Overall Status:
Red Projects: Yellow Projects: Green Projects: Blue Projects
Green
1 0 15 0
Key
Red Yellow Baseline will not be met. Major issues with project, stake holders highly dissatisfied Outstanding risks are present, which could affect baseline, the issues are being managed by PM; Issues with project where deliverables are not being met in accordance with agreed project plan Green BlueAll is running according to plan. No issues present to risk baseline. Project is no longer "Active", but is in Closure phase.
16
15 0 1
Previous Period (to 02 May 08): Green Total Active Score Yellow Red
ID
Sponsor
Country
Project Name
Project Description
Installation of a router, switch and circuit to a new branch/site
Phase
% Completed Status
Revised Finish
Orange PM
Comments
Completed: Circuit installed 22 April, hardware delivered. Branch UPS installed 6 May Pending: Site migration to be scheduled during week commencing 12 May. Completed: Circuit delivered to nearest point outside ANZ premises 07 January. Router and switch delivered in country 18 January. Pending: Customer premises still under construction Completed: Circuit delivered to nearest point outside ANZ premises 17 December 2007. Router and switch delivered in country 12 December2007. Pending: Customer premises still under construction Completed: Hardware and circuit installed 20 April. Pending: Migration scheduled for Friday 9 May Completed: Circuit delivered and tested. Hardware on site. Pending: Migration scheduled for 10 May. ISDN to be connected 11 May. Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
Vietnam
Tan Da Court
Execution
80%
Paul Piva
Vietnam
Execution
50%
TBA
Paul Piva
Vietnam
Noi Bai
Execution
50%
TBA
Paul Piva
Vietnam
Execution
90%
9-May-08
9-May-08
Paul Piva
Vietnam
Execution
75%
11-May-08
11-May-08
Paul Piva
Vietnam
Hanoi
Planning
10%
TBA
Paul Piva
Vietnam
Planning
10%
TBA
Paul Piva
Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
Singapore
Singapore upgrade
Execution
80%
9-May-08
Jim Rankin
Completed: Circuit delivered and tested. Router installed. Pending: Migration scheduled for 9 May.
United States
New York
Planning
5%
October
Jim Rankin
Red Flag: Due to High level risk of circuit delivery not meeting customer expectations, due to TDD (target delivery date) of 180 days - under PMO escalation. Completed: Order placed for circuit. Pending: Site survey and confirmed delivery date from circuit provider. Completed: 155M access circuit delivered and tested. Router hardware on site. Pending: Migration scheduled for 9 May. . Completed: Telepresence equipment ordered and delivered to Australia. Pending: Shipment of Telepresence equipment to Bangalore. Network Path Accessment, Room Readiness Accessment.
India
Manyata
Execution
50%
9-May-08
Jim Rankin
Manyata Telepresence
Execution
15%
August
Jim Rankin
Indonesia
Jakarta
Upgrade of access circuit from 512k to 1024k. Installation of 4 new routers at Pannin , Papan and SCB. Installation of new 512k cable primary access circuit
Execution
15%
end of May
Paul Piva
Cambodia
Cambodia
Planning
5%
TBA
Paul Piva
Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
China
Shanhai
Planning
5%
TBA
Paul Piva
Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
Beijing
Planning
5%
TBA
Paul Piva
Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
Equant Confidential
4/10/2012
Page 2
Guangzhou
Planning
5%
TBA
Paul Piva
Completed: Order placed on PTT. Pending: Confirmation from PTT of delivery date.
Equant Confidential
4/10/2012
Page 3
TOTAL:
Equant Confidential
4/10/2012
Page 4