Академический Документы
Профессиональный Документы
Культура Документы
131
132
the least cost compared to other sources mentioned above, whereas the long-term perspective of alternative energy sources contributing to meet the power demand needs to be further studied. Hydropower Hydropower potential is still quite low in Bangladesh, because rivers are mostly on flat surfaces with low gradients. Presently, the only hydroelectric plant in the country (Karnafuli) has a capacity to produce 230 MW of electricity. There is a potential to produce 250 MW of power at Sangu and Matamuhuri river, though the cost of new storage is very high; such projects are not encouraged by the government considering their adverse environmental and social impacts. Fifteen prospective sites have been identified as having potential for on-site small hydropower generation. Solar Solar power utilization is being accepted gradually, but its slow progress is due to high initial cost, low daily operation time, and lower output level. Bangladesh is ideally located for tapping solar energy effectively (3 - 6 kWh/m 2 per day). Solar energy has been used in Bangladesh for drying crops and fishes since many decades. Bangladesh Atomic Energy Commission (BAEC) has commissioned pilot project for beacon lighting, refrigeration for vaccines storage, and water pumping. The Rural Electrification Board (REB) has introduced solar photovoltaic electricity in Narsingdi District. Government has waved duty and taxes on solar and other renewable energy applications to encourage both public and private sectors. Bangladesh University of Engineering Technology, Bangladesh Centre for Scientific and Industrial Research, Dhaka University and a few other organizations are continuing efforts to improve solar utilities in Bangladesh. Biomass and biogas Most of the rural people are fully dependent on biomass energy for their daily energy needs. It is estimated that as much as 70 per cent of total energy requirement in Bangladesh is met by biomass. Different forms of biomass-use include rice husk (26 per cent), cow dung (19 per cent), rice straw (16 per cent), twigs and leaves (14 per cent), badges (7 per cent), fuel wood (5 per cent), and jute sticks (4 per cent). Because of the high rate of biomass use at present, there is serious concern about preservation of limited forests in the country and striking a balance between ecological, social and environmental needs. About 400 biogas plants have already been installed in different parts of the country. Limited success has resulted from high capital cost, insufficient supply of raw material and lack of maintenance support.
133
70 60 50 kgOE 40 30 20 10 0 1973 75 77 79 81 83 85 87 89 91
15
10 % 5
134
Table 3.1
Prevailing tariff for primary fuels and electricity Electricity Price (Taka/kWh) 3.30 2.55 4.75 4.45 3.10 7.10 3.10 2.50 5.75
Primary Fuels Type of fuel Natural gas Market price (Taka)* 1.68/m 3
Type of users Small industries: flat rate Furnace oil 4.51/litre off-peak hours peak hours LDO 11.89/litre Commercial: flat rate HSD 12.41/litre off-peak hours peak hours SKO 12.41/litre General use (11 kV): flat rate Fuel wood 2/kg (average) off-peak hours peak hours * Exchange rate (1998): 1 US$ = 48 Taka
The Government is restructuring the power sector and promoting private sector participation in the generation of electricity for attaining higher economic efficiency. The Government is strongly committed to attract private investment for installing new power generation capacity on a Build-Own-Operate (BOO) basis. A Power Cell under the Ministry of Energy and Mineral Resources (MEMR) was created in 1995 to facilitate promotion, development, implementation, commissioning and operations of private power generation projects. The modalities for implementing private power project are as follows. Financing regulation The funds for the private power projects will be raised without any direct sovereign guarantee of repayment. The project sponsor(s) must look to the revenues earned by the sale of electricity for their returns on equity and debt servicing. Minimum requirement for equity investment will be 20 per cent. A Private Sector Infrastructure Development Fund (PSIDF) will be established and money would be available at market-based interest rates with extended maturity periods. As corporate debt securities market is essential for raising local financing for power development projects, provisions for corporate bonds, shares and tax facilities with the recognition by Securities and Exchange Commission (SEC) will be allowed. Security package Model Implementation Agreement (IA), Power Purchase Agreement (PPA) and Fuel Supply Agreement (FSA) will be prepared for private power projects to eliminate the need for protracted negotiations. The government will guarantee power purchase agreement for performance obligations of the concerned utilities and the performance of the fuel supplier, which is a public sector organization. For private power projects, protection will be provided against specific force major risk and changes in certain taxes and duties. Allocation of project/plant site and provision of fuel The government will select project/plant site in consultation with the investor/project sponsor, and determine the fuel, keeping in view the preference for indigenous resources but the use of imported fuels may also be allowed. Investors may be asked to bid for projects based on renewable and/or non-conventional sources of energy.
