The information in this document is only meant to be a reference for ERP Process configured as per the Business Process approved by BSNL Management for Project System Module and is not a complete description of the SAP product and its functionalities. Its main purpose is to serve as a reference Document for User Training and Support.
Page 1 of 81
Course Overview
SAP Project System supports comprehensive functions for planning, controlling and organizing all the activities carried out during the course of a project. It helps you manage your project structures, dates, costs, and resources throughout the entire project lifecycle. Course provides you with an overview of the functions in SAP Project System.
Target Audience
This course is intended for the following audiences: Project managers Project team members Consultants
Course Prerequisites
Knowledge of navigating SAP systems Basic knowledge of project management
Course Goals
This course will prepare you to: Discuss the basic functions of SAP Project System for structuring, planning, executing, and monitoring projects
Course Objectives
After completing this course, you will be able to: Use work breakdown structures, activities, and networks to structure projects Discuss aspects of planning dates, resources, materials, costs, and revenues Name the functions used for budgeting Explain aspects and processes used for executing projects Explain various period-end closing activities in Project Management Use reporting options for monitoring project data
Page 2 of 81
Table of Contents
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. OPERATIVE PROJECT DEFINITION & WBS ...................................................................................... 6 SEND WBS FOR DETAILING/OBSERVATIONS USING NOTE SHEET ...................................... 15 READ NOTE SHEET RECEIVED IN THE SAP INBOX ..................................................................... 16 OPERATIVE NETWORK ....................................................................................................................... 17 ASSIGN INTERNAL ACTIVITY ........................................................................................................... 20 ASSIGN MATERIAL TO AN INTERNAL ACTIVITY ....................................................................... 22 ASSIGN & EXPLODE BILL OF MATERIALS ..................................................................................... 24 ASSIGN SERVICE ACTIVITY .............................................................................................................. 29 ASSIGN GENERAL COST ACTIVITY ................................................................................................. 31 RELATIONSHIP BETWEEN ACTIVITIES .......................................................................................... 32 ATTACH MILESTONE TO AN ACTIVITY ......................................................................................... 34 ATTACH MILESTONE TO A WBS ELEMENT ................................................................................... 35 PROJECT SCHEDULING ....................................................................................................................... 37 CREATE & ASSIGN SURVEY REPORT TO PROJECT ..................................................................... 38 UPDATE THE PROJECT STATUS TO TECHNICALLY APPROVED ............................................. 42 UPDATE THE PROJECT STATUS TO SURVEY DONE. ................................................................... 44 SEND WBS FOR SURVEY APPROVAL TO COMPETENT AUTHORITY ..................................... 45 UPDATE THE PROJECT STATUS TO SURVEY SENT FOR APPROVAL (SRSP) ........................ 46 READ NOTE SHEET RECEIVED IN THE SAP INBOX ..................................................................... 47 UPDATE THE PROJECT STATUS TO SURVEY APPROVED (SRVA) ........................................... 48 UPDATE THE PROJECT STATUS TO PE CREATED ........................................................................ 49 SEND WBS FOR PE APPROVAL TO COMPETENT AUTHORITY USING NOTE SHEET ......... 50 READ NOTE SHEET RECEIVED IN THE SAP INBOX ..................................................................... 51 REVIEW PROJECT ESTIMATE CREATED ......................................................................................... 52
Page 3 of 81
25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47.
