Вы находитесь на странице: 1из 7

Session 1: Solar Photovoltaic Power

CASE II 40 MW PV - Leipzig, Germany

Base case Central grid connection Changing Currency Settings Start Spreadsheet: Show settings. Currency - Choose appropriate currency For up-to-date exchange rates, go to www.xe.com/ucc/ Proposed case 40MW photovoltaic power plant at an installed cost of 130M 800,000 Thin-Film, Cadmium Telluride 50W panels from First Solar, Fixed, 30deg slope Can sell PV generated electricity to grid at 0.67/kWh all year round 6.9% Efficiency, Misc. Losses of 5% Inverter Efficiency of 90%, 72kW Capacity, Misc. Losses Negligible Project life is 25 years

Questions 1. What is the resulting Capacity factor for this proposed setup? 2. At this capacity factor, how much electricity is exported to the grid, in MWh/year? 3. If the panels are not cleaned for one year, and incur eventual miscellaneous losses of 20%, how much electricity would be exported to the grid? Answers 1. The capacity factor for this proposed setup is 11.4% 2. At such a low capacity factor only 40,113MWh/yr of electricity is exported to the grid. 3. If the panels are not cleaned for one year, and incur miscellaneous losses 20%, the electricity exported to the grid reduces to 33,780MWh/yr.

Session 2: Wind Power


CASE II: Part 1 1 MW Wind - Ross Island, New Zealand Note: Start this assignment using the spreadsheets from Case I. This will ensure that the financial variables remain filled in. This comparison will be focused on the technologies. Base case (Start Tab) Analysis Type: Method I Central grid connection Changing Currency Settings Start Spreadsheet: Show settings. Currency - Choose appropriate currency For up-to-date exchange rates, go to www.xe.com/ucc/

Proposed case 1MW wind power plant at an installed cost of NZ$10M 3x330kW Enercon 33 49m Turbines 6.5m/s annual wind speed, measured at 10m Can sell wind generated electricity to grid at NZ$1.25/kWh 1.0% Array Losses, 1% Airfoil Losses, 5% Misc. Losses, 95% Availability Project life is 25 years Questions 1. What is the resulting Capacity factor for this proposed setup? 2. At this capacity factor, how much electricity is exported to the grid, in MWh/year? 3. Display and discuss the Power and Energy Curves. 4. If the turbine blades accumulate ice, and incur airfoil losses of 20%, how much electricity would be exported to the grid?

CASE II: Part 2 1 MW Wind - Ross Island, New Zealand

Note: Start from the spreadsheet created in Part 1 of Case II. Instructions: Create a solar power system that supplies the same amount of electricity exported to grid as the wind power system using the following specifications: Thin-Film, Cadmium Telluride 50W panels from First Solar Can sell solar generated electricity to grid at NZ$1.25/kWh Fixed, 30 deg slope 6.9% efficiency, Misc. losses of 5% Inverter efficiency of 90%, 72 kW Capacity, Misc. Losses negligible Project life is 25 years

You need to determine the amount of solar panels that are needed. The installed cost of an individual panel is NZ$200/panel. Questions: 1. How many solar panels are needed to have same amount of electricity exported to the grid? 2. For these financial specifications, how do the installed capital costs compare? 3. Another important issue when considering renewables is land usage. When locating wind turbines, they are generally placed in a rectangle formation and spaced apart according the following rules of thumb: 3-5 rotor diameters apart in the prevailing wind direction and 1-3 rotor diameters apart in the other direction. For example, one Enercon 33 wind turbine will need approximately (2x(3x34m))*( 2x(1x34m)) = 13,872 m2. Assume that the solar panels use 1 m2 of land each (Other factors in land usage that were not included here are maintenance roads and some spacing between the panels in order to service them). Calculate how much land the wind case and the solar case uses and compare. 4. Considering this climate, the finances, and the land useage, which technology would you choose?

Answers Part 1: 1. The proposed wind system has a Capacity Factor of 40.5% 2. At this capacity factor, 3511MWh/yr of electricity is exported to the grid. 3. The cut-in speed is 3m/s. This is the speed at which the torque on the blades of the wind turbine is just enough to generate usable electric power. Above this wind speed, the rate of increase of power and energy curves is very high, finally saturating (the power curve) at about 13m/s. This is the rated speed and would result in the maximum power and energy generated. Beyond 15m/s, which is the cut-out speed (speed at which energy can be extracted without causing structural failure) the energy generated is zero.

