Abstract
Concern about the poor performance of the construction industry, in the UK and elsewhere, is coming at a time when its
customers are demanding more and projects are becoming increasingly complex. Many of the industry’s performance
problems stem from inadequate inter-organisational co-operation. The paper explores the problems and solutions in aligning
the construction industry more closely to its customers in CoPS-type projects. Using the example of a high value, high
complexity offshore oilfield construction project, the paper examines the use of ‘partnering’ as a tool for stimulating
performance gains at the project level and innovation and learning benefits at the organisational level. q 2000 Elsevier
Science B.V. All rights reserved.
)
Tel.: q44-1273-877166; fax: q44-1273-685865.
1
E-mail address: j.g.barlow@sussex.ac.uk ŽJ. Barlow.. See Appendix A for details of research method.
0048-7333r00r$ - see front matter q 2000 Elsevier Science B.V. All rights reserved.
PII: S 0 0 4 8 - 7 3 3 3 Ž 0 0 . 0 0 1 1 5 - 3
974 J. Barlowr Research Policy 29 (2000) 973–989
ment ŽKubal, 1994., or strategic planning ŽHancock cluding clients, and the nature of interactions be-
et al., 1996.. One of the main reasons for customer tween contractual parties will be partly influenced by
dissatisfaction is said to be the failure of the con- a client’s previous experience of procuring construc-
struction industry to understand the needs of its tion work. Clients range from the very experienced
customers and effectively translate these into prod- to those who are infrequent purchasers of construc-
ucts ŽDulami et al., 1996.. The project-based nature tion services, with little incentive to become expert
of the industry means that different solutions to in the procurement process Žsee Table 1; cf. Game-
similar customer requirements are put forward, hin- son, 1996, for similar classifications.. Inexperienced
dering organisational learning or standardisation in or infrequent clients dominate in sheer numbers
construction processes. ŽAnumba et al., 1996., but experienced clients ac-
This state of affairs has not gone unnoticed in the count for the majority of construction work ŽHMSO,
UK. Improving the project briefing process has long 1990.. These clients — who include many govern-
been seen as critical — government and other re- ment bodies — have become increasingly concerned
ports on this issue date from the 1960s Že.g., MPBW, with the need for change and have exerted consider-
1964; Higgin and Jessop, 1963; O’Reilly, 1973; able influence over the construction industry to try
NEDO, 1974, 1991; Barratt et al., 1996.. Until re- and raise its standards. Table 2 indicates the largest
cently, however, major customers and government clients in the UK, measured by the value of their
have tended to see improvements to the briefing construction expenditure for the period 1998-99. As
process as a quick fix for the construction industry’s the table shows, many are major, ‘blue chip’ manu-
performance problems. This obviated the need to facturing and service companies. These are fre-
take harder decisions about ways of fundamentally quently involved in procuring complex, high value,
deepening the level of customer focus in the indus- high-risk construction projects such as sophisticated
try. However, a series of government initiatives is manufacturing facilities, railway infrastructure, or
now attempting to modernise the construction indus- complex urban regeneration schemes.
try ŽLatham, 1994; Construction Taskforce, 1998., Traditional approaches to organising the construc-
and there is some evidence that client satisfaction tion process, described above, can work well for
has improved since 1995 ŽCIBrBuilding 1999.. relatively simple, slow and certain projects. When
Concern about the industry’s poor performance is this is not the case — when projects are more
coming at a time when its customers are demanding
more from it. Indeed, many customers for construc-
Table 1
tion products and services represent considerably Types of construction client
more advanced industrial sectors than the construc-
Frequency of Reason for procurement
tion industry itself. Their requirements have been a procurement Investor Occupation
major driving force for change in the construction
Frequent Ø Property developers Ø Large clients
industry.
Ø Investors seeking Ø Experienced in the
short-term returns construction
process
3. The customer interface in complex construction Ø Influential on the
projects construction
industry
Ø Long-term view
In any given construction project, there is a chain
of internal and external customers. The end-customer Infrequent Ø Many clients
— generally known as the ‘client’ or project ‘owner’ Ø Inexperienced in
in the construction industry — is usually defined as construction
the person or firm responsible for commissioning Ø Dissatisfied, but
unable to influence
and paying for the project ŽAnumba et al., 1996..
the industry
There is considerable diversity between and within
organisations involved in construction activities, in- Source: DoE and British Telecom Ž1995..
976 J. Barlowr Research Policy 29 (2000) 973–989
Table 2
Largest UK construction clients
Client Ownership Construction activity £ Žmillions.
Railtrack Private Rail infrastructure 858.0
London Borough of Southwark Local government Urban regeneration 619.7
London and Continental Railways Private High-speed rail line 595.9
Energy Power Development Private Power generation 595.0
Dept of the Environment, Transport Central government Urban regeneration 590.2
and the Regions
Ministry of Defence Central government Military facilities 555.1
National Power Private Power generation 544.2
English Partnerships Public Urban regeneration, land reclamation 490.6
Powergen Private Power generation 373.3
BP Oil ŽUK. Private Petrol stations 362.7
HBG Construction Private Property development 356.1
Chelsfield Private Property development 328.7
Sainsbury Private Supermarkets 320.2
Basingstoke and Deane District Local government Housing renewal 304.8
Council
Severn Trent Private Water services 296.9
North of Scotland Water Private Water services 278.6
LG ŽLucky Goldstar. Private Microprocessor factory 267.0
Land Securities Private Property development 252.0
Cardiff County Council Local government Cardiff Bay barrage and land reclamation 251.2
West of Scotland Water Private Water services 238.5
Manchester City Council Local government Urban regeneration 225.6
BNFL Public Nuclear fuels processing plant 216.0
Transco Private Gas pipelines 215.0
United Utilities Private Power generation, water services 211.9
Southern Water Private Power generation 210.6
Home Office Central government Prisons 205.5
Scottish Power Private Power generation 202.0
Yorkshire Water Private Water services 200.9
Measured by average monthly value of outstanding contracts for the 24 months to March 2000. Excludes pure engineering work.
