Академический Документы
Профессиональный Документы
Культура Документы
PMP
Preparation Training
Your key in Successful Project Management
Akram Al-Najjar, PMP Project Management Consultant
Chapter 7
5/2/2006
AGENDA
What is Cost Management? Cost Management Processes
Project Cost Management Processes involved in planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. Cost Estimating Cost Budgeting Cost Control
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 4 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
5/2/2006
Gantt Chart
5/2/2006
5/2/2006
PV and EV
5/2/2006
PV , EV and AC
PV , EV and AC
5/2/2006
New: SV = EV PV
= $24,000 - $32,000 = ($8,000)
The project has delivered $8,000 less work at this point in time than was planned. This project is behind schedule. This is a great way to depict ahead or behind on schedule, even though it is in monetary terms!!!
Akram Al-Najjar, PMP.
Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
5/2/2006
New: CV = EV AC
= $24,000 - $29,000 = ($5,000)
The project has cost $5,000 more to deliver the work done so far than was planned. This project is over budget.
New: SPI = EV / PV
= $24,000 / $32,000 = 0.75
The project is delivering work slower than planned. The work is being done at 75% of the expected rate.
5/2/2006
New: CPI = EV / AC
= $24,000 / $29,000 = 0.83
The project is spending money faster than planned. Only 83% of work is being delivered for the amount of money being spent.
Case 1
PV = $ 1,860 EV = $ 1,860 AC = $ 1,860
This is the ideal situation, where everything goes according to plan.
5/2/2006
Case 2
PV = $ 1,900 AC = $ 1,700
In this Case, without Earned Value measurements, it appears were in good shape. Expenditures are less than planned.
Case 2
PV = $ 1,900 EV = $ 1,500 AC = $ 1,700
But with EV measurements, we see...$400 worth of work is behind schedule in being completed; i.e., we are 21 percent behind where we planned to be.
SV = EV PV =- $ 400 SV % = SV / PV x 100 =- 21 %
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 20 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
10
5/2/2006
Case 2
PV = $ 1,900 EV = $ 1,500 AC = $ 1,700
In addition, we can see... Actuals exceed Value Earned (EV), i.e., $1,500 worth of work was accomplished but it cost $1,700 to do so. We have a $200 cost overrun (i.e., 13% over budget) .
CV = EV AC =- $ 200 CV % = CV / EV x 100 =- 13 %
Case 2
PV = $ 1,900 EV = $ 1,500 AC = $ 1,700
This means only 79 cents worth of work was done for each $1.00 worth of work planned to be done. And, only 88 cents worth of work was actually done for each $1.00 spent
11
5/2/2006
Case 2
PV = $ 1,900 EV = $ 1,500 AC = $ 1,700
This is the worst kind of scenario, where all performance indicators are negative.
Case 3
PV = $ 2,600 EV = $ 2,400 AC = $ 2,200
In this case there is bad news and good news.
12
5/2/2006
Case 3
PV = $ 2,600 EV = $ 2,400 AC = $ 2,200
The bad news is that our work efficiency is a bit low; were getting only 92 cents of work done on the dollar. As a result, we are behind schedule.
Case 3
PV = $ 2,600 EV = $ 2,400 AC = $ 2,200
The good news is that were under-running our budget. Were getting $1.09 worth of work done for each $1.00 were spending.
13
5/2/2006
14
5/2/2006
If we know that we can finish the rest of the work as it was originally planned Use actual to-date plus budgeted amount for the rest of the work EAC = AC + BAC EV = $29,000 + $100,000 - $24,000 = $105,000
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 29 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
If the original estimates were flawed, we should build new estimates for all the remaining work Assume this ETC is the Estimate to Complete the was the total ETC remaining work. from a completely EAC = AC + ETC rebuilt = $29,000 + $120,000 estimate = $1,49,000
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 30 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
15
5/2/2006
If we assume that past performance is a good indicator of future performance Use actual to-date plus budgeted amount for the rest of the work, modified by a performance factor, such as CPI EAC = BAC/CPI = $100,000/0.83 = $120,481 (rounded off)
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 31 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
16
5/2/2006
Present Value
Budgeting technique that debates the future value of money based on inflation, etc. PV = FV (1 + r)t FV = amount of money t years from now r = interest rate (also called discount rate) t = time period
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 34 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
17
5/2/2006
Present Value
Year FV PV 0 $50,000 $50,000 1 $35,000 $31,819 2 $15,000 $12,397 Assume a 10% interest (or discount) rate PV (Year 1) = FV / (1 + r)t =$35,000/(1 + 0.1)1 = $31,819
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 35 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
0 1 2 3 Total
0 50 100 300
0 45 83 225 353
200 100 0 0
200 91 0 0 291
Akram Al-Najjar, PMP.
NPV =353-291=62
Source: pmbok guide 2004 Slide 36
18
5/2/2006
Payback Period
The exact length of time needed to recover an initial investment as calculated from cash inflows.
Month 1 2 3 4 5 6 7 Costs $5000 $5000 $8000 $5000 $2000 $0 $0 Total Cost $5000 $10000 $18000 $23000 $25000 $25000 $25000 Benefits $0 $0 $0 $5000 $10000 $10000 $10000 Total Benefits $0 $0 $0 $5000 $15000 $25000 $35000
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 37 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
19
5/2/2006
20
5/2/2006
Types Of Costs
Direct Costs- Cost that are directly attributable to the work on project. Examples are team travel, team wages, recognition and cost of material used on the project
Indirect costs Overhead items or costs incurred for the benefit of more than one project. Examples include taxes, fringe benefits, and janitorial services.