4. With the increased airfoil losses of 20%, electricity exported to the grid is 2837MWh/yr. Part 2: 1. The no. of solar PV panels required to export the same amount of electricity as the 1MW Wind Power is 83,330. 2. A comparison of the installed capital costs shows solar to be NZ$16,666,000, while wind is only NZ$10,000,000. 3. A comparison of the land resource required to export 3511MWh/yr of electricity shows wind to take up 26,136m2 ( 3x(4x33)*(2x33) ), while solar requires 83,330m2 almost 3 times the land. 4. The climate is windy most of the year with high wind speeds (still less than the cut off) throughout, the initial cost of wind turbines for the required grid electricity supply is lower than the solar pv option, and even the land required for the wind farm is 3 times less than for the solar farm. Thus, in this case, we choose the wind farm over solar farm as it is cheaper, requires less land and is more suitable to the climatic conditions prevailing.

Session 3: Financial Analysis


CASE II 63.7 MW Wind - Fort Hancock, TX, USA Start from Case Study from the Project Database: Wind Power in Pasco, Washington Note: This case will be the starting point for the values in the spreadsheet that we will not be changing.

Base case (Start Tab) Analysis Type: METHOD II Central grid connection Proposed case 63.7 MW Wind Farm In the financial tab there are many more components included. Since the case study uploaded was in Washington and this analysis is in Texas, some of the costs have changed. So input the following costs: Wind turbines costs $1,000/kW Install 25 km of roads at $25,000/km Install 25 km of transmission line at $35,000/km Install 2 substations at $2,000,000/station Every 8 years you need to replace 20 renewable energy deep-cycle batteries at $5,000/battery (add this cost as a Periodic cost) Questions 1. How many years to break even? What is the impact of the Clean Energy Production Income? What would it take to get a 5 year payback? 2. What is your calculated IRR? Does this seem to be an attractive project to you? Why or why not? 3. Change your location to Montpelier, VT. How did your electricity exported to grid, payback, and IRR change? 4. Change your location to St. Louis, MO. How did your electricity exported to grid, payback, and IRR change? 5. Using the Sensitivity Analysis worksheet, evaluate the sensitivity of NPV to 20% adjustments to Initial Costs and Electricity Export Rate. If your initial estimates for Initial Costs and Electricity Export Rate are 10% too high, how much more or less money will you make? 6. Using the Risk Analysis worksheet, conduct a risk analysis for an NPV with a 10% range in Initial Costs. For this level of uncertainty in Initial Costs, what is the probability that you will make money on this project?

Answers

1. To break even, 5.2years were required. The Clean Energy Production Income has an inverse correlation with the payback period. For a clean energy production income of 0.041$/kWh, with a total CE production income being $4,178,567, the payback period is 5years. 2. The calculated IRR was ve, for Fort Hancock, TX, USA (u=4.2m/s, height=10m). Thus, it does not seem to be an attractive project. 3. Answered along with 4th answer in the table shown below. 4. Fort Hancock, TX 101,916 n/a -ve Montpelier, VT 49,202 n/a -ve St. Louis, MO 63,042 n/a -ve

Electricity Exported (MWh/yr) Payback (yr) IRR (pre-tax equity)

5. If the initial estimates for initial cost and electricity export rate are 10% too high, the loss in NPV would be $1,460,006 less (NPVinitial = $31,998,461, NPVfinal = $30,538,455) 6. The probability of making money is 0, since the NPV is all along ve.

Session 4: Fuels and Emissions


Case II 66MW Steam Turbine Fuel Comparison Louisville, Kentucky, USA Questions 1. What is the annual GHG emission reduction for this cofiring plant compared to all types of fuel in the United States? (Both corn stover and Christmas trees have the same emissions factors) 2. What cost of Christmas trees ($/t) makes this plant unattractive (IRR less than 15%)? 3. The stockpile of Christmas tree fuel has run out and now the plant is switching to co-firing 60% corn stover and 40% bagasse at $35/ton. The bagasse gas a CH4 emission factor of 0.991 tCO2/MWh and a N2O emission factor of 0.54 tCO2/MWh. Because your planthas switched to bagasse, you no longer receive Clean Production income. Is this still an attractive project? Discuss.

Answers 1. The annual GHG reduction for this co-firing plant compared to coal combustion in the USA is 531,864.4tCO2/yr. 2. The pre-tax IRR for this configuration was 18.8%. To make this plant an unattractive proposition (IRR<15%), the cost of Christmas tree fuel had to increase to $61/ton. 3. If we change the fuel mixture from Christmas tree & corn stover, to corn stover & bagasse, the GHG emission reduction changed from +531,864.4tCO2/yr to 197,053.2tCO2/yr, i.e., it was an increase in GHG emissions as compared to coal. The IRR in this new case is 8.7%, which is less than the 15% (our hurdle IRR, as mentioned in question 2). Thus, this was an unattractive proposal, for both financial and environmental reasons. The bagasse released high CH4 and N2O (as seen from the emission factors) and since the mass to energy conversion is very low for the bagasse + corn stover fuel mixture as compared to coal, the total CO2 emission was higher than coal. The GHG emission factor for coal was 5 times higher than the mixed fuel, but even then the 10 times higher fuel consumption (in MWh) lead to an overall increase in GHG emission.

Вам также может понравиться