Академический Документы
Профессиональный Документы
Культура Документы
Industry Backdrop
Projects An Update
Industry Backdrop
World
18% 8%
RoW o
16% 9%
6.0
7.2
12.6
17.5
China
20% 11%
5.1 7.3
14.8
12.9
6.9 4.1
2008 2009 2010 Q1 2010 Q2 2010 Q3
2008
2009
910
Consumer Durable
H1 FY10
H1 FY11
Large scope for metal consumption to rise from current levels End user segments have a strong/positive outlook i e i.e. Power, Transport, Construction, Industrial etc Rising per capita consumption of in India
6%
Industrial Machinery
296
H1FY10
H1FY11
Packaging
4%
H1 growth affected by temporary slowdown in electrical demand, which is primarily dependent on Govt. allocation
Result Highlights
Q2 FY 11: Highlights
Proactive Steps
HighestEverproduction ofCCR
LowerCuPremium
CoalPriceSurge
Efficienciesimproved
Kalwa VRS
pp Copper
Financial Performance
` Cr Net Sales PBITDA PBT PAT EPS (`) ` Cr Net Sales PBITDA PBT PAT EPS (`)
9
Q2 FY10 4,915 666 434 344 2.02 H1 FY10 8,812 1,500 1,034 1 034 825 4.85
Q2 FY11 5,860 780 556 434 2.27 H1 FY11 11,038 1682 1,229 1 229 968 5.06
Q2 profit would have been significantly higher, but for Hirakud production loss and Kalwa VRS settlement
10
Driver LME
Current Assessment Support from global liquidity and cost pressures, but downside risks related to rewind of financing deals USD weakness and continued FII flows to India may lead to rupee appreciation Upward pressure related to coal and carbon costs
Impact
11
13% 38%
Alumina - Resource companies insisting on short-term contracts - De coupling of alumina & aluminium
7%
32%
Power - Electricity price hikes in China - Power cuts in certain Chinese provinces leading to cutbacks in production (~1.5 mt capacity)
Metal (kt)
140 Hkud 123
12%
Growth in Output
(H1 FY11 vs H1 FY10)
Hkud
10% -4% 3% 3%
312
100 Rkoot
Q2 FY10
Q2 FY11
Q2 FY10
FRP (ton)
53,150 53 150
2%
54,042 ,
Extrusions (ton)
2%
9,815 9 815
13
Q2 FY10
Q2 FY11
Q2 FY10
Q2 FY11
100.0 90.0 80.0 80 0 70.0 60.0 50.0 40.0 30.0 20.0 10.0 0.0
84 kt
48% 49%
54 kt
34.2
PrimaryDom 6% VAP 6%
33.5
44%
50%
Q2 FY10 Specials
Q2 FY11 Standard
Q2 FY10
Q2 FY11
14
15
(` cr)
Net Sales & Operating Revenue EBIT
16 64 Change (%)
(` cr)
Net Sales & Operating Revenue EBIT
16
23 37
17
Current Assessment Long term TCRC lower than last year LME being supported by liquidity Appreciating rupee Recently on an improving trend Correlated with commodity cycle; likely to be firm
Impact
Challenging ti Ch ll i times
18
2007
2008
2009
2010 (E)
2011 (P)
TCRC to continue to remain under pressure FY 10 bench mark TCRC were significantly FY higher than FY11 benchmark
19
LNG
Q2: Record cathode production and sharp jump in Own CCR production
Cathode C th d (kt) Own CCR(kt) O
5%
94
41%
43
90
31
Q2 FY10
Q2 FY11
Q2 FY10
Q2 FY11
(` cr) Net Sales & Operating Revenue EBIT (` cr) Net Sales & Operating Revenue EBIT
21
Q2 FY10
Q2 FY11
Change (%)
5,748 374
7,265 253
26 (32)
29491
11% 18%
89.7
26488
75.7 75 7
FY10 H1
FY11 H1
FY10 H1
FY11 H1
Strong Performance
22
III
1 2 3 4 5 6
Capital Efficiency Leadership in domestic market offering better realisation Supply Chain Reengineering Global C t Gl b l Cost Competitiveness Value Chain Enhancement Long Term feedstock securitisation
Transforming the copper business into a globally competitive smelting value chain
23
Projects An Update
24
Utkal Alumina
Engineering
Basic Engg-100 % Complete, Detailed Engg- 95% Completed, not on critical path Obtained Over 82% More than 7,000 people working at site. p p g Major Contractors like L & T, Simplex, GDC mobilized fully at site. 94% of Piling work completed. RCC, structural, fabrication and erection has been ramped up and is on track for timely completion. Erection of BTG units under progress
Power Plant
25
26
Mahan Aluminium
Engineering Statutory pp approvals Orders Commitment Basic Engineering - 94% Complete, Detailed Engineering-60% Complete All Major approvals in place. Orders for all major, long delivery equipment placed. Around 83% Around 12,000 people at site. Major Contractors like L & T, BHEL, Rohan builders etc are working. Concreting & structural work p g g progressing in line with the first pot start up g p p schedule. Power plant Fabrication and erection in line with the start up of the power plant. Foundation for 5 boiler units, 4 ESP units, 2 power house units completed. completed Work on other units in full swing. Work on all chimneys in full swing swing. Two chimney completed- 125 m height. Erection of engineering structure for boilers in progress.
