Вы находитесь на странице: 1из 5

DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5

REPAIR WORKS FOR BIOREACTOR -5 SEWERAGE TREATMENT PLANT -DOHA NORTH

05-Apr-12 13:41

Activity ID

Activity Name

Original Start Duration

Finish Apr

Qtr 2, 2012 May Jun

Qtr 3, 2012 Jul 07-

DOHA NORTH SEW SEWERAGE TRATMENT PLANT-BIOREACTOR 5


GENERAL
SWT-G-1000 SWT-G-1010 Preparation & Submission of Detailed Repair Methodology Management rep Approval of Detailed Repair Methodology Management report

76d 10-Apr-12 07-Jul-12 19d 10-Apr-12 01-May-12 5d 10-Apr-12 15-Apr-12 14d 16-Apr-12 01-May-12 57d 02-May-12 07-Jul-12 56d 02-May-12 05-Jul-12 18d 02-May-12 22-May-12 10d 02-May-12 13-May-12 2d 13-May-12 14-May-12 2d 14-May-12 15-May-12 2d 15-May-12 16-May-12 1d 17-May-12 17-May-12 1d 21-May-12 21-May-12 1d 22-May-12 22-May-12 26d 02-May-12 31-May-12 10d 02-May-12 13-May-12 2d 13-May-12 14-May-12 2d 14-May-12 15-May-12 2d 24-May-12 26-May-12 1d 27-May-12 27-May-12 1d 30-May-12 30-May-12 1d 31-May-12 31-May-12 18d 02-May-12 22-May-12 10d 02-May-12 13-May-12 2d 13-May-12 14-May-12 2d 14-May-12 15-May-12 2d 15-May-12 16-May-12 1d 17-May-12 17-May-12 1d 21-May-12 21-May-12 1d 22-May-12 22-May-12 35d 02-May-12 11-Jun-12 10d 02-May-12 13-May-12 2d 13-May-12 14-May-12 2d 14-May-12 15-May-12 2d 04-Jun-12 05-Jun-12 1d 06-Jun-12 06-Jun-12 1d 10-Jun-12 10-Jun-12 1d 11-Jun-12 11-Jun-12 18d 14-May-12 03-Jun-12 10d 14-May-12 24-May-12 2d 24-May-12 26-May-12 Date Revision Checked Approved 1 22-May-12, PANEL-1 Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab 31-May-12, PANEL-2 Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab 22-May-12, PANEL-A Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab 11-Jun-12, PANEL- B Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base 01-May-12, GENERAL Preparation & Submission of Detailed Repair Methodology Management report Approval of Detailed Repair Methodology Management report

CONSTRUCTION PH PHASE- REPAIR WORKS


INTERIOR EXPANSION J JOINT AND MEMBRANE (NEAR GRID 9)
PANEL-1 SWT-CP-1030 SWT-CP-1031 SWT-CP-1032 SWT-CP-1033 SWT-CP-1034 SWT-CP-1035 SWT-CP-1036 PANEL-2 SWT-CP-1220 SWT-CP-1230 SWT-CP-1240 SWT-CP-1250 SWT-CP-1260 SWT-CP-1270 SWT-CP-1280 PANEL-A SWT-CP-1290 SWT-CP-1300 SWT-CP-1310 SWT-CP-1320 SWT-CP-1330 SWT-CP-1340 SWT-CP-1350 PANEL- B SWT-CP-1360 SWT-CP-1370 SWT-CP-1380 SWT-CP-1390 SWT-CP-1400 SWT-CP-1410 SWT-CP-1420 PANEL- C SWT-CP-1430 SWT-CP-1440 Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Summary

0705-Jul-

Expansion joint,Reinforcement fixing and shuttering of Concreting of floor slab 03-Jun-12, PANEL- C Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation

DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5

REPAIR WORKS FOR BIOREACTOR -5 SEWERAGE TREATMENT PLANT -DOHA NORTH

05-Apr-12 13:41

Activity ID SWT-CP-1450 SWT-CP-1460 SWT-CP-1470 SWT-CP-1480 SWT-CP-1490 PANEL- D SWT-CP-1500 SWT-CP-1510 SWT-CP-1520 SWT-CP-1530 SWT-CP-1540 SWT-CP-1550 SWT-CP-1560 PANEL- E SWT-CP-1570 SWT-CP-1580 SWT-CP-1590 SWT-CP-1600 SWT-CP-1610 SWT-CP-1620 SWT-CP-1630 PANEL- F SWT-CP-1640 SWT-CP-1650 SWT-CP-1660 SWT-CP-1670 SWT-CP-1680 SWT-CP-1690 SWT-CP-1700 PANEL- G SWT-CP-1710 SWT-CP-1720 SWT-CP-1730 SWT-CP-1740 SWT-CP-1750 SWT-CP-1760 SWT-CP-1770 PANEL- H SWT-CP-1780 SWT-CP-1790 SWT-CP-1800 SWT-CP-1810 Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone

Activity Name Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Summary

Original Start Duration

Finish Apr

Qtr 2, 2012 May Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Jun

Qtr 3, 2012 Jul

2d 26-May-12 27-May-12 2d 27-May-12 28-May-12 1d 29-May-12 29-May-12 1d 02-Jun-12 02-Jun-12 1d 03-Jun-12 03-Jun-12 26d 14-May-12 12-Jun-12 10d 14-May-12 24-May-12 2d 24-May-12 26-May-12 2d 26-May-12 27-May-12 2d 04-Jun-12 05-Jun-12 1d 06-Jun-12 06-Jun-12 1d 10-Jun-12 10-Jun-12 1d 12-Jun-12 12-Jun-12 18d 14-May-12 03-Jun-12 10d 14-May-12 24-May-12 2d 24-May-12 26-May-12 2d 26-May-12 27-May-12 2d 27-May-12 28-May-12 1d 29-May-12 29-May-12 1d 02-Jun-12 02-Jun-12 1d 03-Jun-12 03-Jun-12 35d 14-May-12 23-Jun-12 10d 14-May-12 24-May-12 2d 24-May-12 26-May-12 2d 26-May-12 27-May-12 2d 16-Jun-12 17-Jun-12 1d 18-Jun-12 18-Jun-12 1d 21-Jun-12 21-Jun-12 1d 23-Jun-12 23-Jun-12 18d 26-May-12 14-Jun-12 10d 26-May-12 05-Jun-12 2d 05-Jun-12 06-Jun-12 2d 06-Jun-12 07-Jun-12 2d 07-Jun-12 09-Jun-12 1d 10-Jun-12 10-Jun-12 1d 13-Jun-12 13-Jun-12 1d 14-Jun-12 14-Jun-12 26d 26-May-12 24-Jun-12 10d 26-May-12 05-Jun-12 2d 05-Jun-12 06-Jun-12 2d 06-Jun-12 07-Jun-12 2d 16-Jun-12 17-Jun-12 Date Revision Checked Approved 2

Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab 12-Jun-12, PANEL- D Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of Concreting of floor slab 03-Jun-12, PANEL- E Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab 23-Jun-12, PANEL- F Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall Concreting of wall base Expansion joint,Reinforcement fix Concreting of floor slab 14-Jun-12, PANEL- G Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shutter Concreting of floor slab 24-Jun-12, PANEL- H Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall

DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5

REPAIR WORKS FOR BIOREACTOR -5 SEWERAGE TREATMENT PLANT -DOHA NORTH

05-Apr-12 13:41

Activity ID SWT-CP-1820 SWT-CP-1830 SWT-CP-1840 PANEL- I SWT-CP-1850 SWT-CP-1860 SWT-CP-1870 SWT-CP-1880 SWT-CP-1890 SWT-CP-1900 SWT-CP-1910 PANEL- J SWT-CP-1920 SWT-CP-1930 SWT-CP-1940 SWT-CP-1950 SWT-CP-1960 SWT-CP-1970 SWT-CP-1980 PANEL- K SWT-CP-1990 SWT-CP-2000 SWT-CP-2010 SWT-CP-2020 SWT-CP-2030 SWT-CP-2040 SWT-CP-2050 PANEL- L SWT-CP-2060 SWT-CP-2070 SWT-CP-2080 SWT-CP-2090 SWT-CP-2100 SWT-CP-2110 SWT-CP-2120 PANEL- M SWT-CP-2200 SWT-CP-2210 SWT-CP-2220 SWT-CP-2230 SWT-CP-2240 SWT-CP-2250 Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone

Activity Name Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Summary

Original Start Duration

Finish Apr

Qtr 2, 2012 May Jun Concreting of wall base

Qtr 3, 2012 Jul Expansion joint,Reinforcement fix Concreting of floor slab 14-Jun-12, PANEL- I Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shutter Concreting of floor slab 04-Jul-12 Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing Concreting of wa Expansion Concretin 26-Jun-12, PANEL- K Manual Break Out of Existing Joint Along Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering o Concreting of wall base Expansion joint,Reinforcem Concreting of floor slab 05-JulManual Break Out of Existing Joint Along Cleaning and Surface preparation Waterproofing works Reinforcement fixing Concreting of wa Expansion Concre 26-Jun-12, PANEL- M Manual Break Out of Existing Joint Along Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering o Concreting of wall base Expansion joint,Reinforcem