UPDATE THE PROJECT STATUS TO PE APPROVED (PEFI) ......................................................... 53 UPDATE THE PROJECT STATUS TO PE SENT FOR APPROVED (PESA) ................................... 54 UPDATE THE PROJECT STATUS TO PE APPROVED (DGM) ....................................................... 55 LINK WBS ELEMENT TO AN INVESTMENT PROGRAM POSITION ......................................... 56 BUDGET DISTRIBUTION TO PROJECT ............................................................................................ 58 CHANGE ORIGINAL BUDGET ........................................................................................................... 59 UPDATE THE PROJECT STATUS TO FUND ALLOCATED............................................................ 61 UPDATE THE PROJECT STATUS TO DETAIL ESTIMATE (DE) CREATED ................................ 62 UPDATE THE PROJECT STATUS TO DETAIL ESTIMATE (DE) APPROVED............................. 63 UPDATE THE SYSTEM STATUS OF A WBS ELEMENT TO RELEASED ...................................... 64 UPDATE THE SYSTEM STATUS OF A NETWORK TO RELEASED .............................................. 65 ACTIVITY CONFIRMATION ............................................................................................................... 66 MILESTONE CONFIRMATION ASSIGNED TO A WBS ELEMENT ............................................. 69 MILESTONE CONFIRMATION ASSIGNED TO AN ACTIVITY ................................................... 69 UPDATE THE PROJECT STATUS TO PRE AT DONE ...................................................................... 71 UPDATE THE PROJECT STATUS TO AT DONE .............................................................................. 72 UPDATE THE STATUS OF A WBS ELEMENT TO TECO (TECHNICALLY COMPLETE) .......... 73 UPDATE THE STATUS OF A NETWORK TO TECO (TECHNICALLY COMPLETE) .................. 74 UPDATE THE PROJECT STATUS TO COMMISSIONING DONE ................................................ 75 UPDATE THE PROJECT STATUS TO MAKE OVER DONE ........................................................... 76 UPDATE THE PROJECT STATUS TO TAKE OVER DONE ............................................................. 77 UPDATE THE SYSTEM STATUS OF A WBS ELEMENT TO CLOSED .......................................... 78 TRANSACTIONS FOR PROJECT MONITORING:- .......................................................................... 79
Page 4 of 81
OVERVIEW
SAP Project System supports comprehensive business Process for Planning, Controlling & Organizing all the activities carried out during the course of a Project. It helps you to manage your Project structure, dates, cost & task throughout the entire Project lifecycle. Western Telecom Projects is responsible for planning, survey and execution of various long distance Telecom Transmission Projects and Switching Projects for building up National Telecom Infrastructure in different Zone for Optical Fiber Cable system, Digital Microwave, Trunk Automatic Exchange (TAX) and Satellite based communication systems in entire Western part of the country which includes states of Maharashtra Gujarat Madhya Pradesh Chattisgarh Goa
Important information to be noted: All documents are to be created in reference to the preceding document. All SAP Transactions can be executed either by navigating to the required Transaction through the Menu Path or by simply entering the Transaction Code for the respective Transaction in the Command Field.
Page 5 of 81
Menu path
Logistics Project system Project Special Maintenance function Work Break Down Structure(WBS) Create CJ01
Transaction
Page 6 of 81
2. Select the appropriate coding mask (For example TP/10/000001) for Project Definition in the Start value. Definition-Open Number-This is the free number available in the System. Press Enter to use the proposed Project Definition
3. Enter Project profile: BSNL_TP Transmission Project (Fig. below) 4. Enter Standard Project Definition (Project to be copied) in the Template section (Refer Fig. below)
Page 7 of 81
Press Enter (Definition-Project profile-This contain default values and control parameters for processing objects and functions in the Project System) 5. Enter description/Short text for Project: 6. Click on Basic data tab (Organization section) and, Enter Company Code, Business Area & Plant (Refer Fig.) For Example: Field Description Person Responsible Start Date Finish Date Company Code Business area Plant Profit Center Remarks Enter the Person Responsible Enter the Start date of Project Enter the Planned finish date of Project Select the relevant Project circle Select the Project Area Select the relevant Plant Select the Relevant Profit center
Page 8 of 81
7. Click on Details Project Definition customer fields & enter the data
Page 9 of 81
Page 10 of 81
9. Click on Include and save. 10. Now, Click on WBS Element Overview
11. Ensure that the PE (Planning Element) indicator is ticked for all the WBS Elements (Except the Level 1 WBS Element)
(Definition-Planning Element: An Element of a work breakdown structure for which costs can be planned) If this indicator is un-ticked for a particular WBS Element, system will not allow cost planning for that WBS Element. 12. Ensure that the Acct(Account Assignment Element) indicator is ticked for all the WBS Elements (Except the Level 1 WBS Element) (Definition-Account Assignment Element: An Element of a work breakdown structure for which Actual Costs can be posted) If this is un-ticked for a particular WBS Element, system will not allow Posting of actual cost on that WBS Element.
Project Type
Page 12 of 81
14. Now, Click on the Dates Tab. Enter the Basic start & Basic Finish Dates for the WBS Element.
15. Click on continue 16. Click on Details WBS Element Customer Fields
Page 13 of 81
Page 14 of 81
Change Project
CJ02
Menu path
Project system Project Special Maintenance Work Break Down Structure(WBS) Change
Transaction
For making any changes in the parameters once the Project is created the above menu path OR the Transaction is to be used.