135
Tariff for bulk purchase of power at busbar The tariff structure would consist of two parts. In the solicited bids, the bidders shall offer bulk power tariff based on the capacity payment and energy payment and also provide the equivalent levelized tariff. The capacity payment will be made in Bangladeshi currency (Taka), but denominated in both Dollars and local currency. This will cover debt service, return on equity, fixed operation and maintenance cost, insurance and other fixed cost. The energy payment will be denominated in local currency to the extent to which the variable costs are in local currency. This will cover the variable costs of operation and maintenance, including fuel. Interconnection of IPP to transmission system: The power will be purchased from the IPP at a specified voltage and frequency at the outgoing terminal of the substation of the power plant. The cost of interconnecting facilities up to outgoing terminals of the private power project will be borne by the private power producers. Fiscal incentives The private power companies shall be exempted from corporate income tax for 15 years. Repatriation of equity along with dividends will be allowed freely. Income tax will be exempted for foreign companies. The foreign investors will be free to enter into joint ventures but this is optional and not mandatory. The companies will be allowed to import plant and equipment without payment of customs duties, VAT and any other surcharges. Private power companies will be exempted from the requirements of obtaining insurance/reinsurance only from the national Insurance Company and exempted from duty payments. Power generation companies are eligible for all concessions that are available to industrial projects. Private parties may raise local and foreign finance in accordance with regulations applicable to industrial projects as defined by the Board of Investment (BOI). Local engineering and manufacturing companies shall be encouraged to provide indigenously manufactured equipment of international standard to private power plants. Other facilities and incentives for foreign investors: Several other incentives extended by the government include tax exemption on royalties, technical assistance fees, and facilities for their repatriation; tax exemption on interest on foreign loans; tax exemption on capital gains from transfer of shares by the investing company; avoidance of double taxation in case of foreign investors on the basis of bilateral agreements; exemption of income tax for up to 3 years for the expatriate personnel employed by the industry, etc. Starting from 1997, the government is considering to install a capacity of 1,500 MW through IPPs. Four agreements have so far been made, two of which are being implemented while several other projects are in the pipeline. An Independent Power Producer (IPP) is generally required to sign four contract agreements. These are the Power Purchase Agreement with BPDB; Implementation Agreement with the Government; Fuel Supply Agreement with the buyer and the supplier of fuel; Land Lease Agreement with the buyer. Many special features included in the IPP contract are very much in favour of the IPP, and are not extended to BPDB which is working presently with an installed generating capacity of 2,900 MW. The tariff charges in some cases are above the international price.
136
3.2
137
kW
590 570
Ton of Refrigeration
550
530 510
490 470 450 6 8
Chiller-1 Chiller-2
10
12
14
16
18
20
22
24
Figure 3.3 Cooling provided by chillers as a function of time The management of the mills cites several advantages of the cogeneration plant, such as primary fuel savings, reduced energy costs, enhanced reliability of power supply, and reduced environment pollution. Following are the benefits from the process side: reduced lapping, reduced end breakage, improved product quality due to cleaner environment, reduced burnout of the motors. Moreover, turnover of technical staff has reduced considerably, workers feel less fatigued and there is reduced absenteeism. As a result, there is 30 per cent increase in overall productivity. The gas engine generator with vapour absorption chillers is found to be an effective performance enhancement option. The result of this specific study should encourage other process industries to look seriously into the prospects of opting for cogeneration in their respective plants. This will not only be rewarding to them, but also to the country as a whole
138
since the indigenous energy sources will be exploited more rationally and the national power utility would have a lower burden of coping with the ever-increasing power demand. Cogeneration in sugar mill There are 15 sugar mills in Bangladesh. These mills are owned by the government but controlled and managed by 'Bangladesh Sugar and Food Industries Corporation (BSFIC)'. Sugarcane required by each mill is collected from its surrounding areas. The industry meets the major requirement of country's sugar. Sugar mills also produce molasses and bagasse, two very important by-products that are used as raw materials in distilleries and paper industry respectively. Bagasse is also the main fuel for sugar mill boilers, producing steam that is required in the manufacturing process of the mill. In 1993-94, these mills crushed 2.7 million tons of cane, producing close to a million tons of bagasse. Data on installed capacity, cane crushed, turbine capacity, on-site power generation, power purchased, are shown in Table 3.2. Table 3.2
