operators must be trained and inducted into the particular type of crane they operate. All doggers / slingers are required to prove their qualification by producing a valid industry ticket.
3.2
4.0 Lifting co-ordination 4.1 4.2 Daily co-ordination of lifting to occur. Details of lifting operations and areas to be closed to general access, are to be adequately communicated with appropriate lead times to assist any required procedure adjustment of near proximity work All BLL sites shall nominate a Lifting Supervisor whom will be responsible for ensuring all lifting activities are carried out as per the agreed and approved plan
4.3
5.0 Codes for National Certificates of Competency: Scaffolding, Dogging, Rigging SB Basic scaffolding SI Intermediate scaffolding SA Advanced scaffolding DG Dogging RB Basic rigging RI Intermediate rigging RA Advanced rigging Load Shifting TO Turbine operation ES Reciprocating steam engine operation Crane and Hoist CT Tower cranes CP Portal boom cranes CV Vehicle loading cranes CD Derrick cranes CB Bridge and gantry cranes CN Non-slewing mobile cranes (telehandler over than 3 tonnes)
LF Forklift truck (also used to evidence competency CS Self-erecting tower cranes for use of telehandler under 3 tonne, along with confirmation of training in the type of telehandler)
Page 3 of 5
Revision No 2
LD Dragline Pressure Equipment BB Basic boiler operation BI Intermediate boiler operation BA Advanced boiler operation 6.0 Prior to plant and equipment arriving/used on site 6.1
Subcontractor and /or supplier to provide documentation to certify the compliance of the plant and equipment to relevant Standards, Legislation and/or Manufacturers specifications and safe to use. This certification to be carried out by a Qualified person such as a plant mechanic, fitter, mechanical engineer, motor trades person. In some instances an item of plant and equipment may require a number of certifications by different Qualified persons (e.g. a crane or hoist may require Plant mechanic, Electrician and Rigger to certify different components or specific configurations to be used) Where the plant or equipment has a number of attachments, these must also be inspected and certified as fit for use in conjunction with the main item of plant or equipment by a Qualified person to the Manufacturers specifications (e.g. rock saw, quick hitch, rock breaker)
6.2
The operator of the plant or equipment shall be sufficiently trained to be able to operate it competently and safely Where required by legislation, the operator shall hold an appropriate certificate of competency. Where no certification is required by legislation, the subcontractor must supply training records which identify the specific type of plant and equipment the person has been trained in (e.g. sheepsfoot roller, x brand semi-automatic quickhitch).
6.3
As the BLL Project team member designated responsible for the Management of EHS, the Site Manager (or their delegate, e.g. Area Foreman) will verify the above documentation has been received, and confirm the general condition and type of plant and equipment by a visual inspection, prior to the equipment being used on site. The BLL Site Manager (or delegate) is to ensure that the plant and equipment is listed on the BLL Plant and Equipment Register.
6.4
Page 4 of 5
Revision No 2
7.2
7.3
7.4
7.5
Page 5 of 5
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
1 Temporary Supply Electrical supply panels must be sufficient in number, inspected before use by a competent person, located in close proximity to work areas to minimise trailing cables and secured to prevent unauthorised access. All electrical circuits must be protected by an ELCB or RCD, fitted at source and regularly checked. All electrical cables, cords, plugs and sockets used on projects must be suitable for construction use, in good condition and regularly inspected. Supply boards, cables and cords must be safe by design, and located or protected so as to avoid physical damage by vehicles, water, etc. (e.g. by elevation or armour).
Standard:
Leads kept off the ground at all times Lead stands fixed to Reo
Highlighting under ground cables or cables behind or in immediate vicinity conduits in walls.
Page 1 of 6
Revision No 2
Facility provided to add on SPDB without working live by isolating the junction box
Example of SPDB
Page 2 of 6
Revision No 2
Page 3 of 6
Revision No 2
Definitions Main Switchboard (MSB). Usually only 1 per site but could be more on larger projects. Main Distribution Board (MDB). Usually one per area. Site power distribution board (SPDB). The switchboard used for feeding plug in type equipment. 1.1 Electrical site temporary supplies will be protected by ELCB / RCD that is tested every 1 month minimum. 1.2 All Main Distribution Boards (MDB) and Main switch boards (MSB) will be kept locked and access to boards unobstructed, clear and dry (consider gravel in front with free drainage). 1.3 Site Power Distribution boards (SPDB) will be provided in sufficient quantities so that power leads run from them will be max 35m. (1.5mm2). 1.4 DBs will be tested and tagged by a licensed electrician (A Grade) monthly as a minimum. Injection testing will record Milli. seconds. 1.5 SPDBs will have a lockable cover and will have cable access that allows door to be closed and no damage to cables (ie: through base). Note: live boards will always have access to main switch. 1.6 SPDBs will have signage and will as a minimum have: - Site electrical contact (name and mobile number) - Plus statutory signage. 1.7 Water coolers not to be located near SPDBs where possible. If no other suitable location is available then ensure adequate drainage is in place to ensure no water near board. 1.8 Temporary site power switch boards require: 1.8.1 1.8.2 1.8.3 1.8.4 1.8.5 Cable entry management (holes in base of DB) Lockable cover Signage noting electrician contact details Locked RCD cover (to prevent re-set of RCD and circuit breakers by unauthorised personnel Dry access around it
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 4 of 6
Page 5 of 6
Revision No 2
150
150
6.0 Underground Temporary Power 6.1 All underground cabling shall be minimum depth of 600mm, laid with warning tape place 300mm above conduit.
Related Information
Suppliers / Resources
AS 3012 Temporary Electrical
Page 6 of 6
Revision No 2
Standard:
Lock Out - Tag Out (LOTO) and a Permit to Work system must be used to ensure energised systems are locked off and de-energised before work is conducted upon them.
Locking Device used to lock individual circuit to prevent operation of the MCCB (without ram) in OFF condition
Multi lock out devices should be used for circuits supplying power to another electrical contractor eg: mechanical / sprinkler / lift etc.
NOTE: ALL TESTING EQUIPMENT MUST BE PROVEN ON A KNOWN LIVE SOURCE BEFORE AND AFTER TESTING.
