Академический Документы
Профессиональный Документы
Культура Документы
Paper 130-29
ABSTRACT
Risk management is project management for adults. It guides project managers to focus specifically on what can go wrong, instead the more usual "if everything goes as planned" approach. The benefits of risk management include these: it enables aggressive risk-taking it protects management from being blind-sided it provides minimum cost downside protection In this keynote, Tom DeMarco lays out the basics of a risk-focused strategy and provides clear guidelines for its implementation.
SUGI 29
SUGI2004: Montreal, May 10, 2004 Copyright 2004 by Tom DeMarco: The Atlantic Systems Guild
SUGI 29
RISK MANAGEMENT . . .
nothing but the beef: three reasons why you bother one key tool use of monte-carlo simulation one metric to track (late) risk manifestation a useful pattern from the past a scary but wonderful observation the did-we-really-do-it? test
Planning, Development and Support
SUGI 29
SUGI 29
SUGI 29
Airport opening
SUGI 29
SUGI 29
SUGI 29
1. You have zero chance of delivering before January of next year. 2. My best guess is youll be done around April 1st . . . 3. but to be at least 50% sure, youd better advertise a date of May 1 or later. 4. To be 100% safe, youd have to allow for delivery as late as end of next year.
Planning, Development and Support
SUGI 29
RISK DIAGRAM:
A risk diagram shows explicitly how uncertain we are about delivery date (or anything else).
10
SUGI 29
11
SUGI 29
52 person months
Planning, Development and Support
20,000 FP
12
SUGI 29
13
SUGI 29
Productivity Variation
Sources of Uncertainty
Flaw in size estimate
Delivery Date
Planning, Development and Support
Resultant Uncertainty
etc.
14
21-FEB-04
3-JUN-04
15-SEP-04
Alpha Platform:
27-DEC-04
9-APR-05
SUGI 29
Completion Date
15
21-JUL-05
3-NOV-05
15-FEB-06
27-MAY-06
9-SEP-06
CANCELLED
SUGI 29
16
SUGI 29
Jun-04
Dec-04
Calendar Date
17
SUGI 29
18
SUGI 29
19
SUGI 29
20
SUGI 29
The real reason we need to do risk management is not to avoid risks, but to enable aggressive risk-taking.
Planning, Development and Support
21
SUGI 29
22
SUGI 29
23
SUGI 29
6. Is the scheduled delivery date significantly different from the best-case scenario?
24
SUGI 29
25