BOTTOM LOADING ARM SHALL HAVE FOLLOWING FEATURES:1.Design should be such that arms can fully cross over within the API RP1004 specific loading envelope. 2.Every Bottom Loading Arm should be fitted with API Coupler conforming to API RP 1004. 3.All API Couplers should be easy to maintain with automatic latching and ergonomic ball type handle. 4.Bottom Loading System are designed around using 4 (100 mm ) bore Pipe, Valves, Meters, Strainers, Hoses etc. 5.Loading Rate of Bottom Loading Arms can be up to a maximum of 2400 LPM for a 4 piping system. 6.Bottom Loading Facility for MS will have a 4 Vapour Recovery Arm as well. Vapour recovery arm will be complete with poppeted vapour coupler to comply with API RP1004 standard. Coupler should also have a sight glass for visible warning of liquid in vapour line. 7.Bottom loading rack will require overfill and grounding assurance system with gantry plug and intrinsically safe signaling to truck connection as per API RP1004. 8. With Bottom Loading System the Tank Truck Driver should be able to carry out the following basic tasks:(i) Park the Bottom Loading Tanker in correct location in the loading Area (ii) Connect the grounding and overfill gantry plug to the truck mounted overfill and Grounding system to enable the pumping system to achieve a permissive state (iii) Connecting the Vapour arm to the Vapour recovery connection on the truck for loading MS (iv) Connect Bottom Loading Arm API Coupler to the Tanker (v) Open Tanker Foot Valves / Emergency Valves and Compartment Vapour Vents (vi) Set the Flow Meter and start loading (vii) When loading is completed the Driver disconnects the Bottom Loading Arm and vapour recovery arm (after loading MS) and closes the Tanker Foot Valves Vapour Vents provided on the Manhole Covers on the Top of the Tankers.
Page 1 of 15
TECHNICAL SPECIFICATIONS GENERAL This specification outlines the minimum requirement under which the manufacturer shall design, manufacture, test and supply the Bottom loading arm for loading / unloading operations of road tanker with bottom loading arrangement. In the event of failure, the spring must be contained in a heavy duty cylinder to avoid any injury to the operator. CODES AND STANDARDS The material of construction of the pipes, flanges, valves, joints etc. shall be in accordance with relevant ASTM standards. The specification of the pipes and flanges shall be in accordance with relevant ASME, ANSI, TTMA (Tank Truck Manufacturers Association), and API standards. Wherever international standards and codes are not available, vendor may follow internationally proven standards and practices with prior approval of owner. TECHNICAL REQUIREMENTS Bottom loading arm shall generally consist of base (input) riser, inboard arm, outboard arm with flexible hose, swivel joints, balancing arrangement, supporting arrangement and arrangement for parking position dummy Adapter for parking stand post Inboard The arms shall be of seamless pipes suitable for the hydrocarbon service. It shall be of seamless Carbon steel material to ASTM A106/Aluminium pipe material to ASTM B345(6061/6063T3) to avoid sparking. The material of construction of input riser shall be CS/Aluminium and inboard onwards aluminium alloy. The arm pipe thickness shall be selected for the specified design pressure, and the bending and torsional stresses encountered in the loading operations. Outboard Arm Drop hose stainless steel with braided hose conforming to AISI-321 equivalent with coupler end with the following features. 1. Stiffener at the end of hose pipe to be provided. 2. Corrugated inside hose shall be SS 321 3. External braided shall be SS 304. 4. Both side of braided steel shall be SS 5. Continuous electrical continuity
Page 2 of 15
Approved makes: OPW/ LIQUIP/ ALFONS-HARR/ EMCO WHEATON/WOODFIELD Supporting Arrangement The arm shall be self supported on base riser location. The supporting arrangement shall be such that there is complete flexibility in operation. The supporting arrangement shall be such that no load or force due to bottom loading arm is transferred to piping. Grounding Arrangement Each bottom loading arm shall be electrically continuous, otherwise earthing conductors shall be provided across the non-insulating joints to make it electrically continuous and input will be given to the grounding unit. Vendor shall integrate and power on the grounding unit with the loading arm. Monitor Multi-purpose monitors per gantry to provide overfill protection, position sensor combined with ground assurance connector compatible with all common probes. The system shall also be compatible with the terminal automation software being provided by
Page 3 of 15
1.
2. 3. 4.