Source: derived from Glenigan construction contracts data.
complex or uncertain, or need to be completed rapidly Many important clients involved in procuring
— it becomes much harder to coordinate the large complex construction projects now hold the view
number of specialist participants that are often in- that that the current framework for managing the
volved. Under these circumstances construction tends construction process is inadequate. These clients have
to resemble a prototyping process, whereby project increasingly turned to ‘partnering’ as a strategy for
ends and means are continuously negotiated by the project management. In doing so, they have found
various parties involved ŽHowell et al., 1996.. This that short-term project performance has often im-
tends to blur the traditional boundaries between con- proved considerably and, furthermore, the approach
struction phases and activities, requiring more com- has resulted in technical and business process inno-
plicated, non-hierarchical organisational structures. vation.
As in typical CoPS projects, in this situation it The rising practical interest in construction indus-
becomes essential to establish tools and techniques try partnering mirrors the attention paid in organisa-
for achieving rapid integration of the necessary tional theory to forms of ‘hybrid’ or ‘ virtual’ enter-
knowledge and skills possessed by participating or- prise ŽMiles and Snow 1987; Powell 1990;
ganisations, and mastery of the interfaces between Thompson et al., 1991; Williamson 1993.; in institu-
various subsystems. tional economics to uncertainty-reducing arrange-
J. Barlowr Research Policy 29 (2000) 973–989 977
ments such as obligational contracting and supply underlying rationale is that influence on final project
agreements ŽWilliamson 1975; Kregel 1980; Hodg- outcomes is greatest in the earliest phases of a
son 1988; Imrie and Morris 1992.; or in manufactur- project and problem resolution is easier where there
ing logistics to lean and agile supply chains ŽNaylor is closer and early involvement of all parties. Part-
et al. 1999.. nering essentially represents an attempt to reconceive
the construction process, moving towards the bottom
of Fig. 1 but maintaining the best elements of tradi-
4. Structures and strategies for managing com- tional approaches.
plex construction projects The critical feature defining partnering is the ex-
tent to which the arrangements attempt to facilitate
There is nothing new about collaborative arrange- an improvement on both sides of the client–supplier
ments between firms in the construction industry — interface. Although the transactions between parties
this has long been the industry’s pattern of day-to-day are still governed by commercial contracts, more
trading relationships. Partnering, as a new approach important for success is the way in which the Õalues
to collaboration, emerged in the UK construction and objectiÕes held by each party are accommodated
industry during the late-1980s in the offshore oil and to ensure that no one set dominates the outcome of
gas sector, although some major supermarket chains the project. Genuinely performance-enhancing rela-
had also been involved in informal long-term con- tionships frequently involve clients, contractors and
struction industry relationships. other suppliers engaging in some form of collabora-
Broadly, partnering is a generic term embracing a tive arrangement, which involves sharing the benefits
range of different business processes designed to of partnering ŽBarlow et al., 1997.. We return to this
enhance collaboration Žsee Barlow et al., 1997.. The point below.
The reasons for partnering have tended to vary ŽBennett and Jayes, 1998.. These ‘second genera-
from sector to sector, depending on the extent to tion’ partnering relationships, involving companies
which there has been a perceived need to move from that have already been through the learning curve,
traditional approaches to construction procurement also provided their participants with more stable
ŽFig. 2.. For instance, supermarket chains have pro- workloads, improved flexibility, faster project start-
gressed from informal long-term relationships in or- up, the elimination of defects, innovation and better
der to outsource their non-core construction activi- design. Some ‘third generation’ partnering relation-
ties, through more formalised arrangements Žperhaps ships, where participants have undergone fundamen-
with an agreed pool of suppliers. to improve con- tal changes to attitudes, organisation and technology,
struction performance, to full partnering relation- demonstrate even greater benefits — 80% time sav-
ships. Because the construction of supermarkets is ings and 50% cost savings. Underlying these perfor-
now highly efficient, partnering for these clients mance gains are the beneficial effects of improved
tends to be for ‘soft’ reasons, such as ensuring their communications on problem resolution, the develop-
suppliers represent the supermarket’s brand and pub- ment of inter-organisational and inter-personal trust,
lic image effectively ŽBarlow et al., 1997.. Other and the promotion of an innovation culture.
types of construction client have begun to partner at
different times and for different reasons.
Despite slow adoption of partnering in some con- 5. Partnering, innovation and organisational
struction sectors, recent evaluations show that im- learning in construction CoPS
proved construction performance — in some cases,
greatly improved performance — is possible. Ac- The management of innovation in CoPS is com-
cording to one study of 200 examples, the most plicated by the discontinuous nature of their project
sophisticated partnering agreements produced time based production processes. These often involve bro-
savings of more than 50% and cost savings of 40% ken learning and feedback loops, in an environment
J. Barlowr Research Policy 29 (2000) 973–989 979
where the architecture of the production system may 1991.. Moreover, as Kogut and Zander Ž1992. have
fluctuate with the changing shape of the project argued, the transferability of knowledge between
ŽGann and Salter, 1998.. A further factor complicat- organisations is shaped by the degree to which it can
ing the inter-organisational transfer of knowledge is be codified — structured according to a set of easily
the number of suppliers, each of which may be communicated identifiable rules — and its complex-
highly specialist, and complexity of networks they ity. Knowledge that is readily codifiable and simple
are involved in. Moreover, project-based firms often is more easily transferred than knowledge that is
have only patchy knowledge of their own portfolio embedded in the culture and work principles of an
of projects, relying on informal channels of commu- organisation. Successfully transferring embedded
nication between project groups as the principal forms of knowledge between or within firms is most
source of information on their activities. The flow of effective in a longer term relationship, since these
knowledge and innovation between organisations thus are more likely to promote the emergence of shared
needs to be managed in a context of short-term, coding systems.