DEPRECIATION
STRAIGHT LINE DEPRECIATION : the same amount of depreciation is taken each year, A US $ 1,000 item with a ten year useful life and no salvage value (how much item is worth at the end of its life) would be depreciated at US $100 per year. ACCELERATED DEPRECIATION you only need to know: There are two forms of accelerated depreciation Double Declining Balance and Sum of the Years Digits. They depreciate faster than straight line. You do not have to know what these two forms means or do any calculations.
21
5/2/2006
PROJECT
costs
costs
Akram Al-Najjar, PMP.
Slide
43
PMBOK Chapter 7
There are 3 major processes:
1. 2. 3.
22
5/2/2006
Cost Management
Planning Controlling
23
5/2/2006
Cost Estimating
Process of developing an approximation (or estimate) for the cost of the resources necessary to complete the project activities Difference between cost estimating and pricing:
Cost estimating: Assessing how much it will cost the organization to provide the product or service Pricing: Assessing how much the organization will charge for the product or service
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 47 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
Cost Estimating
Tools & Techniques
Analogous estimating Determine Resource Cost Rates Bottom-up estimating Parametric estimating Project Management Software Vendor Bid Analysis Reserve Analysis Cost of Quality
Inputs
Enterprise Environmental Factors Organizational Process Assets Project Scope Statement Work Breakdown Structure WBS Dictionary Project Management Plan Schedule management plan. Staffing management plan. Risk register.
Source: pmbok guide 2004
Outputs
Activity Cost estimates Supporting detail Requested Changes Cost management plan
Akram Al-Najjar, PMP.
Slide 48 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
24
5/2/2006
Inputs
Enterprise Environmental Factors , considers: Marketplace conditions. Commercial databases. Organizational Process Assets Cost estimating policies. Cost estimating templates. Historical information. Project files. Project team knowledge. Lessons learned.
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 49 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
Inputs (cont.)
Project Scope Statement describes the business need, justification, requirements, and current boundaries for the project. Work Breakdown Structure WBS provides the relationship among all the components of the project and the project deliverables WBS Dictionary provide an identification of the deliverables and a description of the work in each WBS component required to produce each deliverable.
Source: pmbok guide 2004 Slide 50
25
5/2/2006
Inputs (cont.)
Project Management Plan Schedule management plan: The type and quantity of resources and the amount of time those resources are applied to complete the work of the project is a major part of determining the project cost. Staffing management plan. Project staffing attributes and personnel rates (Section 9.1.3.3) are necessary components for developing the schedule cost estimates. Risk register. The cost estimator considers information on risk responses (Section 11.2.3.1) when producing cost estimates.
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 51 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
26
5/2/2006
Outputs
Activity Cost estimates Quantitative assessments of the cost of resources (e.g., units of currency or staff hours) Types of estimates Order of magnitude (-25% / +75%) Budget estimate (-10% / +25%) Definitive estimate (-5% / +10%) Supporting detail
Description of estimated scope of work Documentation of the basis for the estimate Documentation of any assumptions made Range of possible results
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 54 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
27
5/2/2006
Cost Estimating
Outputs (cont.)
Requested Changes The Cost Estimating process may generate requested changes that may affect the cost management plan, activity resource requirements and other components of the project management plan. Requested changes are processed for review and disposition through the Integrated Change Cost management plan
Cost Budgeting
Aggregating the estimated costs of individual activities or work packages to establish a cost baseline.
28
5/2/2006
Cost Budgeting
Tools & Techniques
Cost Aggregation Reserve Analysis Parametric Estimating Funding Limit Reconciliation
Inputs
Project Scope Statement Work Breakdown Structure WBS Dictionary Cost estimates Supporting Detail Project schedule Resource Calendars Contract Cost management plan
Source: pmbok guide 2004
Outputs
Cost baseline Project Funding Requirements Cost Management Plan (Updates) Requested Changes
Inputs
Project Scope Statement : WBS Identifies the project elements to which the costs will be allocated WBS Dictionary Cost Estimates Cost Estimate Supporting Detail Project schedule Used to assign costs to project elements for the time period when costs will be incurred Resource Calendars
Akram Al-Najjar, PMP.
Source: pmbok guide 2004 Slide 58 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
29
5/2/2006
Inputs
Contract (Section 12.4.3.2) information related to what products, services, or results have been purchased and their costs are used in developing the budget. Cost Management Plan The cost management plan component of the project management plan and other subsidiary plans are considered during cost budgeting.
30
5/2/2006
Outputs
Cost baseline Time phased budget that will be used to measure and monitor the cost performance of the project
140 120 BCWS ($K) 100 80 60 40 20 0 Jan Feb Mar Apr May Jun
Reporting Period
Outputs
Project Funding Requirements Cost Management Plan (Updates) Requested Changes
31
5/2/2006
Cost Control
Influencing the factors that create changes to the cost baseline to ensure that changes are agreed upon Determining that the cost baseline has changed Managing the actual changes when and as they occur
Includes:
Monitoring cost performance to detect variances from the plan Ensuring that all appropriate changes are recorded Preventing incorrect, inappropriate, or unauthorized changes Informing the appropriate stakeholders of authorized changes Analyzing positive and negative variances and how they affect the other control processes
Source: pmbok guide 2004 Slide 63
Cost Control
Tools & Techniques
Cost change control system Performance measurement Analysis Forecasting Project Performance Reviews Project Management Software Variance Management
Outputs
Inputs
Cost baseline Project Funding Requirements Performance reports Work Performance Information Approved change requests Project management plan
Source: pmbok guide 2004
Cost Estimates (Update) Cost Baseline (Updates) Performance Measurements Forecasted Completion Requested Changes Recommended Corrective action Organizational Process Assets (Updates) Project ManagementAkram Al-Najjar, PMP. Plan (Updates)
Slide 64 Project Management Consultant Akram_alnajjar@hotmail.com +20105394312
32
5/2/2006
Cost Control
33