Вы находитесь на странице: 1из 7

Activity Based Costing Worked Example

The following information provides details of the costs, volume and transaction cost drivers for a period in respect of XYZ Ltd: Products: A B C Total Sales and production (units) 90,000 30,000 15,000 135,000 Raw materials usage (units) 10 7 14 1,320,000 Direct materials cost () 30 40 15 4,125,000 Direct labor hours 2.5 3 1.5 337,500 Machine hours 5 3 7.5 652,500 Direct labor cost () 20 30 10 2,850,000 Number of production runs 5 10 50 65 Number of deliveries 18 7 50 75 Number of receipts 50 70 700 820 Number of production orders 45 25 60 130

Overhead costs Set up Machines Receiving Packing Engineering Total

75,000 1,000,000 900,000 650,000 750,000 3,375,000

You are required to: a) Calculate the total costs for each product if all overhead costs are absorbed on a labor hour basis; b) Calculate the total costs for each product, using activity based costing; c) Calculate and list the unit product costs from your figures in (a) and (b) above to show the differences between them and to comment briefly on any conclusions which may be drawn which could have pricing and profit implications.

Solution to the worked example


There is more extensive treatment of Activity Based Costing in my book Cost and Management Accounting (1996) Prentice Hall ISBN 0-13-205923-1

We will be working through these data three times. Firstly to see how traditional cost accounting methods might deal with them; secondly to look at the multiple volume based overhead method; and, finally, to look at the ABC method itself. Of the three approaches we will be looking at, only ABC will be using all of the data in any great detail. This is consistent with the general nature of the traditional method, and the only slightly more advanced multiple volume method. Traditional direct labor hours basis The direct labor hour rate is 10, calculated by dividing the total overheads by the total number of direct labor hours: Total overheads / Total number of direct labor hours 3,375,000 / 337,500 10 per dlh Since we are using the direct labor hour rate method for the absorption of all overheads, the product costs per unit must be: A 30 20 30 25 B 40 30 15 30 C 15 10 15 40

Direct Materials Direct Labour Overheads Total Product Cost

The overheads recovered are, of course: Direct labor hour rate x number of direct labor hours per product For product A, for example, the calculation is: 10 per dlh x 2.5 dlh = 25 Multiple volume based allocation method The multiple volume allocation method is an advance on the traditional allocation method in that it does make some allowance for activities to influence the absorption of overheads. In this example, we have two absorption rates to apply here: the receiving department overhead rate, and the "other" overhead rate The reasoning here is that the organization we are simulating is using a two rate basis of apportioning overheads: firstly, a material handling overhead rate is used to assign overhead to a separate cost centre and then charge it to production on the basis of the number of receipts; secondly all of the other overheads are assigned using a general machine hour rate on the basis that the number of machine hours far exceeds the number of labor hours.

Notice here, the rate we are using to assign the materials handling overheads is based on the number of receipts of materials into a department. The reason we are using this rate is that the activity of receiving dominates the reason for the existence of the overhead. Drury uses an overhead rate expressed as a percentage of direct materials cost. This is not a rate to be recommended particularly since tying the assignment of an overhead to the cost of a material is not realistic. As we know, merely because a material is expensive does not mean that its attendant overheads will vary in proportion to it. The receiving overhead rate is: Total receiving overheads / Total number of receipts 900,000 / 820 1,097.56 per receipt Using this rate as a constant allows us to evaluate the product overhead apportionments: Overheads per receipt x receipts per product group For product A: 1,097.56 per receipt x 50 receipts 54,878 Products A Receiving overheads apportionment

54,787.0 76,829.3 768,292.7

We then divide these product apportionments by the number of units made for each product, to derive the cost per unit for receiving goods. The calculations here give the following results:

Products A Receiving cost per unit 0.60976

B 2.5610

C 51.2195

Notice, when compared with Drury's method of using the overhead rate as a percentage of direct materials cost, the version presented here gives a radically different result. Had we applied Drury's method, the product receiving cost per unit would have been:

Overhead absorption rate: 900,000 x 100 = 21.82% = 4,125,000 Applying this rate to each product's material costs gives: Products B 8.73