No Sugar mills
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Panchagar Thakurgan Setabganj Shyampur Rangpur Jaypurhat Rajshahi Natore North Bengal Kushtia Carew Mobarakganj Faridpur Zeal Bangla Deshbandu Total
As most sugar mills have similar configurations, one of them is described here with more details. This mill has three water tube boilers, each with a steam generating capacity of 16 ton/hr. The pressure and temperature of the steam are 15 kg/cm2 and 246C respectively. Bagasse is the primary source of which is burnt in boiler furnace to generate steam which in turn is used to drive steam turbine generators for electricity generation required for motor drives, driving mill drive turbines and for meeting process steam needs. One steam turbine generator is normally operated during milling season to meet the entire electric demand. One standby diesel generator is also available and run during emergency. Electricity is purchased from Bangladesh Power Development Board (BPDB) as required during cleaning days and during off-season. There are also two crusher drive steam turbines, each of 580 HP capacity and two steam turbine generators, each of 1 MW capacity. About 30 tons/hour of steam is produced in the boiler that has an average efficiency of 56 per cent. High-pressure steam is mainly used for steam turbine generator and crusher drive turbines. An automatic pressure reduction valve reduces steam from 15kg/cm 2 pressure to 3 kg/cm2 that is mainly used in centrifugals for purging molasses and washing/cleaning
139
heaters, evaporators and pans, etc. Turbine exhaust steam is used in processing juice, i.e. mainly heating purposes. Another automatic steam reduction valve reduces 3 kg/cm2 steam to 1 kg/cm2 to supply make up steam. Totally 80 per cent of the condensate is recovered and about 20 per cent make up water is needed for the boiler. During plant visit, it was observed that steam used in heating air of 6 forced air supply units of sugar dryer was being operated with an open bypass valve of traps causing live steam discharge to drains. Though all sugar mills have cogeneration facilities, they operate only during the season, i.e. 150 days per year. If they can be operated during off-season by applying Balancing, Modernization, Rehabilitation & Expansion (BMRE) Programme, more power generated can alleviate the power shortage in the country. Most sugar factories have low-pressure (15 bar) boilers. By installing high-pressure boilers, these can produce more power efficiently. The choice of boiler pressure of 64 kg/cm2 and above appears inevitable for mills intending to sell power to the national grid. Typically, a well-designed 2,500 tons crushed/day plant can sell 10 MW of power to national grid. There are several technical financial and institutional impediments to the use of energy efficient sugar mills, the most important ones being the policy initiatives and shortage of financial resources. In most sugar factories, there is a lack of sound technical management to maintain high-pressure boilers. The existing low-pressure boiler is itself not being maintained satisfactorily in most cases with the result that there are interruptions in crushing sugar cane. In any event, sugar being still a highly regulated industry, the management is occupied with sugar cane farmers, and the financial and administrative problems of producing and selling, and very few have the time to take up the additional responsibility of electricity cogeneration. Cogeneration with improved technology should be seriously considered in sugar factories of Bangladesh as it offers the following advantages: It causes no pollution as the bagasse does not produce flash, or sulphur compared to coal used in a thermal plant; It needs no foreign exchange as the machinery needed for cogeneration boilers, turbines, etc., is indigenously available; It has a low gestation period of two years compared with four to six years of construction period for a coal-based thermal plant; It has a much lower installation and recurring cost compared with a conventional fossil fired power plant; It is small in size and is invariably in the rural area, so the transmission and distribution losses are minimal compared with any centralized plant requiring long lines of distribution; It places no financial and administrative burden on the utility as it is executed and managed by the sugar factory; It improves the financial position of the sugar factory. Cogeneration in paper mill A newsprint paper mill having a steam turbine cogeneration facility is covered here. The mill presently generates 13.1 MW and purchases 2.5 MW from the utility grid to meet all the electrical energy needs of the site, including the residential zones. Furnace oil is used in boilers for steam generation. Steam generated at 42 bar and 400C in three boilers with a total installed capacity of 161 ton/hour, is mainly used in three backpressure turbines to generate electricity. After partial
140
expansion of the steam in turbine a significant amount of steam at 6 bar is used by paper machine and autoclaves. Presently, 13.1 MW is self-generated and a 2.5 MW is bought from the national grid to run the factory and provide residential lighting. The electrical and thermal energy data of the factory for the year 1994 are shown in Figures 3.4 and 3.5.