discrete supply networks, necessitating capabilities in Simply transferring knowledge is insufficient for
coordination and integration across organisations. innovation to occur in a partnering relationship —
Partnering, with its emphasis on communications, organisations need to be able to recognise the value
risk and reward sharing and the development of trust of knowledge and apply it strategically. Three further
between organisations would appear to be ideally features need to be in place to take full advantage of
suited to this requirement. knowledge transfer. First, as Cohen and Levinthal
There is indeed considerable evidence from other Ž1991. have noted, the ‘absorptive capacity’ of an
industries that collaborative relationships help to pro- organisation depends in part on the ways in which
mote product and process innovation Žsee Shaw, knowledge is retained and distributed. This suggests
1994, and other papers in Dodgson and Rothwell, that as well as the turnover of staff, an organisation’s
1994., and interest has grown in the construction internal and external communications structure, and
industry in the possibility that partnering can aid the its political and cultural environments ŽKanter, 1990;
transfer of knowledge between firms. According to Schein, 1985., are important influences. Second, the
Provost and Lipscomb Ž1989., partnering provides presence of ‘champions’ — central figures helping
companies with an environment, which allows them to nurture and implement the partnering process —
to refine and develop new competencies in a more may well be crucial in promoting and distributing an
controlled and lower risk way. A continuity of per- organisational ‘memory’ of the lessons learned from
sonnel from project to project in long-term partner- partnering experiences. Finally, organisations try to
ing relationships may therefore provide organisa- routinise their ongoing and repetitive business pro-
tional learning benefits ŽBaker 1990; CII 1991.. cesses because routines can stimulate innovation and
Clearly the regular use of external organisations provide opportunities for sustained process improve-
with different knowledge bases is potentially benefi- ments ŽGann and Salter, 1998.. Project processes,
cial. However, the mere existence of a partnering which tend to be temporary and unique, do not lend
relationship is not in itself sufficient to result in themselves to standardisation and economies of scale.
cross-organisational knowledge transfer ŽBarlow et Success for project-based firms thus requires the
al. 1998.. The degree to which this will occur is integration of project experiences with continuous
influenced by several factors, which partly relate to business processes. There is, however, often a gap
the objectives of each partner and partly to the type between the rational project development practices
of knowledge, which may be transferred. Both these Ži.e., an organisation’s procedural routines. and ac-
factors are, in turn, affected by the nature of intra- tual development practices, as designers and engi-
and inter-organisational communications and organi- neers respond to unexpected events. Attempts to
sational culture. There may for example be inherent impose rigid formal procedures may force practition-
tensions and conflicts between clients and suppliers ers to mask their real activities and drive them
if each are driven in different directions due to the underground, reinforcing and further widening the
nature of the competitive environments ŽMintzberg, gap ŽHobday and Brady, 1998..
980 J. Barlowr Research Policy 29 (2000) 973–989
6. Partnering and the offshore sector — the that focusing on the nature of their relationships with
British Petroleum (BP) Andrew Alliance suppliers and contractors could offer the possibility
of doing so.
The offshore oil and gas industry has absorbed Much of this early development work on Andrew
between a fifth and a quarter of the UK’s total was subsequently reinforced by, and fed into, the
industrial investment in most years since mid-1970s government- and industry-sponsored Cost Reduction
ŽDTI, 1995.. The industry can be seen as an example in the New Era ŽCRINE. initiative, which was pro-
of CoPS. Investment involves the development of moting new approaches to offshore procurement and
highly technologically complex infrastructure for the a radical change in contracting customs. This in-
exploitation of subsea oilfields. Because the operat- volved the promotion of contractual relationships
ing conditions on each field are unique and continue with smaller numbers of integrated service providers
to change over its life, these products are highly or alliances of firms providing these services. One
customised and demand continuous technological and emerging approach was to replace traditional forms
organisational innovation over a lifecycle of 25 years of contractual relationship with risk and reward shar-
or more ŽBower and Young, 1995; Bower et al., ing arrangements, whereby the benefits from innova-
1996.. There are, however, problems in managing tion and performance improvement are shared be-
innovation and sustaining organisational learning in tween project participants. CRINE made a number of
the offshore sector because of the nature of its recommendations, which the Andrew team felt should
supply chains. be addressed:
Despite the high degree of vertical integration of
the oil companies, aspects of exploration, design, Ø Improving the relationship between the operator
construction and the operation of oilfields have long and contractors is a key element in reducing
been contracted out. During the early 1990s the oil project cost.
companies outsourced many activities and cut jobs. Ø Common objectives for all project parties are
Many smaller specialist product and service suppli- more important than individual objectives.
ers were faced with the loss of previous communica- Ø There is a need to remove the adversarial climate
tion channels with the oil companies, becoming more prevailing in the UK’s offshore industry.
reliant on their relationships with the prime contrac-
tors ŽBower et al., 1996.. These supply a wide range BP’s aim in using partnering was to use smaller,
of services from in-house capability and subcontract- more closely integrated project teams to substantially
ing relationships, but most were relatively inexperi- reduce the cost and time of delivering field facilities,
enced in managing innovation, either internally or in without compromising quality, safety or environmen-
collaboration. In contrast, although there are several tal performance. Table 3 lists the principal project
thousand specialist firms subcontracting and supply- targets and Table 4 indicates the individual elements
ing to the offshore industry, perhaps 250 are ac- of the target cost saving. The Andrew Alliance was
knowledged to be leaders in the provision of techno-
logical innovation to the industry. There is a high
degree of geographical clustering in this sector, and Table 3
informal communication between them is extensive Andrew targets at project sanctioning
ŽBower et al., 1996.. Andrew Industry benchmark
The Andrew oil field was discovered by BP in Cost Ž1993 £. 373 450
1974, but until 1990, it was economically marginal Platform rig 1800 2000
because of the unfavourable balance between the weight Žtonnes.
