Вы находитесь на странице: 1из 1

CORNERSTONE 9/14/07 3:30 PM Page 38

CORNERSTONE CONSTRUCTION

the project exceeded the budget by


almost $6 million, within 10 days, the
company used value-engineering, pulled
out unnecessary mechanical, electrical
and plumbing elements and brought the
budget back in check.
In March, Cornerstone broke ground
on the facility, constructing the founda-
tion and erecting the steel and concrete
frame. The company had to pay close
attention to the seismic zone require-
ments. To meet the zoning requirements,
the company constructed five groups of
pilings made of steel pipe that were each
driven 40 feet below the surface and
capped off with as much as 160 pounds
of concrete and steel plates.
“I have never seen anything quite like
this – and I have been doing construc-
tion for 30 years – with the giant seismic
plates of steel that go down so far,”
Palmatier says.
As if merely constructing a building of
this magnitude wasn’t enough of a feat,
Cornerstone must also deal with the sea-
sonal, but harsh, Alaskan climate. “Our
timeframe is the biggest challenge,”
Palmatier says. “We just don’t have
enough summer to get things in place.
The building is too large. We’ve been
working crews as much as [12-hour
shifts, seven days a week].”
The company plans to have the roof
on by early October, which will allow the
team to work inside the structure during
the winter months.
The location also makes it more chal-
lenging for the contractor to meet work
The centrally located atrium at UAA’s 120,000-square-foot Integrated Sciences Building will serve as force goals. Extensive preplanning and
the main area for faculty, researchers and students to socialize when it opens in 2010.
scheduling helped cut the risk of coming
ness of the need to prevent the state’s The Anchorage-based company has up short with its work force.
“brain drain” fueled the need for the new found its niche constructing complex “We put together an organizational
building. Before, the university could facilities in Alaska, where the competi- chart; the planning up front was enor-
only provide a portion of the students tion cannot. Cornerstone specializes in mous, so we assigned duties before we
with the latest technology and lab facili- medical, military, laboratory, educational started,” Palmatier explains. Several
ties, forcing many to look out-of-state for and industrial projects. members of the team have also been
other programs, and eventually, careers. Meeting tight deadlines and budgeting assigned to specific tasks, with individu-
Now, Hatch says, “there is no doubt we requirements while still building a quali- als in charge of document control and
will retain more students.” ty facility requires the company to part- construction management.
ner with UAA, a team of subcontractors Cornerstone also held an extensive
Meeting Complex Requirements and ZGF Architects. According to Project interview session to select the 40-plus
Cornerstone Construction, the construc- Manager Mark Palmatier, the subcontractors it will have working on
tion manager-at-risk on the facility, broke design/assist relationship has helped site by the building’s completion. During
ground on the facility in March 2007 keep all parties aligned with the budget, the interview process, Palmatier says, the
after an extensive preplanning process allowing the company to make immedi- company looked closely at the subcon-
that involved forming a strong partner- ate adjustments when needed in the ini- tractors’ experience in complex design,
ship with the owner and the architect. tial design phases. For example, when cost margins and ability to meet tight

38 ■ CONSTRUCTION TODAY ■ OCTOBER 2007

Вам также может понравиться