Вы находитесь на странице: 1из 2

Unit

Core

Fukushima Daiichi Status Summary - 0430 EDT 04/2/2011 - Update


400 fuel assemblies- damaged; RPV pressure: 57.4,tpsig (JAIF 4/2); RPV level: -1/2 -TAF (JAIF 4/2); fresh water inject. 31 qlm 4. (Site Team 4/2) via fire ext. line to feedwater line using temp. elect. Pumps (TEPCo); Vessel temp: Btm Head 119.7 0C4,(Site Team 4/1) FW nozzle: 248.64,oC (JAIF 4/2), On external power - CR Lighting for U-i, 2, 3 & 4 (JAIF 4/1); instr pwr on for U-1, 2 & 4 (IAEA 3/29); Primary: functional. D/w pressure: 9.2.,psig (JAIF 4/2). Loosing 10-30% drywall volume/day (TEPCo via Site Team 4/2) Pumping water from turbine bldg basement to main condenser (IAEA 3/29). 3820 rem/hrt (Site Team 3/31) Torus: 1740 rem/hrl, (Site Team 4/1). Secondary: severe damage from H, explosion. 292 bundles (GEH); Temp & level: unconfirmed, White smoke emitting (TEPCo 0630 JDT 3/29) Water spray using concrete pump truck started (JAIF 4/1) 548 fuel assemblies - damaged; RPV pres: -1.2t'psig (JAIF 4/2); RPV level: 2/3 TAF (NISA 3/27); freshwater injection 39.6 gpm into RPV (Site Team 4/1); Injection via temp. electrical pump w/ diesel B/U (IAEA 3/28) Vessel temp: Btm Head 1370Ct\ (Site Team 3/31), FW nozzle 163.60C,, (Site Team 4/1), receiving external power (NISA) & power dist. panels connected (IAEA 3/27); Fresh water (non-borated) injecting into core (NISA-METI 3/29) Primary: damage suspected. D/w pressure 1.3 psig (JAIF 4/2). Pumping water from turbine bldg to main condenser (NEI 3/28) 3860 rem/hr4,. (Site Team 3/31) Torus: 111 rem/hrl (Site Team 4/1) Secondary: panels removed from side of Rx bldg reducing H, build-up.
0 587 bundles (GEH); Temp: 50.01" C (JAIF 4/2); Level: pool may be overflowing, - water in adjacent areas (NRC site team); White smoke emitted on 3/26 (NISA, EPCo 3/29); Fresh water injection continuing (IAEA 3/30)

Priority

p. .

Containment

Core

Containment

Core

Containment

548 fuel assemblies - fuel damaged; RPV pressure: -5.224,psig (JAIF 4/2); RPV level: - 2/5 TAF (IAEA 3/28) Rad levels indicate fuel covered (site team); freshwater injection 30.64gpmvia temp. electric pump (Site Team 4/1) Vessel temp: Btm Head 116.3 0Ct (Site Team 4/1); FW nozzle: 92.6 0Ct (Site Team 4/1) rec. ext. power (NISA). Primary: Japanese report functional. RST suspects failure. D/w pressure: 0.82 psig (JAIF 4/1). 2750 rem/hrJ, (Site Team 3/31) Torus: 100 rem/hr4, (Site Team 4/1) Secondary: - severe damage from H2 explosion. Same plan as U-2 to

pump out TB basement.


SF Pool 514 bundles (GEH) - damage suspected (JAIF 3/28); Temp: unconfirmed; Level: low - fresh water spray periodically (Tepco 3/29) Continued water spray and injection. Switched from seawater to freshwater. (JAIF 3/31) . White smoke emitting as of 0630 3/29 (NISA). 1331 bundles in SFP (GEH & NISA) Temp & Level: low level - Fresh water injection completed 05:33EDT on 3/30 via the extended boom pumper truck (IAEA 3/31) Continued water spray and injection. On external power & dist. panels connected (IAEA 3/27). Secondary contain: severe damage from H, explosion. White smoke confirmed 0630 3/29 (NISA). 548 fuel assemblies - no damage; RPV intact; temp 35.0C (JAIF 3/29); Cold shutdown at 1430 JDT 3/20 (NISA); offsite electrical power supplying house loads (IAEA 3/28) injection via normal make-up water (IAEA 3/31); 946 bundles (JAIF); Temp: 38.11'1 0 C (JAIF 4/2); Cooling capability recovered (JAIF 4/1) 764 fuel assemblies - no damage; RPV intact; Temp 37.7 0 C (JAIF 3/29); Cooling using RHR; Cold shutdown at 1927 JDT 3/20 (NISA); offsite elect power to house loads (IAEA 3/28); injection via normal make-up water (IAEA 3/31); SF Pool 876 bundles (GEH); Temp 21.0,bC (JAIF 4/2); Cooling capability recovered (JAIF 4/1) 6,000 bundles (GEH) maintained at 32.20C,4, (INPO 3/30); normal cooling started 1805 JDT 3/24/2011 (NISA) 7 6

SF Pool Core SF Pool

4 5

Common SF Pool

Summary Sheet Notes:


Basis for Assigned Priority to Units
PRIORITY 1 - Unit 1, maintaining containment is high priority PRIORITY 2 - Unit 2, containment damaged PRIORITY 3 - Unit 3, Primary containment may be intact. However, flooding in turbine building contains 1-131 PRIORITY 4 - Unit 4, due to the condition of its spent fuel pool PRIORITY 5 - Unit 5, Higher priority than Unit 6, spent fuel pool temperature is 38 C (increased slightly) vs. 21 C in Unit 6. Difference not significant. Cooling being maintained. PRIORITY 6 - Unit 6, SPF cooling being maintained

Common SFP is low priority, adequately maintained.

Вам также может понравиться