prevailing oil price and development costs. These Topside 10 20
were escalating under traditional procurement ap- installation time
Žman-hoursrtonne.
proaches. The Andrew team realised that technologi- Development 33 ca.50–60
cal innovation alone would be insufficient to sub- time to first oil
stantially reduce construction costs and postulated
J. Barlowr Research Policy 29 (2000) 973–989 981
Table 5
Andrew Alliance partners
Function Firm Riskrprofitability
share Ž%.
Project management, BP 46
operational management,
commercial management and
external coordination
Design, procurement, Brown Root 22
and project management
support
Integrated deck Trafalgar House Offshore Fabricators Ltd. 12
fabrication
Jacket fabrication Highland Fabricators Ltd. 6
Export pipelines Allseas Engineering 4
Transportation and Saipem UK Ltd. 6
installation
Drilling design and Santa Fe Ltd. 3
fabrication
Accommodation Emtunga AB 1
design and fabrication
982 J. Barlowr Research Policy 29 (2000) 973–989
work and incorporated the actual contractual con- breakthrough in construction and engineering pro-
trols, gave the client the option of continuing the curement. The headline benefits for BP and its Al-
project in a conventional way if the Alliance Agree- liance partners were certainly striking, as follows.
ment failed. Ø The cost of the Andrew development, using
The Alliance Agreement included a gain sharing traditional procurement practices, had been estimated
mechanism. Under this the partners agreed a target at £450 million and the agreed target delivery cost
cost Ž£373 million at 1993 prices.. If the project cost was £373 million Žin 1993 prices.. The final out-turn
more than the target, Alliance members Žincluding cost of the platform was £290 million. This resulted
BP. were liable for a share of the overrun up to an in a £45 million bonus to be split between the seven
overall limit of £50 million. Conversely, if the pro- partners ŽMorby 1996..
ject was completed within the original estimate, the Ø The initial target was for the first oil to be
Alliance members would received a share of the extracted in January 1997. Partly because the amount
saving. The risk and reward exposure for each mem- of work completed on-shore allowed the time for
ber was determined by the financial amount they ‘hook-up’ Žconnecting the topside structure to the
were willing to put at risk and approximately re- subsea jacket. to be dramatically reduced, this was
flected their ability to influence the final project achieved 6 months ahead of plan. The best in class
outcome ŽTable 5.. The gain sharing mechanism performance for hook-up was twenty man-hours per
essentially prevented contractors from making money tonne, although the range was up to 140 man-hours
out of alterations, as all Alliance members stood to per tonne. The Andrew hook-up target at project
make or lose money collectively. A major break sanctioning was 10 man-hours per tonne, but the
from tradition was that completion for the purposes team actually achieved one man-hour per tonne.
of triggering gain sharing was defined such that the This reduced hook-up and commissioning costs by
client was delivered with a working facility. 75%.
The objectives of the IMT were to manage the Ø There were no disputes in the Andrew project.
project under the leadership of the BP project manger, The strength of the Alliance and its gain sharing
monitor project progress, address key issues impact- mechanism allowed members to deal collectively
ing on the schedule and cost, provide a structured with potential serious unexpected problems Že.g.,
forum for communication and interface management, exposure to an additional cost of $7 m within a few
and encourage innovation and cost saving opportuni- months of the project starting because of the failure
ties. The IMT adopted a policy of no ‘policing’ of of a subcontractor..
the fabricators — accountability was given to those Ø Accident rates were halved compared to con-
who were contractually accountable and there was ventional offshore commissioning programmes be-
no BP team based at each site directly checking the cause virtually 100% of the topside was completed
quality of work. A ‘project controls group’ was also on land, allowing the operation teams to practice the
established to provide a central resource capable of hook-up and carry out fully integrated emergency
supporting all Alliance members without duplication exercises.
of effort. Each member used its own in-house system Underlying these headline outcomes, however,
to control its activity, but electronic transfer of data were numerous technical and business process inno-
and a comprehensive project database, accessible by vations. These partly stemmed from more efficient
all members, were introduced. working during the design and construction phases
of the project and completion of as much work as
possible on-shore. All the contractors were able to
generate novel approaches to the design and installa-
tion of the platform.
7. The Andrew Alliance outcomes
Ø Early involvement by Highland Fabricators,
building the jacket, resulted in 200 fewer design
The Andrew project has been heralded within the drawings and allowed design concepts to be re-
offshore and construction industries as a major viewed to optimise those which were less expensive
J. Barlowr Research Policy 29 (2000) 973–989 983
and best-suited to its fabrication facilities. A redesign ing and distributing that knowledge were felt to have
of the jacket allowed a reduction in the number of been limited. Organisational learning in the Andrew
piles from 16 to 12, saving £1.8 million. Highland Alliance took a number of forms ŽBarlow et al.,
Fabricators were also able to delay its original start 1998.. ‘Vicarious learning’ ŽDutton and Freedman,
date for jacket fabrication by 7 months, creating a 1985. — where organisations acquire second-hand
deferred expenditure of £10 million to save on fi- knowledge and experience — was evident, particu-
nancing costs. larly at the interfaces between contractors, subcon-
Ø The fact that the drilling company ŽSanta Fe. tractors and suppliers. ‘Team learning’ was also
was part of the Alliance from the start meant that evident, once a critical mass of individuals already
equipment could be selected and design requirements committed to the project had been achieved. This
reviewed to ensure that the rig’s functional specifica- was underpinned by the emergence of trust in indi-
tion was tailored to meet the drilling needs of the viduals and the strong commitment to partnering.
project. Finally, ‘individual learning’ was promoted within
Ø Emtunga Žwhich built the accommodation unit. BP and the other Alliance members. The ‘fear of
reported that early participation allowed it to have a failure’ was removed and project members were
greater choice in materials and more influence over more inclined to propose ideas and processes that
the design and location of the unit. once would have been looked on as being too risky.
