Вы находитесь на странице: 1из 8

TAIT ASSOCIATES 701 North Parkcenter Drive Santa Ana, CA 92705 (714) 560-8200 (714) 560-8211 fax

Page 1 5/1/2012

Light Standard Design by Manufacture 20 Foot Lite Standard These calculations are for the foundation only Use Zone 4 Seismic Use 70 MPH Basic Wind Speed, Exposure C Soil Pressure, Q= 1000 psf (20% increase/ft of depth & 33% for wind and seismic) Minimum Conc. Strength to be greater than or equal to f'c 2000 psi Minimum Rebar Strength to be greater than or equal to Fy= 60000 psi Use 1997 Uniform Building Code

GENERAL LIGHT DIMENSIONS


H w h W Total height of light Projected width of luminaire Projected height of luminaire Weight of luminaire 20.5 22 6 120 ft in in lb

Tait Associates

Page 1

TAIT Project #SP

TAIT ASSOCIATES 701 North Parkcenter Drive Santa Ana, CA 92705 (714) 560-8200 (714) 560-8211 fax

Page 2 5/1/2012

WIND Ce Cq qs lw P A Vw M ot Mr

100 MPH Basic Wind Speed, Exposure C from Table 16-G from Table 16-H from Table 16-F from Table 16-K =(Ce)(Cq)(qs)(lw) Largest Luminair Area = w*h Horizontal Force From Wind =P*A Moment Overturning from wind =Vwh Moment Resisting Empty =0.66*Wt*W/2 1.06 1.4 12.6 lbs 1.0 lbs 18.70 psf 0.9 17 2057 0 sf lbs in*lbs in*lbs

SEISMIC Zone 4 ap From Table 16-O Ca From Table 16-Q Ip From Table 16-K Rp From Table 16-O Hx Total height of pole Hr Height of Luminair Wp Weight of Luminair Fp =(ap*Ca*Ip/Rp)*(1+3*Hx/Hr)*Wp Fp MIN =0.7*Ca*Ip*Wp Fp MAX =4*Ca*Ip*Wp Fp that governs Seismic source type - B 5km to nearest fault Table 16-S, Na= 1.0 1 0.44 1.5 3 20.5 0.5 120 3274 lbs 55 lbs 317 lbs 3274

SUMMARY Max, Moment at Base, Seismic Max, Moment at Base, Wind =Fp*H =P*A 67108.8 in*lbs 17.1 in*lbs

Tait Associates

Page 2

TAIT Project #SP

TAIT ASSOCIATES 701 North Parkcenter Drive Santa Ana, CA 92705 (714) 560-8200 (714) 560-8211 fax

Page 3 5/1/2012

Rebar Calculations Diameter of pole footing = b= 0.8*diameter d= 0.8*diameter j= 0.9 24 in 19.2 in 19.2 in

As

M*1.4/(0.9*Fy*j*d)

0.1007 in^2/per ft

Temp Steel As min. per ACI 318-95 7.12.2.1 =0.0018*b*t As provided= 1.86 in^2 0.814 in^2

use 6 - #5 Vertical with #3 hoops @ 10" o.c. & 3-#3 hoops top 5" of footing

Tait Associates

Page 3

TAIT Project #SP

TAIT ASSOCIATES 701 North Parkcenter Drive Santa Ana, CA 92705 (714) 560-8200 (714) 560-8211 fax

Page 4 5/1/2012

Tait Associates

Page 4

TAIT Project #SP

Sheet2

WIND Ce Cq qs lw P A Vw M ot Mr

100 MPH Basic Wind Speed, Exposure C from Table 16-G from Table 16-H from Table 16-F from Table 16-K =(Ce)(Cq)(qs)(lw) Largest Tank Area = H*L Horizontal Force From Wind =P*A Moment Overturning from wind =Vwh Moment Resisting Empty =0.66*Wt*W/2 Moment Uplift = 1.06 1.4 25.6 lbs 1.15 lbs 43.69 psf 0.854167 37.31765 4478.118 0 sf lbs in*lbs in*lbs

4478.118 in*lbs

SEISMIC Zone 4 ap From Table 16-O Ca From Table 16-O Ip From Table 16-O Rp From Table 16-O Hx =0 (tank is on ground) Hr =0 (Tank is on ground) Wp From Full tank weight Fp =(ap*Ca*Ip/Rp)*(1+3*Hx/Hr)*Wp Fp MIN =0.7*Ca*Ip*Wp Fp MAX =4*Ca*Ip*Wp Fp that governs M ot Mr Moment Overturning from Seismic =Fp*h' Moment Resisting (wet Wt) =0.66*Wp*W/2 Moment uplift = SUMMARY Max, Total Vert. Load Max, Total Horz. Load Max, Total Overturning restaint required 7300 lbs 3372.6 lbs 4478.118 in*lbs 1 0.44 1.5 3 0 0 7300 1606 lbs 3372.6 lbs 19272 lbs 3372 404640 in*lbs 52998 in*lbs 351642 in*lbs

Page 5

Sheet3

PHASE I IX. DRY UTLITIES & OTHER COSTS


ITEM UNIT UNIT COST QUANTITY COST

A. GAS B. LADWP ELECTRIC SYSTEM C. TELEPHONE (PUBLIC STREETS) D. FEES & PERMITS: RR PORTION ST./UTILITY E. BONDING COSTS: RR PORTION ST./UTILITY

LS LS LS LS LS LS LS

$10,080 1 $10,080 $658,320 1 658,320 $49,380 1 49,380 $14,140 1 14,140 $23,120 1 23,120 $7,070 1 7,070 $9,560 1 9,560 SUBTOTAL $771,670

Page 6

Sheet4

DEDICATED INFRASTRUCTURE COST ESTIMATE


SUMMARY PHASE I (REVISED 12-23-97) SURVEYING / ENGINEERING / TESTING STREET IMPROVEMENTS STORM DRAIN IMPROVEMENTS STREET LIGHTS LANDSCAPING / STREET TREES SANITARY SEWER WATER RAILROAD DEDICATED INFRASTRUCTURE TOTAL DRY UTILITIES & OTHER COSTS PROJECT GRAND TOTAL $ 84,429 624,419 485,797 56,333 75,594 36,106 67,375 852,178 $ 2,282,231 $ 771,670

$ 3,053,901

Page 7

Sheet5

DEDICATED INFRASTRUCTURE COST ESTIMATE


PHASING SUMMARY (REVISED 12-23-97) SURVEYING / ENGINEERING / TESTING STREET IMPROVEMENTS STORM DRAIN IMPROVEMENTS STREET LIGHTS LANDSCAPING / STREET TREES SANITARY SEWER WATER RAILROAD ON-SITE GRADING DEDICATED INFRASTRUCTURE TOTAL DRY UTILITIES & OTHER COSTS PHASE GRAND TOTAL PROJECT GRAND TOTAL $ $ $ PHASE I PHASE II PHASE III SUMMARY $ 84,429 346,962 208,220 $ 639,611 624,419 485,797 56,333 75,594 36,106 67,375 852,178 2,282,231 771,670 3,053,901 527,105 974,222 111,438 600,390 138,467 249,990 402,100 2,819,262 6,169,936 1,316,160 7,486,096 574,722 162,778 67,430 361,404 85,136 148,661 788,818 1,790,566 4,187,735 789,860 4,977,595 $ 15,517,592 1,726,246 1,622,797 235,201 1,037,388 259,709 466,026 2,043,096 4,609,828 $ 12,639,902 $ 2,877,690

Page 8

Вам также может понравиться