Display Project
CJ03
Menu path
Project system Project Special Maintenance Work Break Down Structure(WBS) Display
Transaction
Page 15 of 81
In the Comment box add/see the comments and press If you want to see the details of the WBS element in edit mode press If you want to see the details of the WBS element in display mode press To see the comment added by other users Press .
Office SBWP
Workplace
Click on the
The note sheet screen will appear. Add the details and forward it to next level, as explained in the Step-6. Alternatively use the note sheet by the T-Code ZPS_NOTESHEET to open the note sheet.
Page 16 of 81
4. Operative Network
A Network represents the flow of Activities or Tasks in a Project. Network Header can be used to default certain values for all the Activities in that Network.
Create Network CN21
Special Maintenance
1. Select the Network Profile: BSNL_TP Transmission Project Network Profile and press Enter (Refer Fig. below) (Definition-Network Profile- Profiles contain default values and control parameters for processing objects and functions in the Project System) 2. Enter Following data Field Description Network Type Plant MRP Controller Remarks Select ZPS2 Select the relevant Plant Select the Relevant MRP Controller
3. Enter the Std. Network (If required) from which data is to be copied.
Network Profile
Page 17 of 81
5. Go to the Assignments tab and Enter Project Definition and WBS Element (Operative Project).
Page 18 of 81
Change Network Menu path Transaction Logistics Project system Network Change CN22 Project
For making any changes in the Network once it is created the above menu path or the Transaction Code CN22 is to be used.
Page 19 of 81
Display Network Menu path Transaction Logistics Network CN23 Project system Display Project
To view the Network created the above menu path or the Transaction Code CN23 is to be used.
1. Enter the Network number created and press Enter (Refer Fig. below) 2. Go to the Activity Overview .
3. On the Int. processing tab, enter the relevant description and assign it to the relevant WBS Element. (Refer Fig. below)
Select the Line for Activity & Click on details at the bottom left corner of the screen
Page 20 of 81
Page 21 of 81
Menu path
Logistics Project system Project Special Maintenance function Network Change CN22
Transaction
1. Enter the Network number created and press Enter (Refer Fig. below). 2. Click on Activity Overview .
3. Search the relevant Material code through the Search option (F4)
4. Click on Continue.
5. Select the Activity & click on Component Overview at the bottom of screen
Page 22 of 81
6. Enter following data. Material Requirement Qty Item Category Procurement type Line wise enter the Material code required for the Activity Enter quantity to be procured. Enter L for stock item. A submenu opens, where we have to select the required button.
Page 23 of 81
Note:- Procurement Types Reservation for Network: To be used if a reservation is to be created for the Network items kept in stock. Reservation for WBS Element: To be used if a reservation is to be created for the WBS Element items kept in stock. Purchase requisition + Reservation for WBS Element: This creates a MR which will be converted to a Purchase Order and then reserves the received Material for the specific WBS Element. Preliminary Purchase Requisition for WBS Element: Creates a preliminary requisition for a long lead time item. This creates a Preliminary order. After Goods Receipt for the purchase order, a receipt is posted to the Project stock. 3rd party requisition for WBS Element: Creates a 3rd party requisition. The Purchase Order is created telling the Supplier to supply Material to the third party. The Reservation is generated automatically as soon as we assign the Material. In case, Requisition is to be generated, it will get generated on releasing the Network. If the Network is already released, Go to Procurement Parameter tab and modify field res/ Purc req to Immediately When the record is saved, the MR is automatically generated. Continue attaching the remaining required Items. See the details by pressing the detail button and enter the Purchase Group / Purchase Org / Price and currency. The G/L account flows from the settings and should not be changed.
Project
Page 24 of 81
1. Enter the Network number created and press Enter (Refer Fig. below) 2. Click on Activity Overview 3. Select the Activity & Click on Component Overview at the bottom of the screen
4. Enter following data. Material Requirement Qty Item Category Procurement type Line wise enter the Material code required for the Activity Enter quantity to be procured. Enter L for stock item. A submenu opens, where we have to select the required button.
Page 25 of 81
Page 26 of 81
Page 27 of 81
Page 28 of 81
Click on Save
Special Maintenance
1. 2. 3.
Enter the Network number created and press Enter (Refer Fig. below) Go to Activity Overview and click.
On the Ext. Processing tab, Click on the Service Indicator. Enter the relevant description and assign it to the relevant WBS Element. (Refer Fig. below)
4. 5.