Ø Allseas was able to reduce the pipeline size by As one manager put it, ‘ . . . it’s OK to make a
20% and influence the pipeline connections to save mistake, ‘fail’, because that’s the best learning’.
steel and welding costs. The installation date of the
pipeline was also rescheduled when the price of oil
fell, to bring forward the date for first oil.
Ø Saipem saved the Alliance £700,000 by elimi-
8. Explaining the benefits — partnering vs. con-
nating the need for water-tight diaphragms inside the
textual changes
jacket legs and also developed an approach for plat-
form hook-up, which saved 36 hours welding time.
Considerable emphasis was also placed on lifecy- What was the role of partnering in achieving the
cle cost planning. This was possible because Brown performance benefits in the Andrew project? As well
& Root was able to collaborate with other Alliance as the familiar difficulties in interpreting opinions
members and their suppliers to develop a simplified presented in interviews, there can be problems in
facilities design system. For example, a single inte- disentangling the specific outcomes of partnering.
grated system for process control, monitoring and This is because a typical partnering relationship in-
emergency response was developed, rather than us- volves a large number of simultaneous business pro-
ing three separate systems. cesses and the organisations engaged in partnering
As well as these immediate benefits arising from often have a wide variety of objectives, which some-
innovative ideas, many involved in the Andrew Al- times change over time. It is necessary to separate
liance felt that the partnering approach had helped to the role played by the processes involved in partner-
promote creativity by encouraging staff to come-up ing, rather than wider contextual factors.
with new ideas. Even though attempts to harness the We argued above that the mere existence of a
ideas of Andrew’s project staff involved nothing partnering relationship is not in itself sufficient for
more than a paper-based suggestion scheme, subse- innovation or the transfer of knowledge between
quently BP began to develop IT-based systems to organisations — these need an element of ‘absorp-
identify the relevant knowledge held by individuals tive capacity’. This, in turn, depends on the internal
and track the information required by project person- and external communications structures of an organi-
nel ŽHoulder, 1997.. sation, the presence of ‘champions’ who are able to
While it was recognised that there had been or- harness knowledge and promote change, and the
ganisational learning under previous approaches to integration of project experiences with routine busi-
construction procurement, the mechanisms for retain- ness processes.
984 J. Barlowr Research Policy 29 (2000) 973–989
Within the Andrew Alliance considerable empha- or ways of working were not penalised if they did
sis was placed on creating a single team without not succeed. The culture of collaboration, under-
duplication of functions or accountabilities. This pinned by the gain sharing mechanism, allowed peo-
meant that more formalised, hierarchical systems of ple to question ways of working without fear of
communications were broken down, resulting a flat- penalty if they were unsuccessful. The perception
ter structure. There was a high level of face-to-face that participants were all striving to achieve a greater
communication because Alliance members shared understanding of each other’s goals meant they could
the same office building, and the presence of inte- break from the confines of the contract and work
grated design and project management systems and specification.
video links with the various manufacturing and as- The importance of the Alliance Agreement and
sembly sites. Direct communications between project gain sharing mechanism in this process cannot be
members was actively encouraged. As well as com- under-emphasised. Essentially, this removed the re-
pressing the flow of information and provide speed- strictions common to standard contractual proce-
ier decision-making or problem solving, this helped dures, whereby communication are obliged to go
to promote a culture within which greater collabora- through a prescribed chain of command, and helped
tion and trust could grow. to break down adversarial behaviour and language.
The second pillar of the partnering process in the Even though contractors were principally paid on a
Andrew Alliance was the considerable effort made at reimbursable basis, total reward was tied to final
teambuilding. BP had management consultants work- project outcome and the gain sharing mechanism
ing on improving the company from the early 1990s therefore undermined the traditional cost-plus way of
and these were put to work on the Andrew Alliance. pricing work. This approach was felt to restrict new
The objectives were to ensure people were commit- approaches since it could result in innovations, which
ted to delivering ‘exceptional results’ and provide reduced contractors’ time input and therefore, their
them with appropriate tools for achieving this goal. remuneration.
Teambuilding was based around a nucleus of people, Although they were not part of the formal Al-
which was sufficiently large in mass to influence the liance, efforts were also made to ensure that partner-
rest of the project. There was a variety of approaches ing principles flowed to suppliers further down sup-
to teambuilding and a great deal of time and money ply chain. Focusing on non-adversarial supply chain
was spent in integrating project members. Induction relationships saved 17% on product manufacturing
workshops to explain the aims and objectives of the costs. Furthermore, harnessing the knowledge resid-
Alliance, and its modus operandi, were run for all ing in suppliers was seen by many as a critical factor
new members when they joined. Although the size of behind the development of new ideas in the Andrew
the project meant that no single individual was re- Alliance.
sponsible for ‘championing’ the partnering concept, Not all the observable performance gains in the
key individuals emerged at critical project stages of Andrew Alliance could be ascribed to the partnering
the project. These were supported by BP’s Chief process alone, though. Two other factors need to be
Executive, who identified partnering as a strategic considered. First, the contribution by other parts of
goal. Each of the main partners had an identifiable BP’s Andrew team — outside the Alliance team
individual providing support and selling the idea to itself — was critical in making the field an eco-
senior executives within their own organisation. nomic prospect for example by:
Arguably, the higher levels of trust emerging
from these features of the partnering process led to
measurable financial savings, as well as promoting
innovative thinking. Trafalgar House noted how, for Ø developing an appropriate reservoir depletion
example, trust meant there was no need for a resident plan, in which associated gas was exploited both
BP team at the construction yard, which would have from a reservoir management and a commercial
been the case under a traditional relationship. This perspective;
saved about £3 million in staff time. Innovative ideas Ø proposing the use of horizontal wells.