Good practice reminder tag on testing equipment Lock out tags must be used when isolated
Page 1 of 10
Revision No 2
MAC signage
2 3
Page 2 of 10
Revision No 2
1.1 Introduction This requirement has been developed to assist BLL in managing electrical hazards associated to works within any building which is not being powered entirely by Temporary Construction Power. Project budgets and contractual requirements for contractors need to consider this requirement. Electrical work is covered by a range of Federal/State/Territory Legislation and A/NZ Standards, Codes of Practice and Guides some of which are referenced at the end of this document. In some instances the legislation or Codes may require more than this requirement. Before Projects develop and agree final Safe Work Method Statements for the safe work procedures for working in the vicinity of electrical services the relevant documents and persons (electricians, supervision, etc) undertaking the work should be consulted 1.2 Working around live special considerations : MAC - Major Area of Concern Working in an area where the possibility exists of coming into contact with the live site wiring. Areas which fall in this category include but are not limited to the following: Working in ceiling spaces. Working within or the penetration of masonry or stud walls or concrete columns. Penetrating concrete slabs Working within risers, switch room or enclosed areas
The major areas of concern shall be known as a MAC The following actions are to be conducted where working in a MAC area. 1.3 ENSURE NO LIVE ELECTRICAL WORK SHALL BE CARRIED OUT 1. All electric shocks and near misses (regardless of how minor the incident) must be reported to your Operations and EH&S Managers immediately after the effected person has been attended to and the area made safe. Do not move anything or clean the immediate area (unless a safety issue exists) until the EH&S/Operations Manager or his representative has personally inspected the area. 2. BLL are to identify MAC zones and define and mark up such areas on staging drawings and locate adjacent to each entry to the MAC area and add to the BLL Impact and Hazard Risk Assessment. 3. All contractors engaged to perform work on a BLL work site shall be notified by BLL of nominated MAC areas. Identified MAC areas may change during the course of the construction and as such, the BLL nominated areas shall be used as a guide only. It is the responsibility of the contractor to identify all MACs applicable to their trade. 4. BLL shall engage a nominated electrical contractor to carry out the following works within each MAC area: Isolate live cables where possible, within the MAC area Where possible connect live cables within a MAC to earth leakage protection. Identify and label and protect where possible all live cables that remain within the MAC area
Page 3 of 10 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Due to the possibility of error and time delays between the initial inspections and the commencement of the works, it is not possible to guarantee that all live cables are identified with each MAC at the time the actual work is carried out. 5. BLL shall ensure that all contractors have their MAC SWMS hold points certified by both BLL and the nominated site electrical contractor, clearing the MAC of hazards BEFORE work commences. 6. BLL sites are to include within their tool box talks for communication and consultation purposes, the topics Working Safely within Major Areas of Concern and Working with cables in a MAC and that All involved must always assume the cables remain a hazard The content of this training/consultation shall be forward to BLL for comment. 7. All contractors shall produce SWMS for each MAC area, identifying the risks, hold points, testing procedures and identify methods of eliminating / reducing the risks etc. 8. All contractors forward appropriate documentation to BLL detailing training, SWMS, tool box talks specifically associated with working within a MAC area. 9. Contractors site employees shall be spot checked to ensure that they are aware of their companies MAC SWMS and they fully understand and follow the requirements of the document. Note: SWMS & procedures MUST be held by all electricians working in MAC area. 10. All contractors site employees shall be issued with PPE (as determined by that companies SWMS) and shall wear such PPE whilst working in a MAC. (over and above BLL site PPE requirements). 11. Drilling & cutting. Any works requiring drilling or cutting into areas, materials or structures that MAY contain live electrical shall be thoroughly investigated prior to works. An electrician is required to sign off prior to drilling / cutting within 1 m of any alignment of a GPO or electrical fitting, light switch. 2.0 PROCEDURE FOR TRANSITION FROM TEMPORARY TO PERMANENT POWER 2.1 PRIOR TO ENERGISING
a. The area and /or service to be energized will be confirmed with the BLL Supervisor responsible for the area or service. The energisation procedure will be reviewed by an independent third party or peer review. b. Area to be checked, tested and commissioned in accordance with the electrical contractors agreed testing and energisation procedure. Ensure all cables and equipment are terminated. Record all details of tests. c. Site safety committee is to be made aware of the area proposed for energisation.
d. Site personnel, including supervisors to be made aware of the area proposed for energisation. Place signage in areas agreed.
Page 4 of 10
Revision No 2
g. A completed Certificate of Energisation and/or Energising Procedure Notification, must be submitted to BLL before energisation. h. A marked up plan shall be displayed clearly showing energised areas. The plan is to be colour coded and must be displayed in the areas agreed. These areas may include: i. Adjacent to Alimaks at amenities levels. ii. Site notice board in the amenities area iii. Site safety-meeting minutes iv. Others as determined by the on site staff. i. All areas, switchboards and / or large items or electrical equipment, once energised, shall have prominent warning signs attached. All warnings signs to be professionally printed / sign written, and large enough to be clearly visible fro a distance of 3 meters, computer generated sheets to be laminated. Generally areas / items to be completed prior to energisation. Where this is not possible / practical, ensure that: i. Incomplete circuits are not terminated at the switchboard (active and neutral). ii. Junction boxes are fixed at unterminated cable ends, with any cabling mechanically protects. iii. Where possible switchboards will only be energised when all circuits are completed and terminate. k. l. Temporary power switchboards shall remain energised for as long as practical. Temporary cabling. Ensure all temporary cabling in areas to be energised has been removed, or where this is not possible, cables terminated in accordance with codes and standards. (so as to avoid having to access temporary cables through permanent energised cables)
j.
m. The area/ service shall be immediately re-checked by the licensed electrician responsible, prior to other trades persons entering the area (in accordance with electrical contractors agreed energisation procedure). n. When switchboards are energised, all protective devices are to be switched off, so that circuits can be energised and checked one at a time. o. Following live testing, areas shall not be left energised if not required. p. Where possible, switchboards (permanent) are to be kept locked. All switchboards to have a label attached stating the following:
Page 5 of 10
Revision No 2
s.
NOTE: after energisation and temporary construction power is removed and tradesmen are using house power therefore portable ELCB units must be used and signage provided to note that power is on.
3.0 ISOLATION, LOCK OFF PROCEDURE 3.1 3.2 Always test prior to touching (THIS IS MANDATORY). The circuitry labelling MAY BE WRONG so dont take the chance. The electrical equipment applicable to this procedure must be isolated from supply by either opening switches, switching off circuit breakers (and rack out if possible), or removing fuses. Following isolation, the circuit isolating device shall be secured in the open position and locked out where possible. Alternatively isolation may consist of disconnection and removal of the cabling from the control device. Where this system of isolation is adopted all active plus neutral and earth conductors forming the circuit must be removed. The isolating device must then have a tag attached in accordance with the Tag procedure. Test using proven equipment which has been tested immediately prior. Volt sticks or similar are not an acceptable testing device to confirm that power is OFF, these can only be used to confirm power is ON.