A 6.55

C 3.27

The method we have used applies the full spirit of ABC by identifying and using fully the ABC approach. The other overhead rate, the Machine Hour Rate, is 3.79. This is calculated by dividing the total other overheads by the number of machine hours applied, or worked. In this case: 3,375,000 900,000 / 652,000 machine hours = 3.79103 When multiplied by the number of machine hours per product, this then gives us the cost per unit for other overheads. For example, in the case of product A, the calculation is: 3.79103 x 5 machine hours per unit = 18.9655 Once all the calculations have been completed, the product cost analysis per unit of each product is: Products A B C Direct materials 30.0000 40.0000 15.0000 Direct labor 20.0000 30.0000 10.0000 Materials overheads 0.6098 2.5610 51.2195 Other overheads 18.9655 11.3793 28.4483 Total Product cost 69.5753 83.9403 104.6678

ABC method
As we said above, to apply the ABC method, we need to identify cost drivers for two stages: 1. Cost drivers tracing the costs of inputs into cost pools; and 2. Cost drivers tracing the cost pools into product costs

The workings that follow illustrate clearly how such cost drivers work through the ABC system in these two stages: an initial overhead rate or amount being further subdivided according the needs of the situation. Workings: The calculations for each of the rates to be used are: The machine hour rate is the only rate that is what we might call a traditional rate. All of the other rates we are about to use involve a two stage process. We will see the elements of these two stages as we get to them. Machine hour overhead rate: 1,000,000 / 652,500 machine hours = 1.5326 This rate is used as normal. For the set up costs, we first devise a rate to tell us the cost per set up: total set up overheads divided by the number of set ups: in this case, this is 75,000 / 65 production runs = 1,153.85 We will return to this rate shortly. All of the other rates are calculated similarly. Hence they will be presented now without further comment. Receiving rate Packing rate Engineering rate 900,000 / 820 receipts 650,000 / 75 deliveries 750,000 / 130 production orders = 1,097.56 = 8,666.67 = 5,769.23

All of this information can now be put together into a cost per unit statement as follows. The final stage in the whole ABC procedure, as far as product cost determination is concerned is to find out the costs per unit. The cost per unit statement follows, and then we will work through the calculations.

Unit costs Direct materials Direct labor Machine overheads Set up costs Receiving costs Packing costs Engineering costs Total Costs

A () 30.0000 20.000 7.6628 0.0641 0.6098 1.7333 2.8846 62.9546

B () 40.0000 30.000 4.5977 0.3846 2.5610 2.0222 4.8077 84.3732

C () 15.000 10.000 11.4943 3.8462 51.2195 28.8889 23.0769 143.5257

Workings: Machine overheads are found by multiplying the machine hour rate by the number of machine hours per product per unit: Machine hour rate 1.5326 x Machine hours Gives 5 7.6628 3 4.5977 7.5 11.4943

The set up costs rate we have already is the rate per machine set up, the cost per unit is calculated by multiplying the rate per set up by the number of set up per product and then dividing the results by the total number of units per product: Set up cost per set up 1153.85 x No. of setups Gives Set up cost per set up 1,153.85 x No. of setups Gives 5 5,769.25 10 11,538.50 50 57,692.50 5 0.0010 10 0.0059 50 0.0592

These values are then divided by the number of units per product to give us the cost per unit: 0.0641 0.3846 3.8462

The receiving, packing and engineering costs are all calculated in the same way as the set up costs. There is no need to repeat these calculations, but check that they are understood.

Summarizing each of these methods now we can see the impact of the different methods on product costs, assuming that the ABC method is really more effective than the traditional approach, product A, shows a cost difference of 42.1085 per unit. Summary 1: Total costs per unit using each of the three methods Products DLH Mult ABC A 75.0000 69.5753 62.9546 B 100.0000 83.9403 84.3732 C 40.0000 104.6678 143.5257

Summary 2: Overheads per unit using each of the three methods Products A B 25.0000 30.0000 19.5753 13.9403 12.9546 14.3732

DLH Mult ABC

C 15.0000 79.6678 118.5257

Summary 3: Overheads as a percentage of total costs Products A B 33.33% 30.00% 28.14% 16.61% 20.58% 17.04%

DLH Mult ABC

C 37.50% 76.11% 82.58%

Вам также может понравиться