SCOPE OF WORK Following systems has been considered in scope of work: Mechanical 1. Coal Handling system 2.

Ash Handling system 3. Mill reject handing system 4. Water Pretreatment system 5. Water Treatment Plant MED/MB Plant 6. Sewage water treatment plant 7. Circulating water System 8. Dosing system 9. Sea water System 10. ACW System 11. Effluent Treatment Plant 12. Chlorination system 13. Fire Protection and detection System 14. LDO pumps , LDO tanks 15. Ventilation system 16. Air condition system 17. Compressed air system (Flow diagram for Bid Purpose) 18. DM Water, Potable & Service Water distribution system 19. H2 and CO2 system 20. DM storage tank. 21. Miscellaneous pumps. 22. HFO storage Tank and pumps 23. Natural Draft Cooling Tower 24. CW Pumps 25. Ash disposal 26. Cranes ,and hoists 27. Elevators 28. Miscellaneous Pumps 29. Piping and valve fittings 30. Piping and insulation 31. Workshop 32. Chemical lab equipments Electrical 1. Generator transformers & Other Transformers(UAT, ST, DT) 2. Switchyard 3. HT Switchgear 4. MCC ,PCC 5. Battery and Battery charger system 6. Generator Circuit Breaker 7. Bus Ducts 8. UPS system 9. PLCC 10. Emergency DG set 11. Illumination system 12. Plant Communication 13. Relay panels 14. Cables 15. Earthing & lightning protection 16. Cable trays & Termination kit

17. NGR 18. NGT 19. Electrical lab equipment Instrumentation and Controls: 1. PLCs/Microprocessor /Relay processor 2. Cables 3. Analyzers 4. Field instruments 5. Instrument lab instruments Civil and Structural 1. Geo technical investigation ( Preparation of specification only) 2. Chimney 3. General Civil, structural and architectural works for portion of BOP buildings 4. and foundation. 5. Erection works -Mech, Electrical and C&I ( Preparation of specification) 6. Painting ( Preparation of specification) Following activities has been considered in Scope of work 1 Basic engineering 1. Design Basis Reports 2. Sizing Calculations 3. Plot Plan, Building GA drawings, Schematic drawings and other layouts 4. Purchase Specifications for packages listed above. 5. Modeling 2 Detailed Engineering Mechanical 1) Piping stress analysis 2) Piping Isometric drawings 3) Piping GAs 4) MTO for Piping, valves,, fittings and supports Electrical Works 1) Electrical SLD 2) Cable schedule drawings 3) Cable MTO 4) System studies Civil, structural and architectural works 1) Detail Civil and structural MTO for Purchase 2) Civil drawings, Roads and drainage drawings 3) Chimney drawings 4) Chimney tunnel study ( it will be part of chimney turnkey package) 5) Foundation calculations and drawings 6) Architectural detailed drawings 7) Structural drawings 8) Review of structural steel Fabrication drawings for all the structures designed by DE Consultants C&I works 1) Configuration drawing 2) Cable MTO 3) Logic diagrams 3 OTHER WORK As built drawings shall be prepared based on red line mark-up drawing received from site. Integration of O&M manuals Attending client / site technical meetings as required Regular review meeting with EPC contractors (F2F or VC)

Scope of Work for Detailed engineering consultant Basic engineering 1) Design Basis Reports 2) Sizing Calculations 3) Plot Plan, Building GA drawings, Schematic drawings and other layouts 4) Purchase Specifications for identified packages(list enclosed) 5) Modeling Detailed Engineering Mechanical 6) Piping stress analysis 7) Piping Isometric drawings 8) Piping GAs 9) MTO for Piping, valves,, fittings and supports Electrical Works 10) Electrical SLD 11) Cable schedule drawings 12) Cable MTO 13) System studies Civil, structural and architectural works 14) Detail Civil and structural MTO for Purchase 15) Civil drawings, Roads and drainage drawings 16) Chimney drawings 17) Chimney tunnel study 18) Foundation calculations and drawings 19) Architectural detailed drawings 20) Structural drawings 21) Fabrication drawings(shall be quoted separately) C&I works 22) Configuration drawing 23) Cable MTO 24) Logic diagrams 25) As built drawings 26) Integration of O&M manuals 27) Attending client / site technical meetings as required 28) Regular review meeting with EPC contractors(F2F or VC) 29) Any other basic or detailed engineering documentation required for completion of the project.
CLARIFICATIONS & CONSIDERATIONS 1. Detailed Engineering will be carried out in accordance with design basis/criteria prepared by DE CONSULTANT and approved by Owners Engineer. 2. DE CONSULTANT will develop the engineering schedule, based on L2/ L3 schedule provided by CCCL and in mutual discussions with CCCL for sequential release of engineering deliverables to meet the project / construction schedule based on the inputs from CCCL such as milestone dates for order placement, manufacturing time, delivery and execution of various equipment and packages. DE CONSULTANTs planning and