12
Purchased power
MWh (Thousand)
Month
Figure 3.4 Electricity consumption data of the paper mill in 1994
3500 3000
2500 2000 1500 1000 500 May Aug Apr 0 Feb Jan
Mar
Month
Figure 3.5 Thermal energy consumption data of the paper mill in 1994 Cogeneration in fertilizer plant This fertilizer factory is one of the largest in the country, with a capacity to produce over 1.8 million tons of urea per year. Main energy source used in this fertilizer factory is natural gas that is used in boilers as fuel. Most of the electrical energy used in the fertilizer factory is self-generated and there is provision for buying electricity from the national grid.
Dec
Sep
Oct
Jun
Jul
Dec
Feb
Sep
Oct
Jan
Jun
Jul
141
The fertilizer factory has two boilers with capacities to produce 180 tons/hr and 171 ton/hr of steam, respectively. The steam generated at 60 bar and 510C is mainly used in two backpressure steam turbines to generate up to 11 MW of electricity. After partial expansion in the turbine, steam at 10 bar is used for processing. Self-power generation and thermal energy consumption data of the factory are given in Figures 3.6 and 3.7, respectively.
8000
7000 6000 5000 4000 3000 2000 1000 Mar May Apr Aug Nov Oct Dec Feb Jan Jul 0 Sep Jun
Month
Figure 3.6
700000 600000
May
Mar
Aug
Nov
Apr
Oct
Month
Figure 3.7
Dec
Feb
Jun
Jul
Sep
Jan
142
Type of Activity Textile Spinning Mills Textile Processing Mills Knitting & Hosiery Plant Jute Mills Paper Recycling Mills Soup & Chemical Industry Tannery Cement Mills Ceramic Industry Tea Gardens Food Industry Distillery Sugar Mills (surplus generation) Industrial Estate Hotel Hospital Housing Complex Office Complex Export Processing Zone
143
3.3
For the purpose of economic analysis, the total installed costs of the cogeneration plants were assumed as follows: steam turbines: US$ 1,200/kWe; gas turbines: US$ 1,000/kWe; and reciprocating engines: US$ 900/kWe. Some common financial data gathered or assumed before conducting the pre-feasibility studies are summarized in Table 3.4. Table 3.4 Parameters Exchange rate Tax rate Discount rate Cogeneration plant service life Electricity purchase price Electricity buy-back rate Fuel price escalation rate Electricity price escalation rate Electricity stand-by rate Fuel purchase price (natural gas) Financial data used for the pre-feasibility study Unit Taka/US$ Per cent/year Per cent/year Year Taka/kWh Per cent of purchase price Per cent/year Per cent/year Taka/kW.month Taka/m 3 Value 48.00 35.00 15.00 15.00 3.60 80 per cent 5.00 6.00 80.00 1.68
The average power-to-heat ratios were found to be 0.52 in 1997. Typical cogeneration system for this site would be based on steam turbine. However, reciprocating engine, gas turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.5. Obviously, the steam turbine option does not seem feasible: (i) with steam turbine thermal match (STTM), less than 25 per cent of the power requirement is generated; (ii) with steam turbine power match (STPM), too much excess heat is generated. With the reciprocating engine thermal match (RETM) option, 200 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems feasible as almost all the power needed can be met though an auxiliary boiler will be necessary to make up for the 30 per cent shortfall in the heat supply.
