7) Platforms and Facilities

Ebok field operations summary of current work

Phase 1 well planning defined FPSO status


-

two main contenders have submitted bids. Currently under review

Wellhead platform options have been identified MOPU/FSO development solution in progress
-

has potential to be a competitive solution with full field capabilities seven rigs identified all fit for purpose five immediately available indicative day rate of circa US$100,000/day

Drilling units short list compiled


-

EHSS regulatory compliance process well underway

Ebok drilling operations

Ebok development Phase 1

Development criteria Water depth 140 ft Initial production early 2010 Minimum oil rate of 20,000 BOPD Minimum water rate of 20,000 BWPD Gas lift on initial completion Water injection on initial completion

Platforms and facilities

Ebok Phase 1 development - facilities


FPSOs /MOPU Several proposals have been evaluated to date for FPSOs / MOPUs / FSOs MOPU and FSO appears to be the most appropriate Wellhead support structures Multiple wellhead refurbishment platforms are available for modification and

Preliminary engineering is continuing on a possible wellhead support structure in association with a FPSO and a freestanding conductor supported structure if the MOPU is used

Platforms and facilities

FPSOs summary of general specifications

Vessel 1
Cargo Storage Volume Processing Capacity Max. Liquid Rate Max. Oil Rate Max.Water Rate Max. Gas Rate Gas Compression Pressure Water Injection Pressure BBLS BPD BOPD BWPD MMCF/D MMCF/D psig BWIPD psig 625,000 121,000 57,000 100,000 20 20 2,475 70,000 4,170

Vessel 2
510,000 25,000 20,000 12,500 10 7 1,800 15,000 2,500

Platforms and facilities

New wellhead platform?

Platforms and facilities

Refurbished wellhead platform clear advantages

Cost efficiencies Speed Higher specification than a new-build Fit for purpose

Platforms and facilities

Advantages of a MOPU vs FPSO

Flexible drilling schedule Does not require a lift barge Immediate access to produced fluid from wellhead Savings on well support structure Savings on flowlines Easier & more cost effective to expand for a full field development

Platforms and facilities

Ebok field development - MOPU / FSO option

Platforms and facilities

Ebok field development. MOPU - FSO option


Key features of MOPU for Ebok

Platforms and facilities

10

Ebok field development - MOPU / FSO option

Storage capacity 1,300,000 bbl Spread Moored DPR approved Fiscal metering unit Helideck Tank heating (if required) Accommodation 32 persons Delivery time 8 months

Platforms and facilities

11

Ebok field development - MOPU / FSO option


Wellhead Support Structure. Eliminates the need for a WHP

Platforms and facilities

12

Ebok field development - MOPU / FSO option


Wellhead Support Structure

Platforms and facilities

13

Ebok field development - MOPU / FSO option


Wellhead Support Structure

WSS

Platforms and facilities

14

Gas solution

Low GOR oil:

D1 70scf/stb D2 315scf/stb

Requirements for gas Gas lift gas for all producing wells
-

estimated per well requirement 3mmscfg/d

Fuel gas requirement for FPSO power generation Ebok-4 has been T&Ad with a mud-line suspension
-

will be used to re-inject any surplus gas to comply with Government regulations.

At this point in time it is considered unlikely that there will be any spare gas for re-injection