3.3
4.0 TAGGING PROCEDURE 4.1 4.2 4.3 Tag shall be of professional manufacture with reinforced eyelets. Tags to be attached with non conductive ties or fasteners / and be individually numbered. This procedure shall be utilised in any situation where work is to take place on or near to energised circuits and / or equipment, and in particular whilst being repaired, modified, tested and commissioned. Where practical warning tags shall be placed at all points of the switching, isolation or disconnection. No device shall be operated whilst a lock or tag is attached.
Page 6 of 10
Revision No 2
5.0 NO LIVE WORK POLICY 5.1 Bovis Lend Lease have a no Live Work Policy. No person shall undertake a task or carry out work on or in the immediate vicinity of energised bare (i.e. not insulated) live conductors unless approval from regional EHS manager. The following steps should be considered in the first instance: a) Can energised equipment be safely isolated b) If a. above cannot be achieved, can the work be rescheduled to a time at which the equipment may be isolated. 5.2 WORKING ON OR IN THE VICINITY OF BARE ENERGISED CABLING CONDUCTORS OR EQUIPMENT INCLUDING SWITCHBOARDS ITEMS TO BE CONSIDERED AS PART OF A SWMS.Works may only proceed on or in the immediate vicinity of an energised source after the following steps have been taken. To carry out works in this manner shall always be as a last resort and after complying with the following procedure: a) A comprehensive SWMS shall be prepared and submitted to the Bovis Lend Lease regional EH&S manager for approval. Work shall not proceed until a written approval has been obtained. This approval may take up to 7 working days. b) All persons who may be involved in the works shall have input into the above S WMS, and shall ensure that the procedures adopted shall not compromise the safety of themselves or their fellow workers. c) The attached sheet titles working on or in the vicinity of energised cabling or equipment including switchboards, shall be used as a guide in preparing the above SWMS. d) A letter from the client noting that power can not be isolated. 5.3 a) Form of segregation of Switchboard. Which compartments are energised? b) Fault Level / Protection. The higher the fault level the greater the danger
Page 7 of 10
Revision No 2
k) Type and calibration of testing instruments and proof of satisfactory operation m) Barriers, Signage etc. to keep area isolated. Must not impair speedy egress if reqd n) If power to area isolated, auxiliary power must be available for tools and lighting, etc. o) Number, qualification and experience of tradespersons undertaking the task. A minimum of 2 no. tradespersons must be present, one of whom must hold a current first aid certificate. (level 2) . The first aid person must not be performing the work. p) A plan must be in place for removal or a person from an energised source. Use a non conductive material without skin contact.(i.e. live rescue kit) q) Use of correct tools. If insulated in good condition. No shifting spanners etc. r) t) Safety equipment including fire extinguisher etc. adjacent. No metallic or conductive jewellery to be worn. Glasses may require securing. s) Area clean at all times, No rubbish, equipment or trip hazards to delay safe exit. u) Lock out or secure remote supplies. May include aux. Generators UPSs or auto change over systems. v) Address vacuuming, cleaning and testing at completion. Document QA checks including visual, insulation, phase rotation etc. and record results. w) Consider company Energisation, Tag and Lock out Procedures associated with the works x) All work to be carried out in a manner which minimised risks, and which ensures no danger to persons performing the work y) All persons engaged in the works must be inducted into the procedures relating to the safe implementation of works. All tradespersons must sign off the SWMS . It should then be displayed at the entry to the area where the work is to take place, in a position where it can easily be referenced as work proceeds. At a determined point during the works the SWMS should be reviewed and any changes required must be documents and tradespersons re-inducted.
6.0 WORK IN CEILING OR WALL CAVITIES (EXISTING OR PRE EXISTING) 6.1 6.2 6.3 6.4 Remove enough ceiling or wall sheeting or tiles to expose and gain entry to the ceiling or wall space. Two (minimum) qualified, competent and experienced tradespersons to be involved in this procedure. Isolate all cabling at their known source of supply. (see tag / lock off procedure). Test all cabling to ensure isolation. Particular attention required to: a) Rogue cabling. (ie Energised from another source.)
Physical GMR 5.2 Work on Live Systems Page 8 of 10 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
6.5
Highlight cabling which remains energised f) ATM including associating security lights
6.6 6.7
Ensure prior to other trades carrying out ceiling works, the designated work area is thoroughly rechecked. Relocate or secure all cabling (where possible) clear of work area. Persons carrying out ceiling works to have SWMSs Identify risks, complete with management of these risks, Mechanical protection may be required adjacent to cabling and no any sharp or protruding materials for additional protection. This particularly apply to : j) l) Sprinkler pipes Air conditioning ducts
k) Hydraulic, Gas refrigeration or other metallic pipes m) Metal plaster support channels. Hot works in the immediate vicinity would require more specific consideration. 6.8 Penetrations through floor slabs. Prior to drilling / coring all efforts should be made to determine the location of any cabling run within, or directly under the floor slab. This may include: n) Check as installed drawings, if available o) Use of cable detector. (not generally recommended if steel present) q) Check from within the ceiling of the floor below the existence of cabling secured to the underside of the slab. 7.0 ENERGISATION PROCEDURE 7.1 Prior to energising carry out all tests as required by AS3000 and AS3017. Also ensure all QA sheets applicable to the area have been completed. Appropriate PPE equipment must be worn or available as requires. Atleast 2 no. (min) appropriately licensed persons to be involved in the testing and subsequent energisation. At least one of these persons must have a current level 2 first aid certificate. This person must not be involved in any aspects of the commissioning which could result in contact with an energised source. Means of communication must be immediately available to ensure contact with medical or other assistance as required. A list of contact phone numbers must be on hand for use in emergency situations. Proven (immediately prior on a known source), currently calibrated meters and
Page 9 of 10 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
p) Check slab at switchboard locations to determine if conduits and / or cables enter / exit the slab.
7.3
7.4
7.5
7.6
7.7
7.8 7.9
7.10 Ensure all equipment room, including switch room, doors are kept locked and appropriate signage installed. A key availability procedure to be agreed and controls put in place. 7.11 All trades persons involved with the testing and or energisation procedure must be inducted into these procedures prior to commencement of these works.
Related Information
Suppliers / Resources
Page 10 of 10
Revision No 2
Standard:
All electrical tools and equipment operating off the site supply must be regularly inspected (monthly), tested and marked as safe to use.
Lockable cover over RCDs and circuit breakers with access hole in cover to operate main isolator. DIN 10 amp outlet for RCD testing of lighting circuits.
