Project Reference Project Reference

San Juan Crossing


Balanced Cantilever Bridge
Country Philippines Client: Consultant: Specialist PT Contractor: Years of Execution: Location San Juan River, Calamba, Philippines JTC International BBR Systems Ltd BBR Construction Systems (M) Sdn Bhd July 1998 to August 1999

March 2004

Project No P0127

Project Description: The San Juan bridge is built by the cast in-situ balanced cantilever method. The entire bridge was designed by BBR Construction Systems, including the design and fabrication of the form carriers used in the construction. A construction cycle of 7 days for every two segments was made possible by the efficient design and simple operation of the form carrier.

Main Span : Back span : Total width of deck : Post-tensioned system : Balanced Cantilever Form carrier: Bridge Contractor :

90 metres 50 metres each 17 m BBR CONA Bonded System BBR Construction Systems BBR JV -JH Pahara Construction Corporation

Headquarters

BBR CONSTRUCTION SYSTEMS (M) SDN BHD


32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my Website: www.bbr.com.my

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Project Reference Project Reference


Sg. Besi Highway
Precast Segmental Construction
Country Malaysia Client: Consultant: Contractor: Years of Execution: Location Kuala Lumpur Besraya Sdn Bhd Robert Beniam Associates Road Builder (M) Sdn Bhd June 1998 to February 1999

March 2004

Project No P0119

Project Description: The two interchanges leading to the upgraded Sungai Besi was built using the precast segmental box sections, erected by the balanced cantilever method. The prestressed tendons used are BBR CONA Bonded Internal System. The BBR CONA Bonded system utilizes 0.6 diameter strands. The tendons are installed inside galvanised ducts, stressed and grouted with cement grout. Tendons size Strands specification Cross section area Ultimate Breaking Strength : : : : 195 ASTM A416 140mm 261 kN

Headquarters

BBR CONSTRUCTION SYSTEMS (M) SDN BHD

32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my Website: www.bbr.com.my

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Project Reference Project Reference


Batang Baram, Miri, Sarawak
Balanced Cantilever Bridge
Country Malaysia Client: Turnkey Contractor: Main Contractor: Consulting Engineers: Years of Construction: Location Sg. Baram, Miri, Sarawak JKR, Sarawak Woodville Development Sdn Bhd BBR Construction Systems (M) Sdn Bhd
in Association with CARNO MBK International Australia

March 2004

Project No P0205

KTA (Sarawak) Sdn Bhd

June 2001 to October 2003

Structural Characteristic:Main Span Anchor Span Approach Spans : : : 180m 109.7m 2 x 8 spans x 40m Precast post-tensioned T-beams (H = 2.2m) 20.5m BBR CONA Bonded Systems

Deck Width : Post-tensioned system :

Project Description: Batang Baram cast in-situ balanced Cantilever Bridge is part of the 1.04km long crossing over Baram River. On completion, this will be the first land crossing linking the town of Miri, Sarawak and Brunei and it will be the longest cast in-situ balanced cantilever bridge in Malaysia.

Headquarters 32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail:bbrm@bbr.com.my Website: www.bbr.com.my

BBR CONSTRUCTION SYSTEMS (M) SDN BHD

Kuching Branchs No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce, 93150 Kuching, Sarawak, Malaysia. Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

P r oj ect R ef er e nce Project Reference


Jeli, Sg. Galas, Kelantan Bridge
Balanced Cantilever and U Beam
Country Malaysia Client: Consultant: Turnkey Contractor: Years of Execution: Location Kelantan Jabatan Kerja Raya Nik Jai Associates Arena Engineering Sdn Bhd December 2001 In progress

July 2005

Project No P0219

Project Description: The bridge consists of a cast in-situ balanced cantilever box girder with a main span of 90m and 2 side spans of 50m each. 2 approach spans on each side of the bridge are designed using 30m precast U-beam and slab. The bridge deck wide is 12m with maximum box depth of 5.2m over the main pier.

Headquarters

BBR CONSTRUCTION SYSTEMS (M) SDN BHD


32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my Website: www.bbr.com.my

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Project Reference Project Reference


Cantilevering River Span With Insitu Anchor Span
Country Malaysia Client: Bridge Contractor: Consulting Engineers: Years of Execution: Location Sg Sebelak, Sri Aman, Sarawak JKR, Sarawak BBR Construction Systems (M) Sdn Bhd TCS Consulting Engineers Sept 2002 to March 2005

December 2004

Sg Sebelak Bridge, Jln Pusa Ke Sesang, Sarawak


Project No. P0243

Structural Characteristics:Main Span Anchor Span Deck Width Post-tensioned system : : : : 120m 65m 11.5m BBR Cona Bonded System

Project Description:The anchor span between the abutment and main pier is constructed on heavy duty scaffoldings. Upon completion of hammerhead, form traveler is installed to cast the 4m length segments over the main (river) span. Due to the low height of the two piers, the bridge was designed to rest on pot bearings. Upon stressing of cantilever tendons, the top hung form traveler was advanced forward for the next casting. Typical cycle period is 7 days.

Headquarters

BBR CONSTRUCTION SYSTEMS (M) SDN BHD

32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Project Reference Project Reference


New Pantai Highway Bridge 19, 22, 23, & 24
Post Tensioning Works
Country Malaysia Client: Consultant: Bridge Contractor: Years of Execution: Project Description: The four viaducts to upgrade New Pantai Highway are being built using precast segmental box sections, erected by balanced cantilever method. The prestressed tendons used are BBR CONA Bonded Internal System. The system utilizes 0.6(15.24mm) diameter strands. The tendons are threaded into the grouted precast galvanized ducts, stressed and grouted with cement grout. Tendons size Strands specification Cross section area Ultimate Breaking Strength : : : : 12O6 ASTM A416 140mm2 261 kN Location Selangor Darul Ehsan Road Builder (M) Sdn Bhd RB Perunding Sdn Bhd (Robert Beniam) BBR Construction Systems (M) Sdn Bhd February 2003 to In progress

August 2005

Project No P0262

Headquarters

BBR CONSTRUCTION SYSTEMS (M) SDN BHD

32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my Website: www.bbr.com.my

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Project Reference Project Reference


Post Tensioning Works
Country Malaysia Client: Consultant: Main Contractor: Specialist Contractor: Years of Execution: Project Description: Structural Characteristics Main Span Anchor Span Deck Width : : : 100m 55m 10m BBR Cona Bonded System Location Pahang JKR HSS Integrated Sdn Bhd Latimer Corporation Sdn Bhd BBR Construction Systems (M) Sdn Bhd December 2003 to In progress

August 2005

Road Construction at Pakej 3/1A, Simpang Pulai


Project No P0268

Post-Tensioned System :

Headquarters 32 Jalan PJS 11/20, Sunway Technology Park, Bandar Sunway, 46150 Subang Jaya, Selangor D Ehsan, Malaysia Tel: 603 5636 3270 Fax: 603 5636 3285 E-mail: bbrm@bbr.com.my Website: www.bbr.com.my

BBR CONSTRUCTION SYSTEMS (M) SDN BHD

Kuching Branch No. 2.21, Lot 3005, Jalan Tun Ahmad Zaidi Adruce 93150 Kuching, Sarawak, Malaysia Tel: (6082)-248591 Fax: (6082)-248594 E-mail: bbrkch@tm.net.my

A Member of the

Group of Companies

Вам также может понравиться