monitoring activities are limited to the engineering deliverables in DE CONSULTANTs scope only. 3. DE CONSULTANT will review vendor drawings and documents with respect to specification compliance and interfaces requirements (excluding interface within scope of Vendors Package). DE CONSULTANT will maintain the vendor drawing status record. 4. To expedite the technical bid evaluation process, it is considered that all the bids for all packages will be made available to DE CONSULTANT. The number of bids to be evaluated will be about on an average four (4) bids. 5. All drawings will be in Microstation / Auto Cad. 6. The soft copy of final As-built drawings will be subsequently submitted at the end of the project in Microstation / Auto Cad. 7. Suitable software (ex.PDS) for power plant detail engineering. 3-D modeling software like PDS is required to be used for the project. 8. Technical assistance for liaison with government/ local authorities for any statutory / contractual requirements, will be provided by DE Consultants. 9. Wherever the BOP packages will be unitized, DE Consultants will prepare necessary supporting documents. 10. Above ground conduit layout shall also be considered in detail engineering scope. 11. Monthly engineering progress report will be prepared and submitted by DE CONSULTANTto CCCL. 12. BTG vendor documents/drawings shall only be reviewed by DE CONSULTANT to derive design inputs for various DE CONSULTANTs deliverables for BOP portion. 13. All the engineering deliverables from DE CONSULTANT will be submitted to CCCL for further distribution to Owner/Owners consultant. 14. Co-ordination and expediting with Owner/ Owners Consultant /Vendors / Equipment suppliers is not considered in DE CONSULTANT scope of work. However, any contractor for detail Engineering/ drafting if employed by you shall be expedited by DE Consultants. 15. Cable Engineering shall be carried out for those cables which are in CCCLs scope of supply. Cable raceway drawings. 16. Special / Transient Studies like Hazop Study , CW transient analysis, model sump study, wind tunnel study and CFD analysis shall be carried out by DE consultants. 17. Preparation of piping isometric drawings and pipe support drawings for all pipe sizes including small bore pipes. 18. Lighting Design Preparation of lighting calculations, lighting layouts, lighting power distribution scheme, lighting BOQ etc. 19. Electrical Harmonic analysis and transient stability studies. 20. Hazardous Area Classification Study and Cathodic Protection system study. 21. Specification for soil investigation study. 22. Review and preparation of structural fabrication drawing. 23. Review of bar bending schedules. 24. Architectural drawings and BOQs. Payment Terms: Design and detailed Plant Engineering price for each Unit will be paid as per detailed break-up as set forth in the Contract after issue of certification of completion of same by Engineering Contractor to EPC contractor and acceptance thereof by EPC contractors representative in following installments:

10 (Ten)% of Design and detailed Engineering as initial advance on fulfillment of conditions in sub- clauses detailed below in Item 1 20 (Twenty)% of Design and detailed Engineering on submission of design engineering documentation, like heat and mass balances, Process and Instrumentation Drawings, plot plan of BOP package, General arrangement Drawings, single line diagram, design criteria and sizing calculations, investigation reports etc. List shall be prepared by Contractor and approved by EPC contractor as per the specification. 10 (Ten)% of Design and detailed Engineering on submission of design engineering documentation, as final documentation of (ii) above, including soft copies and progressive submission of piping Drawings, motor list, instrument list, pipeline reference list, sub-vendor Drawings, etc., as per the Specification. 15 (Fifteen)% of Design and detailed Engineering on submission of design engineering documentation, instrumentation logic diagrams including set points, etc., supervision of erection and Commissioning Manuals and balance documentation. 10 (Ten) % of Design and detailed Engineering on submission of all O&M Manuals complete in all respects. 10 (Ten) % of Design and detailed Engineering on final approval of all documentation and submission of all necessary documentation to make the documentation complete. 5 (Five) % of Design and detailed Engineering on certification of successful completion of Reliability Operation of the Unit. 10 (Ten) % of Design and detailed Engineering on Take over of the Unit. 10 (Ten) % on Acceptance and Issuance of Final Acceptance Certificate by EPC contractor for BOP package i.e. comprising of all Units. Service Contractor acknowledges that certification or its acceptance by the EPC contractor's Representative shall not, however relieve or absolve in any way or manner the Contractor from the performance of Work and other obligations under the Contract including Guarantee and Warranty obligations under the Contract. Note: Payment shall be made based on detailed billing schedule prepared by Contractor and approved by EPC contractor.. Item 1 : Submission of i. Signing of Contract Agreement; ii. Submission of a detailed Network Schedule/PERT network indicating detailed milestones based on the Work schedule and its approval by the EPC contgractor. iii Detailed break-up of equipment components / systems; iv. Detailed activity wise price break up for all Services vii. Documentation and Bank Guarantee for advance viii. Subsequent 5(Five) % payment against advance payment guarantee will be paid within 3 months from effective date.