144
Summary of pre-feasibility study of the recycled paper mill Steam Turbine Gas Engine Gas Turbine
Power Match
2,750.00 316.00 21,945.00 112.20 1,467.00 -49.80 0.80 132.00 213.44 38.30
With gas turbine thermal match (GTTM) option, about 30 per cent excess electricity is generated which may be acceptable. Gas turbine power match (GTPM) option is also good as the 30 per cent deficit in the heat supplied can be met by auxiliary natural gas firing in the recovery boiler. Accordingly, sensitivity analysis done to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to REPM, GTTM and GTPM options. What if the investment cost increases?
Int er na l Ra(IR te R) of Re tur n
42% 40% 38% 36% 34% 32% 30% REPM GTPM
1%
3%
5%
8%
10%
13%
15%
145
From the sensitivity analysis of the potential cogeneration alternatives for the recycled paper mill, the reciprocating engine power match option meeting power requirement of 2750 kW is found to be the most suitable cogeneration system. It represents an initial investment of 118 Million Taka and leads to an internal rate of return of 41.9 per cent.
The average power-to-heat ratio was 0.53 in 1997. Typical cogeneration system for this site would be based on steam turbine, though its size will be quite small. However, reciprocating engine, gas turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.6. Obviously, the steam turbine option does not seem feasible: (i) with steam turbine thermal match (STTM), less than 20 per cent of the power requirement is met; (ii) with steam turbine power match (STPM), 300 per cent excess heat is generated. With the reciprocating engine thermal match (RETM) option, 235 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems feasible as almost all the power needed can be met though an auxiliary boiler will be necessary to make up for the 30 per cent shortfall in the heat supply.
146
Table 3.6
Major Parameters
Gas Engine
Thermal Match 1,804.00 164.00 13,819.00 30.20 9,950.00 1.60 1.87 77.93 102.69 34.30 Power Match 520.00 47.30 3,984.00 8.70 -245.00 -19.90 1.87 22.46 39.82 40.30
Gas Turbine
Thermal Match 772.00 85.20 5,914.00 30.20 1,685.00 1.60 0.80 37.06 49.27 34.40 Power Match 520.00 57.40 3,984.00 20.40 -245.00 -8.30 0.80 24.96 37.61 36.80
Installed power (kW) Fuel consumption (TJ/year) Electricity generated (MWh) Heat generated (TJ/year) Excess/deficit(-) power (MWh/year) Excess/deficit(-) heat (TJ/year) Equipment power-to-heat ratio Total investment (million Taka) Net present value (million Taka) IRR (per cent)
With gas turbine thermal match (GTTM) option, about 35 per cent excess electricity is generated which may be acceptable. Gas turbine power match (GTPM) option is also good as the 30 per cent deficit in the heat supplied can be met by auxiliary natural gas firing in the recovery boiler. Accordingly, the sensitivity analysis carried out to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to REPM, GTTM and GTPM options. What if the investment cost increases?
45%
40% 35% 30% 25% 20% 1% 2.50% 5% 7.50% 10% 12.50% 15%
40%
6%
7%
8%
9%
10%
11%
12%
13%
147
From the sensitivity analysis of the potential cogeneration alternatives for the vegetable oil refinery, the reciprocating engine power match option meeting power requirement of 520 kW is found to be the most suitable cogeneration system. It represents an initial investment of 22 Million Taka and leads to an internal rate of return of 40.3 per cent.
The power-to-heat ratio of the site was estimated as 1.1 for 1997. Typical cogeneration system for this site would be based on reciprocating engine. However, steam turbine and gas turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.7. As expected, the steam turbine option is not suitable: (i) with steam turbine thermal match (STTM), less than 10 per cent of the power requirement is met; (ii) with steam turbine power match (STPM), 770 per cent excess heat is generated. With the reciprocating engine thermal match (RETM) option, 62 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems feasible as almost all the power requirement can be met though the heat generated is largely inadequate to meet the demand. An auxiliary boiler will be necessary to make up for over 65 per cent shortfall in the heat supply.