J. Barlowr Research Policy 29 (2000) 973–989 985
Second, the importance of the context within ing performance. Unlike the early days of partnering
which partnering occurs was identified in Barlow et in the onshore construction sector, there seems to
al. Ž1997..2 Arguably, the market power of clients in have been a better understanding of the need to
the early 1990s — a time of deep recession in the introduce approaches, which lead to mutual im-
UK construction industry — played a part in the provement through the entire supply chain. The de-
headline gains noted in early partnering arrange- velopment and introduction of gain sharing mecha-
ments, since clients were able to impose tough per- nisms — long before other parts of the construction
formance improvement targets. The large number of industry — is a demonstration of this.
competing contractors and suppliers also provided Along with market structure and conditions, an-
clients with a strong negotiating position during the other contextual factor, which helps to explain the
early 1990s. dramatic outcomes of the Andrew Alliance was the
The market context for the Andrew Alliance was evolution of construction and engineering technology
somewhat different from the mainstream UK con- during the course of the project. While it was ac-
struction sector at that time. Key drivers for the knowledged by the Andrew team that technological
introduction of partnering in the offshore industry improvements on their own would be insufficient to
were the decline in oil prices — 1990 prices were deliver the desired project outcomes, the ability of all
less than half those of 1980 in real terms — and partners to benefit through the Alliance gain sharing
escalating development and production costs. Like mechanism encouraged a willingness to adopt new
onshore construction, however, there was virtually technological developments. Some of these were not
no standardisation of components — most operators necessarily new. For example, improved lifting ca-
had their own company, or even oilfield, specifica- pacity of barges had been a feature of the offshore
tions for large ranges of components. Also similar industry since the late 1980s, but in the case of
were the fragmentation of the supply chain and Andrew, this was coupled with an approach, which
limited understanding of value flows. For BP, 53% led Alliance members to seek ways of maximising
of its North Sea expenditure Žtotalling $3 billion in the onshore completion and commissioning of the
1993. was spent with third parties. This was spread topside structure.
amongst 4200 suppliers and contractors, 70% of Other technology developments affected the qual-
which accounted for 0.5% of expenditure. Third-party ity and performance of steel, and welding processes.
costs were escalating and BP had little idea of value This allowed a reduction in the number of jacket
added within the supply chain as its principal focus piles, saving £2 million. Improvements in IT were
was on price, construction and delivery time, and also important; in particular, a new interactive 3D
inspection and testing costs. Moreover, although BP CAD system for structural steel work, which allowed
— and other oil companies — were not unaware of a stage in the design modelling and drafting process
the costs associated with re-design, delivery and to be skipped, leading to further time and cost sav-
start-up delays, debugging, poor plant layout and ings. Additional IT developments included improved
ongoing maintenance, what was not known was how software for pipeline design and computer modeling
to influence them. to allow the project team to work from a single set of
Given this context, it is perhaps unsurprising that drawings.
partnering should emerge as an approach for improv- To make best use of these technology changes
and to adopt new ideas required, however, a high
degree of collaborative working and trust between
2
Bennett and Jayes Ž1998. also note how an Esso partnership partners. In all these instances, the cultural and or-
to create a standard, modular service station shop for outlets ganisational context interacted with changes in the
across Europe led to uneven time and cost savings — between available technologies to produce innovative tech-
1994 and 1997, costs fell by 50–60% in Germany and Switzer-
land, 15–25% in the UK, France and Benelux, while in Finland
niques. In the Andrew Alliance, this completely
and Italy, Esso has failed to achieve anything more than minor changed the economics of the scheme and allowed a
savings. project that had marginal chances to succeed.
986 J. Barlowr Research Policy 29 (2000) 973–989
ers to performance improvement in situations where ments on an earlier draft of the paper. The normal
there is a need to integrate organisations with differ- disclaimers apply.
ent objectives and knowledge bases. It is, however,
important to understand the role played by context in
influencing the way the largely generic processes Appendix A. Research method
comprising partnering are introduced and imple-
mented. Partnering has had a variable impact within The research on the Andrew Alliance was carried
construction, with perhaps the greatest project per- out as part of an ESRC-funded study of the organisa-
formance and longer term innovation and learning tional and managerial processes involved in con-
benefits being seen in the CoPS sectors of the indus- struction industry partnering. The research involved
try. While partnering has been used to great effect in a major review of current research on partnering and
more routine and repetitive areas, notably the con- literature on relevant economic and organisation the-
struction of hotels, supermarkets and drive-through ory; background interviews with key organisations
restaurants, it has had only limited impact in house- and firms involved in partnering; and five case stud-
building. This remains deeply traditional and dis- ies of existing and emerging partnering arrange-
plays a serious lack of technical and process innova- ments. Over 40 companies were involved in these
tion because of a variety of cultural, economic and case studies, which were chosen to represent differ-
regulatory barriers ŽBarlow, 1999.. ent types of partnering and different construction
Parts of the construction industry have become sectors Žsee Barlow et al., 1997 for details.. A series
increasingly similar to other CoPS sectors and clients of semi-structured interviews with key staff in as
are growing more demanding. Although the need to many of the companies involved in the partnerships
improve the client–contractor briefing process has as possible was conducted. There were only 2 re-
long been recognised as a factor behind performance fusals, out of 36 partners which were approached. In
improvement, this is no longer sufficient. The ability total, 75 interviews were conducted. Twenty of the
to manage value and knowledge flows across the interviews were taped and transcribed, and written
boundaries of firms is necessary for the successful notes were taken in the remainder.