General
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 1 of 2
Adequate facilities for charging cordless tools must be provided. Battery charges not to be left on boards.
Locks to prevent unauthorised access shall restrict access to electrical circuit breakers and RCDs. Isolating switches are to be accessible and clearly marked to assist in emergency isolation. Lighting circuits shall be separated from power circuits and lighting circuits shall not be used to operate power tools. Where power for construction works is being undertaken and the power source is from a permanent distribution board or supply then portable RCD protection must be used. People shall be trained in the use of power tools particularly grinders and percussion equipment. Tools or lead found faulty shall be removed from duty immediately. All Live boards and equipment will be appropriately marked as live with signage.
Testing & Tagging All electrical equipment introduced to the site must carry a non transferable label stating date of last inspection. Where no licensed electrician is available on site then electrical equipment shall be removed from site or isolated until inspected. Testing and tagging of leads and equipment in site offices and amenities will be a minimum of every 3months (except for RCDs which require testing monthly.) Recording of milliseconds should be provided for all RCD items recorded in logbook. A licensed electrician must check all electrical equipment monthly and such inspection shall be recorded in a register of electrical test. Circuits feeding GPOs at swing stage platforms require an RCD test from the platforms taking into account the earth impedance of the total cable length from the SPDB. To facilitate testing of outlets, large items of equipment / fridges etc should not be placed in front of outlets (beside or below instead).
Related Information
Suppliers / Resources
Page 2 of 2
Revision No 2
Standard:
The levels of Illumination need to match the demands of the job and the location. Lighting Installations should avoid the risks of electric shock, burns, and glare. All lighting systems must have an emergency back-up system to ensure sufficient lighting is available to permit escape in emergency situations.
Stair lighting where fixings to finished elements precluded overhead temporary lighting. Light suspended vertically by a catenary wire from slab edge
Guards to lighting
Page 1 of 3
Revision No 2
Page 2 of 3
Revision No 2
Related Information
Suppliers / Resources
Page 3 of 3
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
1 Occupational Health Areas and activities involving harmful levels of chemicals, dust, fumes, noise and vibration levels should be identified and levels reduced where practical by elimination, substitution, attenuation or isolation and personal protection. The risks associated with the use of chemicals and hazardous substances must be assessed by reference to Materials Safety Data Sheets. The safest effective methods should be selected and appropriate protective equipment provided as necessary, e.g. respirators and chemical-resistant clothing. Areas and activities producing noise levels above 80 db(A) should have noise warning signs posted, stating that hearing protection should be worn. Appropriate hearing protection must be provided to, and worn by, all those at risk of sustaining damage to their hearing. Manual lifting tasks must be assessed, weights known before being undertaken and appropriate equipment used to handle heavy/awkward loads. Workers must be instructed and follow safe manual lifting methods, including stretch and flex, bent knees/ straight back, etc.
Standard:
Page 1 of 8
Revision No 2
Medical equipment and trained personnel should be available for providing first aid treatment to injuries and providing advice on health and wellbeing.
Manual Handling accounts for a high percentage of our lost time injuries
Safety stations
Page 2 of 8
Revision No 2
2.0 Manual Handling 2.1 Where there is a potential for manual handling activities to cause injury or strain, documented risk assessments are to address the physical capacity of the persons involved. The risk assessments are to address work position and duration, distance and route of travel, weight and handling characteristics of the load, actions and movements, age, clothing, skills and experience. Each SWMS should take into consideration manual handling hazards. 2.2 SWMS are to be assessed in the first instance for including of lifting aids and methodologies, however, sites should ensure that sufficient manual handling aids are available supplied by the subcontractor of are on site for hire or loan to subcontractors so that Manual handling injuries can be reduced. As a minimum sites should have: Trolley pallet lifters, cable drum lifters, wheelbarrow, removalist trolley. 3.0 Hazardous Substances / Dangerous Goods: 3.1 All hazardous materials / dangerous goods will be listed on the BLL hazardous material register. Copies of the Material Safety Data Sheet (MSDS) will kept on hand in the first aid shed / area. (Note MSDS needs to be updated every 5 years). Where work is to be carried out using hazardous chemicals or substances evidence is required that alternative less hazardous chemicals or substances are not a suitable substitute. Work procedures are to comply with the specifications of the relevant Material Safety Data Sheet or other established safe work procedure. If work is to be undertaken in a confined space, a "Confined Spaces Permit" is to be developed and utilised. Where there is a potential for exposure to noise in excess of 80dba continuously for eight hours , steps
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 3 of 8
1.0 Prestart Meetings / Briefing (PSB) Prior to commencing work each day / shift every sucbontractor must carry out a pre start meeting. BLL staff should witness this on a regular occurrence and ensure that no work starts until the prestart briefing has taken place the PSB will cover as a minimum: Tasks to be undertaken that day / shift. SWMS(s) that will be used that day / shift. Review of previous day / shift i.e: Is there anything that has changed, that can be done better. Any key messages from BLL RE: change of conditions on site or high risk items being undertaken that shift.
5.0 Pollution to Air 5.1 Any discharges of pollutants into the air (fumes, dusts, mists, noise, vapour, odours, ozone, bacterial etc) are to be in accordance with project licences/permits/approvals or environmental protection legislation. 5.2 Site procedures are to be implemented to ensure there is no "environmental harm" and that any "environmental nuisance" is addressed to the requirements of the appropriate environmental protection legislation. 6.0 First Aid 6.1 Any project / works regardless of size will have a trained and certified First aider present at all times during the works. This can be both subcontract and BLL attendant. 6.2 First aid must be provided. It should be easily accessible by employees and preferably available within minutes. So in a very large workplace, or one spanning multiple floors, first aid may need to be available in more than one area 6.3 If you employ more than 25 people at a workplace you need at least one person trained in first aid on staff. 6.4 Trained first aid personnel means either: Senior First Aider HLTFA301B Apply first aid. Occupational First Aider HLTFA301B Apply first aid. HLTFA402B Apply advanced first aid. HLTFA403A Manage first aid in the workforce. 6.5 6.6 Where employees work across separate work areas, the first aid facilities provided may need to be located centrally, with the provision of portable first aid kits in each work area. Where employees work away from the workplace, or in situations where the work performed is not in a building (e.g. vehicles, roadworks), factors to be considered include: 6.7 the type of work performed; access to communications (e.g. telephone); whether the employees work alone or in groups; and Mobile first aid kit.