148
Summary of pre-feasibility study of the textile spinning mill Steam Turbine Gas Engine Gas Turbine
Therm al Match
Installed power (kW) Fuel consumption (TJ/year) Electricity generated (MWh) Heat generated (TJ/year) Excess/deficit(-) power (MWh/year) Excess/deficit(-) heat (TJ/year) Equipment power-to-heat ratio Total investment (million Taka) Net present value (million Taka) IRR (per cent)
Power Match
2,350.00 270.00 18,753.00 -1,316.00 95.90 29.90 0.80 112.80 175.52 37.40
263.00 2,350.00 88.80 794.90 2,096.00 18,753.00 -17,974.00 -1,316.00 71.20 637.40 5.20 507.60 0.106 0.106 15.12 135.36 18.20 41.41 32.80 19.90
With gas turbine thermal match (GTTM) option, about 30 per cent less electricity are generated. Gas turbine power match (GTPM) option takes care of all the power and heat needs but around 46 per cent of excess heat are generated which has no commercial value. Accordingly, the sensitivity analysis carried out to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to REPM and GTPM options. What if the investment cost increases?
1%
3%
5%
8%
10%
13%
15%
41% 40% 39% 38% 37% 36% 35% 5% 6% 7% 8% 9% 10% 11% 12% 13% REPM GTPM
149
49% 47% 45% 43% 41% 39% 37% 35% 6% REPM GTPM 7% 8% 9% 10% 11% 12% 13%
From the sensitivity analysis of the potential cogeneration alternatives for the textile spinning mill, the reciprocating engine power match option meeting power requirement of 2,350 kW is found to be the most suitable cogeneration system. It represents an initial investment of 102 Million Taka and leads to an internal rate of return of 41.9 per cent.
The power-to-heat ratio of the site was estimated as 0.3 for 1997. Typical cogeneration system for this site would be based on steam turbine. However, reciprocating engine and gas turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.8. The steam turbine option is found to be not suitable: (i) with steam turbine thermal match (STTM), less than 20 per cent of the power requirement is met; (ii) with steam turbine power match (STPM), 90 per cent excess power and 170 per cent excess heat are generated. With the reciprocating engine thermal match (RETM) option, 325 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems feasible as almost all the power needed can be met though the heat generated meets up to 80 per cent of the demand. An auxiliary boiler will be necessary to make up for the remaining 20 per cent shortfall in the heat supply.
150
Table 3.8
Summary of pre-feasibility study of the textile spinning mill Steam Turbine Gas Engine Gas Turbine
Major Parameters
Ther Powe Therma Powe Therm Powe mal r r al r l Match Match Match Match Match Match
Installed power (kW) Fuel consumption (TJ/year) Electricity generated (MWh) Heat generated (TJ/year) Excess/deficit(-) power (MWh/year) Excess/deficit(-) heat (TJ/year) Equipment power-to-heat ratio Total investment (million Taka) Net present value (million Taka) IRR (per cent) 238.00 875.00 88.90 326.10 1,849.00 6,783.00 73.00 267.80 -5,584.00 -650.00 -16.30 151.80 0.091 0.09 13.74 50.40 16.94 20.37 33.20 21.30 4,157.00 382.50 32,226.00 73.00 24,793.00 -16.30 1.87 179.59 234.12 34.10 875.00 80.50 6,783.00 15.40 -650.00 -73.90 1.87 37.80 68.43 40.80 1,843.00 205.70 14,284.00 73.00 6,851.00 -16.30 0.80 88.44 110.84 33.40 875.00 97.70 6,783.00 34.70 -650.00 -54.60 0.80 42.00 64.59 37.20
With gas turbine thermal match (GTTM) option, about 90 per cent excess electricity is generated. Gas turbine power match (GTPM) option takes care of all the power needs though heat deficit is as high as 60 per cent. This will require the adoption of auxiliary natural gas firing in the recovery boiler. The total installation cost of GTPM is 50 per cent less than that for GTTM. Accordingly, the sensitivity analysis carried out to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to REPM and GTPM options. What if the investment cost increases?
1%
3%
5%
8%
10%
13%
15%
41% 40% 39% 38% 37% 36% 35% 5% 6% 7% 8% 9% 10% 11% 12% 13% REPM GTPM
151
From the sensitivity analysis of the potential cogeneration alternatives for the textile processing mill, the reciprocating engine power match option meeting power requirement of 875 kW is found to be the most suitable cogeneration system. It represents an initial investment of 37 Million Taka and leads to an internal rate of return of 40.8 per cent.