Page 29 of 81
Page 30 of 81
Click on Back
6. Click on Continue. Save
Project
1. Enter the Network number created and press Enter (Refer Fig. below) 2. Go to Activity Overview .
3. On the Prim. Costs tab, enter the relevant description and assign it to the relevant WBS Element. (Refer Fig. below)
Page 31 of 81
Click on Save
Project
Page 32 of 81
4. Click on
5. Activities can be linked together by assigning FS/SF/FF/SS relation by clicking on the connect tab
Page 33 of 81
1. Enter the Network number created and press Enter (Refer Fig. below) 2. Go to Activity Overview 3. Select the Activity. 4. Click on Milestone Overview. 5. Milestone can be attcahed by following methods : a) Use Standard Milestone Click on Standard Milestone at the Bottom of screen & Search for suitable Milestone. b) Use Milestone Group Click on Milestone Group at the bottom of screen .Search & select the suitable Miestone Group. Double click on the relevant Milestone Group. All the Milestones assigned to the group will be displayed on the screen . c) Define milestone Enter the Milestone Usage & Description.
Page 34 of 81
1. Enter the WBS Element and press Enter (Refer Fig. below)
Page 35 of 81
5. Milestone can be attcahed through the following methods : a) Use Standard Milestone Click on Standard Milestone at the Bottom of the screen & Search for the relevant Milestone. b) Use Milestone Group Click on Milestone Group at the bottom of the screen . Search & select the relevant Miestone Group. Press Enter & double click on the Milestone. c) Define milestone Enter the Milestone Usage & Description. 6. Select the Row of a Milestone & Click on details
7. Enter the Plan Date of finish in Fix`Date & Percentage of completion. 8. Click on continue. Save
Page 36 of 81
Logistics CJ29
Project system
Dates
Scheduling
1. Enter the Project number 2. Click on the Sched. Basic dates button
Page 37 of 81
. Scheduling Carried out to Check Scheduled Dates for the WBS Element.
6. Select the TOP WBS Element. 7. Click on to view Gantt chart. 8. Click on Save (Ctrl+S)
Document Management
1. On the entry screen, enter the Document Type 2. Enter the Document version 3. Press Enter
Page 38 of 81
4. Enter the Description of document 5. Click on open original at the bottom of screen
8. Save the document. An internal no. will be generated. Note down the No.
Change WBS Menu path Logistics function CJ02 Project system WBS Change Project Special Maintenance
CJ02
Transaction
1. Enter the WBS Element No. Press enter. 2. Select the WBS Element. Click on WBS Element Document Overview
Page 40 of 81
3. Select the document type. 4. Select the document by using search option
Page 41 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on
Page 42 of 81
5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 43 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status. 6. Click on Back & check the new status
Page 44 of 81
17. Send WBS for Survey Approval to competent Authority using Note Sheet
ZPS_NOTESHEET
Use the T-Code ZPS_NOTESHEET to open the Note sheet. Enter the WBS element and employee id of the person to whom the note sheet is to be sent.
In the Comment box add/see the comments and press If you want to see the details of the WBS element in edit mode press If you want to see the details of the WBS element in display mode press To see the comment added by other users Press .
Page 45 of 81
18. Update the Project Status to Survey sent for Approval (SRSP)
Change WBS CJ02
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 46 of 81
Office SBWP
Workplace
Click on the
The note sheet screen will appear. Add the details and forward it to next level, as explained in the Step-6. Alternatively use the note sheet by the T-Code ZPS_NOTESHEET to open the note sheet.
Page 47 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 48 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 49 of 81
22. Send WBS for PE Approval to competent Authority using Note Sheet
ZPS_NOTESHEET
Use the T-Code ZPS_NOTESHEET to open the Note sheet. Enter the WBS element and employee id of the person to whom the note sheet is to be sent.
In the Comment box add/see the comments and press If you want to see the details of the WBS element in edit mode press If you want to see the details of the WBS element in display mode press To see the comment added by other users Press .
Page 50 of 81
Office SBWP
Workplace
Click on the
The note sheet screen will appear. Add the details and forward it to next level, as explained in the Step-6. Alternatively use the note sheet by the T-Code ZPS_NOTESHEET to open the note sheet.
Page 51 of 81
1. Enter PS Info prof. 000000000001 2. Enter Project number and the Plan version as 0.
5. Click on Back.
Page 52 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 53 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 54 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 55 of 81
Project
1. Select the Relevant WBS Element 2. Follow the path as shown below:
Page 56 of 81
Page 57 of 81
5. Click on Continue. 6. Similarly assign the relevant IM Position to other WBS Elements.
Click on Save.