A first aid room must be provided and maintained at any construction site at which more than 100 persons work or at any other workplace at which more than 200 persons work. If a first aid room is deemed necessary, the following factors should be considered in determining its location, layout and management: Location - the room must be readily accessible during working hours, and situated at a convenient distance from toilets, sink or wash basin equipped with suitable drainage and a supply of hot and cold running water, and a means of boiling water. It should also be close to motor vehicle access. Workspace - the room should be large enough to accommodate equipment and furniture, leaving enough space for people to administer first aid. Entrances and corridors must be wide enough to
Page 4 of 8 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 5 of 8
Revision No 2
Yes
No Can a 3 inch grinder be used with all safety shields / Handles? No Can a 9 inch grinder be used with all safety shields / Handles?
Yes
Utilise 3 inch
Yes
Proprietary Guard Secondary Handle Correct blade Cut off brake SWMS and proof of training Double eye protection + PPE
Utilise 9 inch
No
Yes
Proprietary Guard Secondary Handle Correct blade Cut off brake SWMS and proof of Training CM sign off on SWMS Double eye protection + PPE
Utilise 9 inch
Deadman switch
Note: check RPM DOs Do visually inspect all wheels before mounting for possible damage in transit. Do check mounting flanges for equal and correct diameter. Do always use a guard of a suitable type supplied by the manufacturer of the grinder. Do allow newly-mounted wheels to run at operating speed Note: check RPM with guard in place for at least one minute before grinding. Do wear all of the above PPE. Do check the correct type of wheel is fitted for the job before starting
Secondary Handle Proprietary Guard DONTs Dont force a wheel onto the grinder or alter the size of the mounting hole. If the wheel wont fit the grinder, get one Deadman switch that will. Dont tighten the mounting nut excessively. Dont grind on the wheel unless the wheel is specifically designed for that purpose. Dont start the grinder until the wheel guard is in place. Dont jam work into the wheel. Dont stand directly in front of a grinding wheel when the grinder is started. Dont allow equipment to be exposed to weather or extreme temperature changes or use a wheel that has been dropped.
Page 6 of 8
Revision No 2
Page 7 of 8
Suppliers / Resources
Page 8 of 8
Revision No 2
2 Personal Protective Equipment All persons exposed to construction operations must wear: Hard hat Safety boots - with toe and mid-sole protection (steel caps) Eye protection Gloves High visibility clothing Other items of Personal Protective Equipment (PPE) should be provided on an as need basis informed by risk assessment, hearing protection should be worn in areas where noise levels exceed 80 db(A) All operatives, managers and visitors should also be encouraged to wear gloves, ear defenders, respiratory protection, high visibility clothing, etc. suitable to protect them from all health and safety risks they are exposed to or following local requirements.
Standard:
Hearing protection on a risk assessment basis and when levels exceed 80dba
Note: eyewear must be appropriate ie: do not use dark glasses inside.
Page 1 of 4
Revision No 2
Page 2 of 4
Revision 2 No 2
Check
And where applicable for the task or situation at hand as determined by the relevant SWMS or JSA -
Page 3 of 4
Compliance rules: PPE is considered a last line of defence against injury and it is noted that the risk of injury should be removed under the hierarchy of control. As such, to ensure minimum levels of compliance and ensure that the time of our construction teams is best spent in identifying and removing risks, the following adherence policy has been set to ensure that we do not spend in effective amounts of time policing the PPE requirement. Not wearing any of the mandatory PPE requirements: a) 1st Warning Verbal warning b) 2nd Warning Written warning, via project web P1. c) 3rd Warning Written Warning and eight (8) hours suspension from site. d) 4th Warning Written Warning and thirty six (36) hours suspension from site. Written warning and offender removed from ALL BLL sites for minimum 1 year. e) 5th Warning This disciplinary procedure will not be unreasonably applied, however, it should be noted that if the offender blatantly disregards the Company Safety Rules and PPE requirements, The General Foremen/ Construction Manager may remove the person from site at anytime. This procedure should be clearly signposted on site, covered in the site induction and strictly enforced. Visitors loans Sites will carry sufficient quantities of PPE to ensure that visitor, consultants, staff and clients etc can use free of charge. This includes: Steel cap boots Disposable gloves High vis bests Hard hats Hearing protection Protective glasses Overspecs (in the case of prescription glasses)
Related Information
Suppliers / Resources
Page 4 of 4
Revision 4 No 2
3 Welfare Welfare requirements must be assessed and facilities provided prior to construction works starting on site. The facilities provided should reflect our company vision and values, the hazards present, numbers of users and their different needs. Where other parties are involved, arrangements must be put in place, which meet the standards below: Sufficient toilet facilities must be provided, in easy access of working areas, and plumbed into the mains (rather than chemical) where practical. Appropriate facilities must be available to meet the needs of different cultures (e.g. for praying). Washing facilities with hot and cold water must be provided and be adequate for the numbers of workers and level of risk. Showers should be provided where reasonably practical and where necessary due to risk. Appropriate supplies of clean drinking water must be provided for workers on all projects. Enhanced levels of welfare facilities must be provided for high risk works, e.g. asbestos or lead removal (e.g. contaminated by hazardous materials requiring shower facilities and PPE cleaning) or environmental conditions (e.g. extreme temperatures).
Standard:
Site Entry Statement gives clear indication of professionalism and clear directions.
Page 1 of 5
Revision No 2
Page 2 of 5
Revision No 2
Outdoor areas
Idea: Subsidise canteens or rent free in return for good prices for workers
Page 3 of 5
Revision No 2
1.0 Site Entry Statement: 1.1 Consideration should be given to the first impressions given when entering sites and also the last message a worker gets before entering the site. Site entry statements should be approved by the Operations Manager and should include: Closed in room, area that is clean, well lit and contains:
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 4 of 5
From time to time sites may be able to provide tea and coffee and or subsidized canteens. It should be ensured that workers understand that these are all BLL safety initiatives and that all we ask in return is that they work safely. A construction project requires the following welfare facilities to be provided on construction sites: Sanitary conveniences Washing facilities Drinking water Changing rooms and accommodation for clothing not worn during working hours Rest facilities Note: see local codes for numbers and sizes etc.
