Академический Документы
Профессиональный Документы
Культура Документы
We do not subsidise
Invested 64.9 bn in more than 3,268 projects since 1991* Private sector > 78.3% of portfolio Portfolio is 80% Debt, 20% Equity AAA rating, 30bn base capital 9bn invested in 2010, a 77% increase since 2008
* through 07 November, 2011
billion
12 65
10
55
45 8 35 6 25 4 15
0 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
-5
Debt ABV
Equity ABV
EBRD Facilities
LOANS
Project finance loans Corporate loans with specified use of proceeds Tenor of 10-15 years Margin benchmarked to market Fixed rate and/or local currency possible EBRD can directly finance up to 35% of an enterprise's long term capital (or project costs for greenfield projects); additional funds mobilized through syndication
EQUITY
EBRD equity stake typically below 2025% (meaningful, but minority) Investment through capital increase Invest in Funds to address smaller projects or larger stakes Exit through IPO, trade sale or put/call agreement Political and regulatory risk mitigation
Infrastructure needs in the sector: in generation (low efficiency due to old equipment and heavy environmental footprint distribution and transport (grid cannot safely absorb more than 2,000 MW of installed wind capacity, according to a 2010 study)
Private sector participation: conventional generation: virtually all state owned greenfield projects coming slowly online such as Petroms 860 MW gas fired plant in Brazi, plus other PPP initiatives of the government, expected to materialize in 2012-2013. regional distribution: 5 out of 8 utilities
Steps that should be taken going forward: privatisation of generation either with strategic investors or IPOs; PPP projects to replace existing power generation infrastructure investment in transmission capacity and regional interconnection focus on strategic projects such as the pump/storage plant in Tarnita renewable sector legislation to start being consistently applied
Wind resource wind measurements for at least 1 year, performed by companies with sufficient expertise and track record.
Land situation the project should have registered rights over the land where it is sited.
Environmental and Social Impact Assessment Studies and Environmental and Social Action Plan based on EBRDs ToR. Stakeholder Engagement Plan (SEP) and Non Technical Summary (NTS) to ensure meaningful public consultation on all projects.
Grid connection concluded connection contracts to connect to the local or national grid.
Technology Wind Turbines Generators (WTG) with track record (no new, untested or experimental technology is acceptable). WTG Supply and LTO&M contracts to be in place by financial closing.
Power Purchase Agreements not a deal breaker, but given the legislation, PPAs would enhance creditworthiness of projects.
Green Certificates Off-take Agreements - difficult to arrange until the GC scheme has more of a track record; if available such would highly improve projects. Mandatory for PV projects, where the dependency on GC prices is substantial.
guaranteed dispatch: by guaranteeing dispatch only for the contracted output of the wind farms, the projects will find it difficult to trade electricity on OPCOM and move towards PPAs.
overcompensation: number of GCs is subject to change, if overcompensation is determined. How will ANRE determine what projects, in development at the time of the decision, will be affected?
oversupply: what happens to GC prices if there are more GCs than required by the quota system?
Projects developed in staged approach: EIA needs to assess full project including infrastructure.
Natura 2000 areas not well defined: EU is commencing infringement action against Romania.
Permitted projects developed by locals are being marketed to international companies: Poor EIA could affect the project, as permits can be withdraw or operators asked to reduce output.
Dobrogea region: key bird migratory corridor of international importance, hence: EIA required for major wind farms Minimal bird and bat assessment 1 year minimal baseline data before operation Appropriate Assessment under Habitats Directive required when in/near Natura 2000 area. EIA to evaluate associated infrastructureroads, substations, transmission lines Public consultations also for local communities
Project Romania - Cernavoda 138 MW - Pestera 90 MW - St. Nikola 156 MW Bulgaria - Suvorovo 60 MW - Wind farm portfolio - Tychowo 50 MW Poland - Wind farm portfolio - Margonin 120 MW Turkey - Rotor 135 MW - Raisner OU 130 MW - Enercap RE Fund Regional - FreEnergy - AES
EBRD Investment - EUR 42.4 mln - EUR 26.7 mln - EUR 70 mln - EUR 60 mln - EUR 50 mln - EUR 30 mln (in PLN) - EUR 75 mln (in PLN) - EUR 45 mln (in PLN) - EUR 45 mln - EUR 0.9 mln - EUR 25 mln - EUR 19 mln
Debt
Equity
- Grupo Enhol - Iberdrola Renovables - Global RPI - Iberdrola Renovables - EDP Renovaveis - Zorlu Enerji - Iberdrola Renovables - Various - Nelja Energia
Hungary
Estonia
The loans, signed in June 2011, financed EDPRs 228 MW wind parks at Cernavoda and Pestera (Dobrogea). EDPR is the worlds third largest onshore wind farm owner and operator The projects represent the first project finance transactions in the energy sector in Romania and in renewables. They contribute to EBRDs objective to support clean, environmental friendly, renewable energy sources and to Romanias strategy of achieving, by 2020, 38% of consumption from renewables. The project supports also EDPRs investment strategy in Central and Eastern Europe.
Project
Structure
Sponsor - Hidroelectrica
Debt
Equity
Romania
Bulgaria
- Vez Svoghe 26 MW
- Petrovilla
- EUR 47 mln
Russia
- RusHydro - RusHydro
Albania
- Power Sector Reconstruction 800 MW - Okami and Lopota HPPs 3.5 MW - Enguri HPP Rehab
Georgia
Armenia
- 20 Various HPPs 56 MW
- Various
- EUR 5 mln
Hidroelectrica, Romania
The loan, signed in July 2011, will finance the rehabiliitation of Hidroelectricas 210 MW Stejarul Bicaz Hydro Power Plant. Hidroelectrica is the largest Romanian power generation company. The project represents the one of the largest transactions concluded by the EBRD in the renewable energy sector in Romania. It contributes to EBRDs objective to support clean, environmental friendly, renewable energy sources and to Romanias strategy of achieving, by 2020, 38% of consumption from renewables. The project supports also Hidroelectricas ambitious investment strategy.
Project
Structure
Thank you!
Mihnea Craciun Principal Banker Power & Energy Utilities +40 21 202 7138 craciunm@ebrd.com