Page 4 of 15
REMARK
2 3 4 5 6 7 8
Page 5 of 15
Non Return Valves Non-Sparking type non-return valve (Check Valve to ensure no reverse flow) shall be provided at the end of each Vapour Loading Arm before the same is connected to the vapour loading header provided in the gantry. The check valve shall be supplied as per the following Data Sheet: Sl.no 1 2 3 4 5 6 7 8 Description Standard, Rating and service Size Ends Valve Port Body Cover Disc Body seat ring Requirement API6D, 150#, MS vapour 4 NB Flanged conforming to ANSI B16.5 with raised face having serrations 125 AARH Reducing Port Cast Steel conforming to ASTM A 216 Gr WCB/ Forged conforming to ASTM A 105 Bolted with material conforming to ASTM A 216 Gr WCB/ ASTM A 105 Material conforming to ASTM A 216 Gr WCB/ ASTM A 105 with 13% Cr. Steel Facing Renewable with Material conforming to ASTM A 216 Gr WCB/ ASTM A 105 with facing of suitable non-sparking material Material conforming to ASTM A 216 Gr WCB/ ASTM A 105 with facing of suitable non-sparking material ASTM A 193 Gr B7 ASTM A 194 Gr 2H Spiral wound SS 316 with soft iron filler Body: 450 psi , Seat:315 psi 80 psi Shall be non-renewable integral type or Non-Integral seat ring seal welded type Suitable for horizontal/vertical installation As per API 6D with zero leak Audco/KSB Pumps Ltd/ BHEL/Leader Valves/ BDK Industries/ Niton/ Steel Strong/ Associated Toolings India
9 10 11 12 13 14 15 16 17 18
Disc Hinge Hinge stud Bolt Cover nuts Bonnet Gasket Hydrotest pressure Pneumatic pressure Seats Installation position Testing Approved makes
Page 6 of 15
Page 7 of 15
Intermediate swivel
Working envelope
Page 8 of 15
Accessories
Painting
Page 9 of 15
DATA SHEETS FOR VAPOUR RECOVERY ARM ITEM NO. 1 2 3 DESCRIPTION Quantity Model Ambient temperature Service Design pressure Operating pressure Flow rate Density(Min/Max) Viscosity(Min/Max) Maximum pressure drop Type Size and rating Battery limit connections Vapour feed direction Balancing type REQUIREMENT As per Bill of Quantities To be specified by Vendor 5 to 50 deg c MS vapour during loading operation 10.5 Kgf/sqcm 7 Kgf/sqcm 2400 LPM 0.70/.86 gm per cc 0.9 cst / 5 cst @ 38 deg C Should conform to CEN regulations Self supporting, high profile, over head (top to bottom) bottom loading arm suitable for above mentioned product service 4 suitable for connecting with battery limit connection 4 Flanged ends with raised face as per ANSI B 16.5, class 150 From below Spring Type (Torsion/Compression) / Gas Strut In the event of failure the Spring/Strut must be contained in a heavy duty cylinder to avoid any injury to the operators Shall have simple adjustment to balance the Arms. Required Schedule 40 seamless pipes carbon steel A106 / Aluminum pipe of ASTM B-345 to avoid sparking with TTMA flanges 4, seamless Aluminum pipe of ASTM B-345, Flexible Hose Pipe having SS convoluted with TTMA flanges as per AISI 321 with SS Braid. To act as electrically continuous. Inside corrugation of braided hose shall be of AISI 321
Page 10 of 15
Intermediate swivel
Page 11 of 15
Working envelope
Accessories
Painting
Erection of all equipments supplied by the vendor as per this Tender shall be carried out by the vendor including testing wherever applicable as per the rates quoted in the price bid. The equipment shall also be commissioned by the vendor. SCOPE OF INSPECTION AND TESTING Equipment shall be subjected to stage wise expediting, inspecting and testing at vendors/ sub vendors works by owner or its authorized Inspection Agency (TPIA). Vendor shall submit Quality Assurance (QA) procedures before commencement of fabrication. Approved QA procedures shall form the basis for equipment inspection. Inspection and Testing at Vendors / Sub Vendors works shall include but not be limited to the following: Sr.No. 1 2 Material Specification Visual inspection of loading arms HPCL Requirement 100% Vendors Confirmation
Dimensional inspection of 100% as per approved loading arms Drawing Hydrotest 100 % Hydrostatic test of
Page 12 of 15
After assembly, the arms shall be subject to the following tests: Balancing test This is conducted in loading arms to demonstrate that the arms are mechanically counter balanced. Rotate the swivel joints for three cycles in forward and three cycles in reverse direction to demonstrate that swivels joints can be easily Operated. Torque required for operating the Swivel joint shall be measured
Quantum of check C All test certificates, indicating details of materials for inboard arm, out board arm and drop pipe and scope of inspection indicated above, shall be provided along with supplies. Also
100%
Page 13 of 15
Bending moment test for It shall be done and the Springs and Base Swivel certificates shall be Joint offered for verification during inspection. Additionally bending moment. test shall be done for split flange type of swivel joint and witnesses by TPIA Quantum of check 1 No. of each type of swivel Joint
Forces required for movement of loading arms: Vendors shall arrange to provide a Force testing arrangement, such that the force is applied perpendicular to arm. The self weight of the mechanism shall be accurately measured prior to applicable of force Quantum of check 100%
Page 14 of 15
Quantum of check H Type test for pressure drop across the loading arms
Testing of O - Ring and 1 sample from each lot/ SEALS batch and internal certificates to be offered for verification during inspection
Vendors to prepare QAP based on above Scope of inspection and get the same approved through TPIA and final approval of HPCL shall be obtained on it. In case vendor is unable to accept any of the above clauses then reasons for the same shall be provided in the vendors confirmation column. However vendors to note that the bid may be liable for rejection in case of non-acceptance of any of the above clauses.
NOTE:1. The bottom loading equipments as per BOQ should have compatibility to performance as per RP 6004 in meeting the point of tank truck equipments of terminal and party to confirm the same. 2. All the equipments shall have the approval from chief controller of explosive, Nagpur. 3. Comissioning spares for Bottom loading arm and vapour recovery arm shall be in the vendors scope. Recommended spares shall be listed separately and will be under vendor scope