2.3
Related Information
Subcontractor Safety Matrix Minimum Sustainable standards for site shed accommodation
Suppliers / Resources
Page 5 of 5
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
1 Fire Prevention Measures All locations must implement measures to effectively manage the risks from combustible materials (such as paper, card, wood dust, timber, plastic and polystyrene) and highly flammable liquids and gases (such as solvents, liquefied petroleum gas (LPG), oxygen, etc.). Particular attention should be paid to the control of polystyrene packaging, textiles, furniture with foam padding and highly flammable gases and liquids: minimise the amounts used and stored on site; remove waste and empty containers as soon as practicable; ensure highly flammable liquids and gases are used and stored safely in well ventilated stores. Materials Safety Data Sheets must be available and used to assess risks, train people and control measures for storage and use of highly flammable materials and hazardous substances. All hot works processes likely to produce sources of ignition such as burning, grinding, heating, welding, flame cutting, etc. should be controlled by the use of a permit system. The issue of permits should be controlled by a competent person who is to inspect work areas to ensure they are safe (before and after) and that fire extinguishers are available before issuing permits and to record details in a site log so others can check what permits are currently in place. Lighting (particularly halogen lights) must not be located near combustible materials. Intrinsically safe (flame proof) lighting and switches must be provided in areas where explosive/highly flammable liquids/gases are used or stored. Damaged or faulty electrical appliances or installations must be taken out of service or repaired immediately. Smoking should be prohibited within all enclosed areas and in the vicinity of combustible materials, explosive, and highly flammable liquids/gases.
Standard:
Hazchem storage
Containment Storage for diesel at site (locked, bund below, signed and extinguishers present)
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Page 1 of 6
Secured method of storage with appropriate bunding to contain Fully mobile and easy to move (balanced)
Inappropriate storage, no bunding to contain spill, bad location, other gases need by also incorrectly stored
Good method of secure storage but no appropriate bunding to contain and over a stormwater drain
Page 2 of 6
Revision No 2
Re-locatable outdoor pallet friendly flammable liquid store Approved storage cabinets for flammable liquids 160 litres
Good storage of gases but inadequate separation needs to be greater than 3m Gases unsecured outside cage and mixed gases together
Page 3 of 6
Revision No 2
5 6
1.0 General 1.1 Undertake Project Impacts and Hazards Risk Assessment to identify potential impacts and hazards which may lead to the outbreak of fire, including assessing the risks, and identifying effective measures aimed at eliminating or subsequently controlling these impacts and hazards. 1.2 The local Fire Brigade or other relevant emergency services should be invited to attend a site visit prior to construction activities commencing to have input into the BLL Risk Assessment, and assist with identifying appropriate types and locations of fire controls/fire prevention/fire fighting equipment, and any requirements they may have regarding access to site and hydrant connection points, should an emergency occur, are incorporated in the BLL Risk Assessment. The Risk Assessment must take into account BLL and Subcontractors project offices, amenities and storage areas related to the Project, but otherwise outside the perimeter fencing (e.g. Project office located across the road, in an adjacent building etc). Where site offices or accommodation is to be located within existing structures (e.g. rented building space, car park in operating shopping centre), structures are to be investigated to confirm compliance with Building Code of Australia inspection, testing and certification requirements. Where the construction works involves refurbishment of existing occupied building or structure, the Building Owner/Manager is to be consulted to ensure BLL is aware of, and takes into consideration, any existing Fire and Emergency requirements or procedures. All hot works processes assessed as high risk in the Project Impacts and Hazards Risk Assessment, to be controlled by the use of a permit system. The issue of permits should be controlled by a competent person who is to inspect work areas to ensure they are safe (before and after) and that fire extinguishers are available before issuing permits and to record details in a site log so others can check what permits
Page 4 of 6 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
1.3
1.4
1.6
1.7 1.8
1.9
1.11 All in-ground services are to be identified prior to works by Dial Before you Dig and other services search by experienced, accredited locators. Ensure any pipe or surface to be cut does not contain live or pressurised services. Isolate these prior to works. Utilise a Lock Out/Tag Out permit where required by Risk Assessment. See also controls identified in GMR No 3 and No 5. 1.12 All hot works (requiring a hot works permit) are to cease at least 30 minutes prior to end of shift to ensure no hot areas are left unattended. 1.13 Note: consideration of material being cut by oxy / grinder needs to take into account smoke produced etc. i.e; oxy cutting galvanised duct or painted metal produces smoke and harmful toxins. 1.14 Spill control kits are to be located on any site where re-fuelling activities take place. 2.0 Storage and signage 2.1 Combustibles, including flammable liquids and / or gases are to be properly stored and have their own designated storage facility in accordance with the requirements of local code and MSDS. The location and construction of the designated storage area should consider any hazards present in areas where BLL has limited control (e.g. a flammable liquids store located at the site perimeter where sources of ignition could be generated from over the site boundary). Signage is to be posted to ensure that no naked flames, heat source, smoking etc are in proximity to
2.2
Page 5 of 6
Revision No 2
1.10 No smoking when refuelling plant and equipment, refuel in well ventilated area make sure the equipment has cooled down prior to fuelling, screw fuel caps on well, and wipe any spilled fuel off surface of fuel containers or equipment. Safety approved fuel containers must be used. A spill kit and spill procedure to be in place, and contaminated waste disposed to an EPA approved facility.
3.0 Lighting and Electrical 3.1 High heat producing or emitting devices like halogen tungsten lamps must be kept away from combustibles. As far as possible, they must be properly hung at heights such that persons and materials are not subjected to inadvertent contact with any hot surfaces. Halogen lighting should not be used as task lighting located on ground or stands, but should be fixed to structure as area lighting. Glass fronts must be in place on fittings. All electrical equipment and temporary installations to be inspected, tested and tagged according to Federal and State Electrical Standards, Regulations and Codes. Damaged or faulty electrical appliances or installations must be taken out of service or repaired immediately. See also controls identified in GMR No 5.
3.2
4.0 Material Safety Data Sheets (MSDS) 4.1 An MSDS register shall be maintained for all chemical or hazardous substances used at the site. The MSDS must be posted at the area of storage, and attached to any SWMS submitted for review. MSDS shall be available upon request. Workers must be inducted to the safe use requirements of the MSDS as part of the SWMS induction. A copy of the MSDS register shall be located at the first aid room.
5.0 Transport 5.1 The Transport, Storage and Use of Dangerous Goods and Hazardous Substances will comply with the requirements of Federal and State Hazardous Goods and Material Standards, Regulations and Codes. No storage of hazardous or flammable chemicals or substances is allowed in unventilated or confined spaces or areas. Intrinsically safe (flame proof) lighting and switches must be provided in areas where explosive/highly flammable liquids/gases are used or stored. They cannot be stored with oxy acetylene bottles or any other explosive or combustible material. They must be in a spill proof or bunded container, approved for the storage of the substance. Appropriate type and numbers of fire extinguishers and spill kits must be kept in working order and accessible for use, in the immediate vicinity of these stored goods. The type, quantity and location of Hazardous/Dangerous goods and materials must be listed in the Site Hazardous Substances Register and stored only in areas nominated by BLL.