delivery of construction CoPS, suggesting that ap- All the case study interviewees were involved in
propriate tools and techniques for integrating supply setting-up andror managing the partnering arrange-
chain members are critical. This is turn calls for new ments. In some instances staff were interviewed
criteria for competency in the construction industry, more than once. Interviews tended to last between 1
notably an ability to offer a customer-focused service and 2 hours and broadly examined the direction of,
rather than one which merely reflects the clients’ and motives for, the particular strategies that had
perceived needs. It remains to be seen whether the been adopted, and their experience of the specific
UK construction industry — in its current guise — partnering relationship. The areas covered in each
is capable of meeting these new criteria. interview depended on the particular role of the
interviewee, but in general the following questions
were explored:
Acknowledgements
Ø how partners were selected;
Parts of this paper are based on research carried Ø the extent to which, and how, members ‘bought
out for a project on construction industry partnering into’ the partnering aims and objectives;
funded within the Economic and Social Research Ø the degree of commitment at different levels of
Council’s Innovation Programme. The project was management;
carried out by James Barlow, Michael Cohen, Ashok Ø how agreements on performance targets and risk
Jashapara and Yvonne Simpson. We are grateful to sharing were arrived at;
the Andrew Alliance companies and their members Ø the level and nature of teamwork, trust and open-
for their help and time. We also thank Bob Scott, ness;
Virginia Acha and two anonymous referees for com- Ø the way conflicting objectives were approached;
988 J. Barlowr Research Policy 29 (2000) 973–989
Ø the techniques for: financial controlrmonitoring, Barlow, J., Jashapara, M., Cohen, M., 1998. Organisational learn-
progress controlrreporting, quality control; ing and inter-firm partnering in the UK construction industry.
The Learning Organization Journal 5 Ž2., 86–98.
Ø the expectations of each partner in terms of pro- Barratt, P., Hudson, J., Stanley, C., 1996. Is briefing innovation?
ductivity and quality improvements, human re- In: Langford, D., Retik, A. ŽEds.., The Organization and
sources and training; Management of Construction. Shaping Theory and Practice
Ø key decisions and events, and ways personnel vol. 3 E & FN Spon, London, pp. 87–95.
adjusted to change by making trade-offs or re- Bennett, J., Jayes, S., 1998. The Seven Pillars of Partnering.
Thomas Telford, London.
structuring work relationships. Bower, J., Young, A., 1995. Influences on technology strategy in
the UK oil and gas related industry network. Technology
In each case study, interviewees’ responses to Analysis and Strategic Management 7 Ž4., 407–415.
identical questions were compared to highlight dif- Bower, J., Crabtree, E., Keogh, W., 1996. Rhetorics and realities
fering perspectives on the outcomes of the partnering in new product development. Groningen, UMIST, Delft Work-
shop, 24–27 April, Delft, Netherlands.
process. In addition, documentary material generated
Buckley, P., Enderwick, P., 1989. Manpower management. In:
by the partners was evaluated and compared with the Hillebrandt, P., Cannon, J. ŽEds.., The Management of Con-
interview material. Finally, reports of each case study struction Firms. MacMillan, London.
were sent to interviewees for validation. CIBrBuilding, 1999. Improving the Performance of the Construc-
For the Andrew Alliance case study, 20 inter- tion Industry. Construction Industry Board and Building, Lon-
don.
views were carried out with representatives from all
CII, 1991. Search of Partnering Excellence. Construction Industry
the member companies, together with a representa- Institute, Univ. of Texas, Austin, TX.
tive from the independent teambuilding facilitators. Cohen, W., Levinthal, D., 1990. Absorptive capacity: a new
The research was carried out in ‘real-time’ Žlate perspective on learning and innovation. Administrative Sci-
1995 to mid-1996., during the second half of the ence Quarterly 35, 128–152.
Construction Taskforce, 1998. Rethinking Construction. HMSO,
Andrew construction programme. A follow-up meet-
London.
ing was held with a senior BP representative in 1999 Dodgson, M., Rothwell, R. ŽEds.., The Handbook of Industrial
to seek views on the Andrew project over 2 years Innovation. Edward Elgar, London.
since its completion. In addition, an initial draft of DoE and British Telecom, 1995. Construction IT. Bridging the
the paper was sent to a former member of the Gap ŽDepartment of the Environment Construction Sponsor-
ship Directorate, London..
Andrew Alliance for comment.
DTI, 1995. The Energy Report, vol. 2, April ŽDepartment of
Trade and Industry, London..
Dulami, M., Baxendale, A., Jewell, M., 1996. Refocusing con-
References struction to meet customers’ requirements. In: Langford, D.,
Retik, A. ŽEds.., The Organization and Management of Con-
Alsagoff, A., McDermott, P., 1994. Relational contracting: a struction. Shaping Theory and Practice vol. 1 E & FN Spon,
prognosis for the UK construction industry. Proceedings of London, pp. 187–196.
CIB W92 Procurement Systems — East Meets West Univer- Dutton, J., Freedman, R., 1985. External environment and internal
sity of Hong Kong. strategies: calculating, experimenting, and imitating in organi-
Anumba, C., Kamara, J., Evbuomwan, N., 1996. Encapsulating zations. In: Lamb, R., Shrivastava, P. ŽEds.., Advances in
the ‘ voice of the customer’ in construction projects. 12th Strategic Management vol. 3 JAI Press, Greenwich, CN,
Annual ARCOM Conference, 11-13 September, Conference U.S.A.