1d 18-Jun-12 18-Jun-12 1d 21-Jun-12 21-Jun-12 1d 24-Jun-12 24-Jun-12 18d 26-May-12 14-Jun-12 10d 26-May-12 05-Jun-12 2d 05-Jun-12 06-Jun-12 2d 06-Jun-12 07-Jun-12 2d 07-Jun-12 09-Jun-12 1d 10-Jun-12 10-Jun-12 1d 13-Jun-12 13-Jun-12 1d 14-Jun-12 14-Jun-12 35d 26-May-12 04-Jul-12 10d 26-May-12 05-Jun-12 2d 05-Jun-12 06-Jun-12 2d 06-Jun-12 07-Jun-12 2d 27-Jun-12 28-Jun-12 1d 30-Jun-12 30-Jun-12 1d 03-Jul-12 1d 04-Jul-12 03-Jul-12 04-Jul-12

18d 06-Jun-12 26-Jun-12 10d 06-Jun-12 17-Jun-12 2d 17-Jun-12 18-Jun-12 2d 18-Jun-12 19-Jun-12 2d 19-Jun-12 20-Jun-12 1d 21-Jun-12 21-Jun-12 1d 25-Jun-12 25-Jun-12 1d 26-Jun-12 26-Jun-12 26d 06-Jun-12 05-Jul-12 10d 06-Jun-12 17-Jun-12 2d 17-Jun-12 18-Jun-12 2d 18-Jun-12 19-Jun-12 2d 27-Jun-12 28-Jun-12 1d 30-Jun-12 30-Jun-12 1d 03-Jul-12 1d 05-Jul-12 03-Jul-12 05-Jul-12

18d 06-Jun-12 26-Jun-12 10d 06-Jun-12 17-Jun-12 2d 17-Jun-12 18-Jun-12 2d 18-Jun-12 19-Jun-12 2d 19-Jun-12 20-Jun-12 1d 21-Jun-12 21-Jun-12 1d 25-Jun-12 25-Jun-12 Date Revision Checked Approved 3

DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5

REPAIR WORKS FOR BIOREACTOR -5 SEWERAGE TREATMENT PLANT -DOHA NORTH

05-Apr-12 13:41

Activity ID SWT-CP-2260 PANEL- N SWT-CP-2130 SWT-CP-2140 SWT-CP-2150 SWT-CP-2160 SWT-CP-2170 SWT-CP-2180 SWT-CP-2190 SWT-CP-2270 SWT-CP-1060 SWT-CP-1070 SWT-CP-1080 TYPE-1 SWT-CP-1090 SWT-CP-1091 SWT-CP-1092 SWT-CP-1100 TYPE-2 SWT-CP-1110 SWT-CP-1120 NORTH FACE SWT-CP-2280 SWT-CP-2290 SWT-CP-2300 SWT-CP-2310 EAST FACE SWT-CP-2360 SWT-CP-2370 SWT-CP-2380 SWT-CP-2390 SWT-CP-2400 SWT-CP-2410 SOUTH FACE SWT-CP-2320 SWT-CP-2330 SWT-CP-2340 SWT-CP-2350

Activity Name Concreting of floor slab Manual Break Out of Existing Joint Along Grid 9 Cleaning and Surface preparation Waterproofing works Reinforcement fixing & Shuttering of wall base Concreting of wall base Expansion joint,Reinforcement fixing and shuttering of floor slab Concreting of floor slab Installetion of sealents Near grid 9 Removal of sealents on Floor joints Grinding of side edges and cleaning Installation of new sealants

Original Start Duration

Finish Apr

Qtr 2, 2012 May Jun

Qtr 3, 2012 Jul Concreting of floor slab 04-Jul-12 Manual Break Out of Existing Joint Along Cleaning and Surface preparation Waterproofing works Reinforcement fixing Concreting of wa Expansion Concretin Installetio 30-Jun-12, SEAL Removal of sealents on Floor Grinding of side edg Installation of ne 30-Jun-12, SEAL 06-Jun-12, TYPE-1 Break out of joints (Incl of necesssary stagging arrangement) Surface preparation works and cleaning Grouting the Wall surface Replacement Sealant 30-Jun-12, TYPE Sealant Removal , Grinding and cleanin Installation of ne 20-Jun-12, MASS CONCRETING 22-May-12, NORTH FACE

1d 26-Jun-12 26-Jun-12 25d 06-Jun-12 04-Jul-12 10d 06-Jun-12 17-Jun-12 2d 17-Jun-12 18-Jun-12 2d 18-Jun-12 19-Jun-12 2d 27-Jun-12 28-Jun-12 1d 30-Jun-12 30-Jun-12 1d 03-Jul-12 1d 04-Jul-12 03-Jul-12 04-Jul-12