Related Information
Hot Works Permit
Page 6 of 6
Revision No 2
2 Fire Detection and Alarm Systems Adequate arrangements should be made to detect and raise the alarm in the event of a fire or other emergency. This may range from the use of bells, horns or sirens and people assigned to fire watch duties on construction sites to fully automated systems in occupied premises. Alarms must be audible in all parts of the location where people may be present. All detector and alarm systems should be checked/tested on a monthly basis to ensure they are functional and the results recorded.
Standard:
1.0 Planning 1.1 Risk and Opportunity at Design review to identify means to fast track design, installation and commissioning of permanent services and fire prevention/control/detection/alarm/fighting equipment. Designs to comply to the Building Code of Australia and other specified Australian Standards, Regulations, or Codes. Undertake Project Impacts and Hazards Risk Assessment to identify potential impacts and hazards which may lead to the outbreak of fire, including assessing the risks, and identifying effective measures aimed at eliminating or subsequently controlling these impacts and hazards. Project Induction to include relevant sections of the Project Incident Management and Emergency Evacuation Procedures, and all workers to undergo Project Induction prior to commencement of work on site. Induction content is updated to address ongoing changes in the fire detection and alarm system. Tool
Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
1.2
1.3
Page 1 of 2
2.2
3.0 Alarms and evacuation 3.1 The Risk Assessment is to identify the system to be used to raise the alarm to BLL of the presence of site emergency incidents and evacuation situations as they arise (e.g. nurse call, 2 way radios, mobile phones), and the system BLL will use to notify site of the need to evacuate (e.g. siren, alarms, signals, fire wardens). All sites will have an audible alarm raising system. The Project Incident Management and Emergency Evacuation Procedures will identify the type, number and location of any detection or alarm systems. Ensure all possible locations are considered, such as hoists, builders lifts, tower cranes, jump forms, plant rooms, and amenities. Refer also to GMR 7.5 Evacuation Procedures. Fire/smoke alarms to be fitted to all temporary site buildings, e.g. office and amenities. Site inspections are conducted weekly to ensure established detection and alarm systems are still relevant, operating and undamaged (e.g. by OHS Committee or EHS Checklist inspection). Monthly review of Project Incident Management and Emergency Evacuation Procedures includes assessment of continued adequacy of fire detection and alarm system.
3.2
3.3 3.4
Related Information
Suppliers / Resources
Page 2 of 2
Revision 2 No 2
3 Means of Escape Two alternative means of escape suitable for the number and specific needs of all people likely to need to use them (e.g. wide enough for wheelchair users where present) must be provided where possible at all work locations.
Standard:
Emergency exit routes must be easily identifiable, kept free from obstruction, have emergency lighting, directional signs and exit points marked. Emergency routes should offer half an hour fire resistance and have fire doors fitted to them where appropriate.
Page 1 of 3
Revision No 2
1.0 Planning and General 1.1 Risk and Opportunity at Design review to identify means to fast track design, construction and installation of permanent fire exits/escape routes, and permanent building emergency and general lighting. ROAD to address designing permanent fire stair construction as part of the jump form, use of prefabricated stair systems for construction, and optimisation of fire rated and fire resistant elements, materials and products. Designs to comply to the Building Code of Australia and other specified Australian Standards, Regulations, or Codes. Undertake Project Impacts and Hazards Risk Assessment to identify potential impacts and hazards which may lead to the outbreak of fire, including assessing the risks, and identifying effective measures aimed at eliminating or subsequently controlling these impacts and hazards. Where the construction works involves refurbishment or fitout of existing occupied building or structure, BLL Evacuation Procedures are to be developed and implemented in consultation with the Building Owner/Manager to ensure they align with any existing Fire and Emergency requirements or procedures. Project Induction to include relevant sections of the Project Incident Management and Emergency Evacuation Procedures, and all workers to undergo Project Induction prior to commencement of work on site. Induction content is updated to address ongoing changes in the location of emergency escape routes and evacuation procedures. Tool box talks or other forms of communication are held to inform previously inducted personnel of ongoing changes.
1.2
1.3
1.4
2.0 Exits and escape Where means of escape is limited, such as on the top deck under construction or a in a jump form, movable stairs are to be used in preference to ladders. Two alternative means of escape should be available at all times, where possible. Site specific Incident Management/Emergency Evacuation Procedures, Site Rules and Safe Work Method Statements are to ensure arrangements are made to keep: Sufficient numbers of fire exits available for the number of people on site, relevant to the building dimensions and ease of safe access around construction areas All fire exits/escape routes are clearly marked, emergency signage in place Fire doors, designated accessways, internal and external stairs/scaffolds, hoist, crane, jump forms and trailing deck/stair and lift access to remain clear at all times Adequate emergency lighting installed/maintained at emergency access points and in general site accessways Drawings showing fire exits and escape routes, evacuation assembly areas, first aid/nurse call/fire alarm/emergency alarm device/fire fighting equipment type and location posted on noticeboards, or in strategic locations (e.g. in hoists, lifts, jump forms), and maintained as access and site conditions change Storage of materials and delivery areas controlled to prevent impact on emergency
Page 2 of 3 Issue date 1 July 2008 Last amendment date 30 July 2009 Revision No 2
Related Information
Suppliers / Resources
Page 3 of 3
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
4 Fire Fighting Equipment Sufficient numbers and types of fire fighting equipment must be available and correctly located at all times in accordance with local regulations and current good practice. Fire extinguishers, hose reels, fire blankets and riser inlet and outlet valves must be readily accessible, unobstructed, clearly signed and regularly checked. Risers should progress with the construction or demolition of buildings, be no more than two floors below the construction floor and be regularly tested to ensure adequate water flow rate/pressure for the length and diameter of the riser and hose attached. Connections for the Fire Authority must satisfy the local requirements. On floors where it is impracticable to provide coverage from risers and hose reels, effective means for extinguishing fires must be provided, e.g. drench drums, fire pails and additional fire extinguishers.
Standard:
A sufficient number of Fire Marshalls/Wardens must be appointed and trained in basic fire fighting techniques using the equipment available. All fire fighting equipment must be checked and serviced regularly, including testing of pump sets of wet risers and fire fighting lift controls and the results recorded. A weekly visual check must be carried out on all fire fighting equipment to ensure they have not been damaged, discharged or gone missing. Adequate access must be maintained at all times for emergency services vehicles. Periodic reviews of the fire fighting facilities shall be made with local Fire Authority to update equipment, access locations and relevant construction processes.