Proceedings vol. 1. Eccles, R., 1981. The quasi-firm in the construction industry.
Baker, S., 1990. Partnering: contracting for the future. Cost Journal of Economic Behaviour and Organisation 2, 335–357.
Engineering 32 Ž4., 7–12. Gameson, R., 1996. Client–professional communication during
Bakshi, A., 1995. Alliance changes economics of Andrew Field the early stages of project development. In: Langford, D.,
development. Offshore 55 Ž1.. Retik, A. ŽEds.., The Organization and Management of Con-
Barlow, J., 1999. From craft production to mass customisation. struction. Shaping Theory and Practice vol. 2 E & FN Spon,
Innovation requirements for the UK housebuilding industry. London, pp. 437–446.
Housing Studies 14 Ž1., 23–42. Gann, D., Salter, A., 1998. Learning and innovation management
Barlow, J., Jashapara, M., Cohen, M., Simpson, Y., 1997. To- in project-based, service-enhanced firms. International Journal
wards Positive Partnering. Revealing the Realities in the Con- of Innovation Management 2 Ž4..
struction Industry. Policy Press, Bristol. Hancock, M., Yap, C., Root, D., 1996. Human resource develop-
J. Barlowr Research Policy 29 (2000) 973–989 989
ment in large construction companies. In: Langford, D., Retik, Mintzberg, H., 1991. The effective organisation: forces and forms.
A. ŽEds.., The Organization and Management of Construction. Sloan Management Review 32 Ž2., 54–67.
Shaping Theory and Practice vol. 2 E & FN Spon, London, Mohamed, S., Tucker, S., 1996. Options for applying BPR in the
pp. 312–321. Australian construction industry. International Journal of Pro-
Higgin, J., Jessop, W., 1963. Communication in the Building ject Management 14 Ž6., 379–385.
Industry. Tavistock Publications, London. Morby, A., 1996. N. Sea platform team reaps a £45 m bonus.
HMSO, 1990. Professional Liability Study Team Report. HMSO, Construction News 20.
London. MPBW ŽMinistry of Public Buildings and Works., 1964. The
Hobday, M., 1998. Product complexity, innovation and industrial Placing and Management of Contracts for Building and Civil
organisation. Research Policy 26, 688–710. Engineering Work. HMSO, London.
Hobday, M., Brady, T., 1998. Rational versus soft management in Naylor, J., Ben, N., Mohamed, M., Berry, D., 1999. ‘Leagility’:
complex software: lessons from flight simulation. International integrating the lean and agile manufacturing paradigms in the
Journal of Innovation Management 2 Ž1., 1–43. total supply chain. Special Issue of International Journal of
Houlder, V., 1997. Far-flung workers find it’s good to talk. Production Economics, Design and Implementation of Agile
Financial Times 9, 27. Manufacturing Systems 62, 107–118.
Howell, G., Miles, R., Fehlig, C., Ballard, G., 1996. Beyond NEDO ŽNational Economic Development Office., 1974. Before
partnering: toward a new approach to project management. You Build. What a Client Needs to Know About the Construc-
Proceedings of the 4th Annual Conference of the International tion Industry. HMSO, London.
Group for Lean Construction. University of Birmingham. NEDO, 1991. Partnering: Contract without Conflict. National
Hodgson, G., 1988. Economics and Institutions. Polity Press, Economic Development Office, London.
Cambridge. O’Reilly, J., 1973, A case study of a design commission. Prob-
Imrie, R., Morris, J., 1992. A review of recent changes in lems highlighted; initiatives proposed. Building Research Es-
buyer-supplier relations. OMEGA International Journal of tablishment Current Paper CP34r69 ŽBuilding Research Sta-
Management Science 20 Ž5r6., 641–652. tion, Watford..
Kanter, R., 1990. When Giants Learn to Dance. Unwin Hyman, Powell, W., 1990. Neither market nor hierarchy; network forms of
London. organisation. In: Staw, B., Cummings, L. ŽEds.., Research in
Kogut, B., Zander, U., 1992. Knowledge of the firm, combinative Organisational Behaviour vol. 12 JAI Press, Greenwich, CT.
capabilities and the replication of technology. Organization Provost, R., Lipscomb, R., 1989. Partnering: a case study. Hydro-
Science 3 Ž3., 383–397. carbon Processing, 48–51.
Kregel, J., 1980. Markets and institutions as features of a capitalis- Schein, E., 1985. Coming to a new awareness of organizational
tic production system. Journal of Post-Keynesian Economics 3 culture. Sloan Management Review 25 Ž2., 3–16.
Ž1., 32–48. Shaw, B., 1994. Userrsupplier links and innovation. In: Dodgson,
Kubal, M., 1994. Engineered Quality in Construction, Partnering M., Rothwell, R. ŽEds.., The Handbook of Industrial Innova-
and TQM. McGraw-Hill, New York. tion. Edward Elgar, London.
Latham, Sir M., 1994. Constructing the Team. HMSO, London. Thompson, G., Frances, J., Levacic, R., Mitchell, J. ŽEds.., Mar-
McDermott, P., Green, C., 1996. An inside-out approach to kets, Hierarchies and Networks. The Coordination of Social
partnering. Partnering in Construction. Proceedings of a One- Life. Sage, London.
Day Conference ŽUniversity of Westminster and University of Williamson, O., 1975. Markets and Hierarchies. Free Press, New
Salford, London and Manchester.. York.
Miles, R., Snow, C., 1987. Network organisations: new concepts Williamson, O., 1993. Transaction cost economics and organisa-
for new forms. California Management Review 28, 62–73. tional theory. Industrial and Corporate Change 2 Ž2., 107–156.