25d 06-Jun-12 04-Jul-12 36d 20-May-12 30-Jun-12 30d 20-May-12 23-Jun-12 30d 26-May-12 28-Jun-12 15d 13-Jun-12 30-Jun-12 51d 02-May-12 30-Jun-12 31d 02-May-12 06-Jun-12 25d 02-May-12 30-May-12 20d 10-May-12 02-Jun-12 15d 19-May-12 04-Jun-12 10d 27-May-12 06-Jun-12 20d 07-Jun-12 30-Jun-12 10d 07-Jun-12 18-Jun-12 10d 19-Jun-12 30-Jun-12 43d 02-May-12 20-Jun-12 18d 02-May-12 22-May-12 13d 02-May-12 16-May-12 8d 09-May-12 17-May-12 5d 15-May-12 20-May-12 1d 22-May-12 22-May-12 34d 06-May-12 13-Jun-12 24d 06-May-12 02-Jun-12 15d 19-May-12 04-Jun-12 6d 30-May-12 05-Jun-12 1d 06-Jun-12 06-Jun-12 4d 09-Jun-12 12-Jun-12 1d 13-Jun-12 13-Jun-12 35d 12-May-12 20-Jun-12 13d 12-May-12 26-May-12 10d 05-Jun-12 16-Jun-12 5d 13-Jun-12 18-Jun-12 1d 20-Jun-12 20-Jun-12 37d 26-May-12 07-Jul-12 Surface preparation along the concrete face Water profing on all sides Shuttering in Noth Concrete Face (4 Panels) Mass concreting in North Face (4 Panels) 13-Jun-12, EAST FACE Surface preparation along the concrete face Water profing on all sides

SEALANT IN FLOOR JOIN JOINTS

SEALANT IN WALL JOINT JOINTS


Break out of joints (Incl of necesssary stagging arrangement) Surface preparation works and cleaning Grouting the Wall surface Replacement Sealant Sealant Removal , Grinding and cleaning Installation of new Sealants

MASS CONCRETING FRO ROCK FACE FROM


Surface preparation along the concrete face Water profing on all sides Shuttering in Noth Concrete Face (4 Panels) Mass concreting in North Face (4 Panels) Surface preparation along the concrete face Water profing on all sides Shuttering in East Concrete Face (1-5 Panels) Mass concreting in East Face (1-5 Panels) Shuttering in East Concrete Face (6-9 Panels) Mass concreting in East Face (6-9 Panels) Surface preparation along the concrete face Water profing on all sides Shuttering in South Concrete Face (4 Panels) Mass concreting in South Face (4 Panels)

Shuttering in East Concrete Face (1-5 Panels) Mass concreting in East Face (1-5 Panels) Shuttering in East Concrete Face (6-9 Panels) Mass concreting in East Face (6-9 Panels) 20-Jun-12, SOUTH FACE Surface preparation along the concrete face Water profing on all sides Shuttering in South Concrete Face (4 Mass concreting in South Face (4 P 07Checked Approved 4

SHEAR KEY FILLING


Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Summary Date

Revision

DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5

REPAIR WORKS FOR BIOREACTOR -5 SEWERAGE TREATMENT PLANT -DOHA NORTH

05-Apr-12 13:41

Activity ID SWT-CP-1160 SWT-CP-1170 SWT-CP-1180 SWT-CP-1190 SWT-CP-1200

Activity Name Grouting of identified shearkey locations in North Side Grouting of identified shearkey locations in East Side Grouting of identified shearkey locations in South Side Sealing by Epoxy injection on cracked surfaces Saw Cutting and Sealing in Construction joint surfaces

Original Start Duration

Finish Apr

Qtr 2, 2012 May Jun

Qtr 3, 2012 Jul Grouting of identified s Gro 17-Jun-12, WALKWAY REPAIRING WO Sealing by Epoxy injection on cracked surfaces Saw Cutting and Sealing in Construction 07Rem Han Grouting of identified shearkey locations in Nor

18d 26-May-12 14-Jun-12 10d 17-Jun-12 27-Jun-12 8d 28-Jun-12 07-Jul-12 40d 02-May-12 17-Jun-12 30d 02-May-12 05-Jun-12 30d 14-May-12 17-Jun-12 55d 05-May-12 07-Jul-12

WALKWAY REPAIRING W WORKS

HANDINGOVER
SWT-CP-1205 SWT-CP-1210 Removal of debris and cleaning of site Handing over

55d 05-May-12 07-Jul-12 0d 07-Jul-12

Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone

Summary

Date

Revision

Checked

Approved