Class B - Flammable & Combustible Liquids Petrol, oil, paint, thinners, kerosene, alcohol, etc
Class C - Flammable Gases L.P.G., Butane, Acetylene, Hydrogen, natural gas and Methane etc
Page 1 of 5
Revision No 2
Class F - Cooking Oils and Fats Cooking oils and fats usually found in industrial kitchens etc.
Extinguisher
Description
Water Red in colour, it contains nine litres of water under pressure and is to be used in an upright position. It is designed for use on carbon based solids such as wood, paper, rubbish or textiles, and has a discharge period of 60 - 100 seconds. Water extinguishers are unsuitable for flammable liquid fires. This extinguisher must never be used on fires involving live electrical equipment. Foam Blue in colour, it contains nine litres of an aqueous film-forming foam additive, and is to be used in an upright position. It is designed for use on flammable liquid fires such as petrol, oils and paint and has a discharge period of 40 - 90 seconds. This extinguishers must never be used on fires involving live electrical equipment. Carbon Dioxide Red in colour with a black band, it is designed for use on fires involving flammable liquids and live electrical equipment. The discharge period depends on the size of the extinguisher.
Dry Chemical Red in colour with a white band, it contains a bi-carbonate based powder and is suitable for fires involving flammable liquids and live electrical equipment. The discharge period depends on the size of the extinguisher.
Wet Chemical Gold in colour, it has a liquid alkaline extinguishing agent, and is specifically designed for use in kitchens on deep fryer fires involving fat and cooking oil. This extinguisher must never be used on fires involving live electrical equipment.
Page 2 of 5
Revision No 2
Page 3 of 5
Revision No 2
1.0 Planning and risk assessment 1.1 Risk and Opportunity at Design review to identify means to fast track design, installation and commissioning of permanent services and fire prevention/control/detection/alarm/fighting equipment. ROAD to address number, location and type of temporary equipment required for site establishment and construction, and allocate as part of the relevant services procurement package. 1.2 Undertake Project Impacts and Hazards Risk Assessment to identify potential impacts and hazards which may lead to the outbreak of fire, including assessing the risks, and identifying effective measures aimed at eliminating or subsequently controlling these impacts and hazards. 1.3 The Risk Assessment to identify an adequate type, size and number of regularly tested and inspected fire extinguishers and/or fire hose reels, hydrants and risers must be provided in all areas. Testing and tagging of fire extinguishers to occur on a 6 monthly basis, or where otherwise specified by Australian, Standards, Regulations or Codes. 1.4 Clear access to fire fighting equipment, and signage indicating its location, is to be maintained at all times. Weekly inspections are to be conducted to ensure this occurs, and that equipment is not damaged, missing or discharged (e.g. OHS Committee, BLL EHS Checklist inspections). 1.5 In consultation with the Project OHS Committee or Representatives, where appropriate, the local
Fire Brigade service should be invited to attend inspections or meetings to give input into and assist in the review of Project Fire Emergency systems and procedures, and review ongoing clear access for emergency fire fighting services.
1.6 Monthly review of Project Incident Management and Emergency Evacuation Procedures includes assessment of continued adequacy of fire fighting equipment type, location and number. 2.0 Equipment and controls 2.1 Where possible, risers should progress with the construction or demolition of buildings, be no more than two floors below the construction floor and be regularly tested to ensure adequate water flow rate/pressure for the length and diameter of the riser and hose attached. Designs to comply to the Building Code of Australia and other specified Australian Standards, Regulations, or Codes. 2.2 Activities associated with hot works such as Oxy cutting, use of LPG, welding to have an appropriate type and size fire extinguisher in the immediate work location and allocated specifically for the works. 2.3 All mobile powered plant and equipment to have an appropriate type and size of fire extinguisher located within each item of plant, or available in close proximity to works. 3.0 Training
Page 4 of 5
Revision No 2
5.3
Related Information
Suppliers / Resources
Page 5 of 5
Revision No 2
is h
ag p
i e
in s
n te
on ti
lly a
la b
k n
5 Evacuation Procedures All staff and visitors must be given instruction on emergency warning systems and evacuation procedures, including the area to assemble for the roll call. Evacuation routes and Assembly Points must be well signed.
Standard:
A sufficient number of Fire Marshalls/Wardens must be appointed and trained in evacuation procedures and their details recorded. Fire drills should be held regularly (at least once per year for low risk situations; more frequently for higher risk situations) and their results recorded and used in performance reviews by the Safety Leadership Team.
Escape signage
Check
1.10 Emergency rescue for trapped or injured personnel. 1.11 First aid facilities, personnel and any site specific procedures for first aid treatment, medical referral, workers compensation and Return to Work monitoring. 1.12 Training or induction of all personnel working on site. 1.13 Ensuring the safe evacuation of visitors to the site, (e.g. Visitors Register, visitors accompanied by site inducted person at all times, visitors issued emergency instructions cards, mini- induction to address evacuation etc). 1.14 Potential interface and emergency management responsibilities and communication with existing client or site occupier/tenant incident and emergency evacuation plans or procedures.
1.15 Control of unauthorised access onto site/registration of personnel arriving on site (e.g. Blue Glue access control, daily attendance book, Subcontractor Supervisors diary etc), and system of accounting for personnel in an emergency situation. 1.16 Incident communication and reporting procedures, emergency contact details, including out of hours emergencies. 1.17 Bomb threat, terrorist threat or other externally influenced emergencies. 1.18 Management of public relations and media. 1.19 Notification to regulatory authorities (e.g. WorkCover, WorkSafe, EPA). 1.20 Incident investigation, counselling and debrief. 2.0 Project Incident and Emergency Management Procedures shall be tested at least every 6 months through drills and other exercises, and reviewed minimum monthly, or as site conditions and controls change, and updated as necessary. 3.0 Project Incident Management and Emergency Evacuation Procedures are posted on project noticeboards along with a Drawing showing the location of fire exits and escape routes, evacuation assembly areas, first aid/nurse call/fire alarm/emergency alarm device/fire fighting and other emergency equipment. 4.0 Relevant sections of the Project Incident Management and Emergency Evacuation Procedures and Project Impacts and Hazards Risk Assessment are required to be issued with subcontract tender packages where items are identified for information to, management of, or action by Subcontractors or other service providers, any relevant agreed responsibilities or actions must be included in contract documentation.
Page 2 of 3
Revision No 2
Related Information
Suppliers / Resources
Page 3 of 3
Revision No 2