Programs
Budgeting
1. Enter Investment Program, Position ID & Approval Year in the selection screen 2. Click on Execute.
Page 58 of 81
Planning
1. On the entry screen, enter the WBS Element No. & Press enter
Page 59 of 81
2. Select the Period. 3. Select the rows of WBS Elements. Click on Edit Copy View & Copy the Planned Value to copt the cost planned for WBS.
Page 60 of 81
Logistics Project System Project Special Maintenance Functions Work Break Down Structure (WBS) Change CJ02
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 61 of 81
Logistics Project System Project Special Maintenance Functions Work Break Down Structure (WBS) Change CJ02
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status.
Page 62 of 81
Logistics Project System Project Special Maintenance Functions Work Break Down Structure (WBS) Change CJ02
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status.
Page 63 of 81
Logistics Project System Project Special Maintenance Functions Work Break Down Structure (WBS) Change CJ02
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element 3. Go to Menu to Menu Bar Edit Option Status Release (Refer Fig. below)
Following error message might appear while changing the status to Release.
Page 64 of 81
6. 7.
Similarly change the status of all other WBS Elements & the the Project Definition. Click on Save
Special Maintenance
1. Enter the Network No. 2. Go to Menu Bar Edit Option Status Release (Refer Fig. below)
Page 65 of 81
1. Go to the Activity Overview on the Header Details screen of the Network :2. Go to the tab for Int. Processing as shown below and select the internal activity
Page 66 of 81
4. On the Next screen carry out the following steps for Partial Confirmation of the Activity:5. Enter the Start and Finish Date in the respective fields as shown below:-
Page 67 of 81
6. Select the Reason by selecting the Reason ID 7. Press Enter. 8. Click on the Back button. 9. Save the Network. 10. Ignore the Warnings. 11. Click on Final Confirmation and Completed Indicators for Full and Final Confirmation by repeating the above steps for the same activity
Page 68 of 81
Logistics Project system Project Special Maintenance function WBS Change CJ02
1. Enter the WBS Element No. and press Enter (Refer Fig. below) 2. Go to WBS Element Overview. 3. Select the WBS Element. 4. Click on Milestone Overview.
5. Select the Row of a Milestone & Click on details
Project
1. Enter the Network no. and press Enter (Refer Fig. below) 2. Go to Activity Overview. 3. Select the relevant Activity.
Page 69 of 81
4. Click on Milestone Overview at the bottom of the screen 5. Select the Row of a Milestone & Click on details
Page 70 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status.
Page 71 of 81
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status.
Page 72 of 81
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Go to the Menu Edit Status Technically Complete (Refer Fig. below)
4. This will change the System Status of the WBS Element to Technically Complete.
Page 73 of 81
Change Network
Special Maintenance
1. Enter the Network No. 2. Go to Edit Status Close Technically (Refer Fig. below)
Page 74 of 81
Project
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status.
Page 75 of 81
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 76 of 81
Menu path
Project
Transaction
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Click on details
4. Click on 5. Check the Status Profile. Select the relevant status. 6. Click on Back & Check the new status
Page 77 of 81
Logistics Project System Project Special Maintenance Functions Work Break Down Structure (WBS) Change CJ02
1. Enter the WBS Element No. Press Enter. 2. Select the WBS Element. 3. Go to Menu to Menu Bar Edit Option Status CLSD (Refer Fig. below)
4. This will change the System Status from Technically Complete to Closed.
Page 78 of 81
47.Transactions for Project Monitoring:1. Monitor Project Structure (CN41) Enter Database Profile Value after executing the Transaction Code
Enter the Following Information: Project Definition, WBS element or Network No. in Single or Multiple Selection Press Execute Note the Output To Change the layout click on the icon fields. on the top and select the desired
Page 79 of 81
Remarks:- In the output of this report user can access information as per a no. of categories viz.
2. Monitor Project Cost (CJI3) Enter Controlling Area :- 1000 Enter Database Profile:- 000000000001 Enter the Following Information:Project Definition, WBS element or Network No. in Single or Multiple Selection Press Execute Note the Output
3. Monitor Project Milestones (CN53) Enter Controlling Area :- 1000 Enter Database Profile:- 000000000001 Enter the Following Information:Project Definition, WBS element or Network No. in Single or Multiple Selection Press Execute Note the Output
Page 80 of 81