27
GTC1 B filt & Bag filter crust bath silo support structure erection
28
29
Aditya Smelter
Detailed Engg- 68% Complete Engg Major approvals received. Forest land stage I clearance received. Permission to start project site consolidation activities received. received Stage II clearance awaited awaited. Around 66%. Major orders placed (along with Mahan) Area grading ,Piling undergoing. R & R under progress. Civil contractor - HCC Team has mobilized well with hydraulic rigs and civil work in permitted fronts is in full swing.
30
Boiler foundation
31
Capacity t increase t 467.5 MW by Addition of 100 MW C it to i to 467 5 b Additi f MW. 30 pots to be commissioned by Dec2011 & balance 50 pots by Mar2012 GAMI Design Power Plant 1. DCPL has been engaged as the EPCM consultant, Engineering is progressing well 2. Major orders for the power plant already placed. Smelter 1. Basic Engineering by GAMI- completed. 2. Major orders like wagons, alumina handling placed. Other major orders being finalized. 3. SPL has been vacated to storage shed. New plant rectifier station will be erected over here. 4. Site grading 80% and boundary wall 90% completed.
Brownfield project Can Body Stock at Hirakud Dismantling completed. All containers received at Vizag port 13000 MT. Order placed on Achenbach. Order placed on ABB for refurbishment of Main Motors Work Motors. progressing as per schedule. Excavation and f E ti d foundation of building column i progress. d ti f b ildi l in Site Leveling and Boundary wall work in progress.
Civil work
33
Jharkhand Smelter
Land
Total land requirement of ~4000 acres for the project. Both private as well as Govt land acquisition started started. Water drawl clearance received for 55 MCM.
Water
Environmental Application to be submitted after sizeable quantity of land has clearance been acquired. Feasibility Reports DFR is ready.
34
Aditya Refinery
Land Water
Majority land acquired, Rest process on track Water drawl agreement in place M/s Simplex Infrastructure Ltd is awarded with the job for supply & erection of water drawl arrangement. They have completed the ground survey work for route alignment for 15 Km. Terms of Reference (TOR) presentation date is awaited. Job has been completed. Line energized. Railway siding clearance obtained obtained.
35
Expansion Projects
Greenfield projects expected to be in global best quartile for manufacturing costs Infrastructure available for further scalability in the future Brownfield capacity increase advantage
Novelis
Improving product mix to drive margins and growth Successful relocation of Roger Stone Convergence of EBITDA and Adjusted EBITDA Leader in Al Recycling
Driver
Highlights
Continued focus on operational excellence for both Al b th Aluminum and Copper i dC Low cost base and robust de-risked business model
Focus on timely delivery of planned projects Maintain high quality of execution Low capex cost per ton with best in class operating capacities
Financial turnaround with continued operational improvement Leverage on high end technology t h l Brownfield expansion Pinda project, Brazil
Sustainable growth
Achieve potential
37
Thank Th k you
38