3.3.5 Hospital
This hospital operates throughout the year without any stop. Electricity is required for lighting, air conditioning and motors whereas as a lot of thermal energy is needed in the form of steam for various applications. Analysis of the monthly electricity and steam consumption data of 1997 led to the following: Total Electricity Consumption in 1997: Maximum Electricity Demand: Minimum Electricity Demand: Total Thermal Energy Consumption in 1997: Maximum Steam Demand: Minimum Steam Demand: 7,108 MWh 1,200 kW 800 kW 91.5 TJ 4.99 ton/hr 3.90 ton/hr
The power-to-heat ratio of the site was calculated to be 0.68 for 1997. Typical cogeneration system suitable for this site would be based on gas turbine. However, reciprocating engine and steam turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.9. The steam turbine option is found to be not suitable: (i) with steam turbine thermal match (STTM), less than 30 per cent of the power requirement is generated and the hospital will have to depend heavily on the utility grid; (ii) with steam turbine power match (STPM), 119 per cent excess heat are generated which has no commercial value. With the reciprocating engine thermal match (RETM) option, 475 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems feasible as almost all the power needed can be met though there will be small (16 per cent) shortage in the heat supply. There is no need for an auxiliary boiler as this shortfall can be easily made up by auxiliary natural gas firing in the recovery boiler.
152
Summary of pre-feasibility study of the hospital Steam Turbine Gas Engine Gas Turbine
Powe r Match
800.00 95.60 6,658.00 34.00 -450.00 -57.60 0.80 38.40 66.51 39.80
With gas turbine thermal match (GTTM) option, about 146 per cent excess electricity is generated, which has to be sold as in the RETM option. Gas turbine power match (GTPM) option takes care of all the power needs though heat deficit is as high as 60 per cent. This will require the adoption of auxiliary natural gas firing in the recovery boiler. Accordingly, the sensitivity analysis carried out to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to REPM and GTPM options. What if the investment cost increases?
1%
3%
5%
8%
10%
13%
15%
41% 40% 39% 38% 37% 36% 35% 5% 6% 7% 8% 9% 10% 11% 12% 13% REPM GTPM
153
49% 47% 45% 43% 41% 39% 37% 35% 6% REPM GTPM 7% 8% 9% 10% 11% 12% 13%
From the sensitivity analysis of the potential cogeneration alternatives for the hospital, the reciprocating engine power match option meeting power requirement of 800 kW is found to be the most suitable cogeneration system. It represents an initial investment of 35.6 Million Taka and leads to an internal rate of return of 43.5 per cent.
3.3.5 Hotel
This hotel operates throughout the year. Electricity is required for lighting, air conditioning and motors, and a lot of steam is required for various applications. Analysis of the monthly electricity and steam consumption data of 1997 led to the following: Total Electricity Consumption in 1997: Maximum Electricity Demand: Minimum Electricity Demand: Total Thermal Energy Consumption in 1997: Maximum Steam Demand: Minimum Steam Demand: 8,580 MWh 1,000 kW 900 kW 137 TJ 9.25 ton/hr 8.02 ton/hr
The power-to-heat ratio of the site was calculated to be 0.23 for 1997. Typical cogeneration system suitable for this site would be based on steam turbine. However, reciprocating engine and gas turbine cogeneration systems were also considered as potential alternatives. Results of the feasibility study are summarized in Table 3.10. The steam turbine option is found to be not suitable: (i) with steam turbine thermal match (STTM), less than 65 per cent of the power requirement is generated and the hotel will have to depend on the utility grid; (ii) with steam turbine power match (STPM), only a small amount of excess heat is generated. With the reciprocating engine thermal match (RETM) option, 900 per cent excess power is generated. The project profitability will depend on the buy-back rate. This may not be a good option as the purpose is not to earn from electricity sale. Reciprocating engine power match (REPM) option seems good as almost all the power needed can be met though there will be small (15 per cent) shortage in the heat supply. There is no need for an auxiliary boiler as this shortfall can be easily made up by auxiliary natural gas firing in the recovery boiler.
154
Summary of pre-feasibility study of the hotel Steam Turbine Gas Engine Gas Turbine
Ther Powe Therm Powe Therm mal r al r al Match Match Match Match Match
Installed power (kW) Fuel consumption (TJ/year) Electricity generated (MWh) Heat generated (TJ/year) Excess/deficit(-) power (MWh/year) Excess/deficit(-) heat (TJ/year) Equipment power-to-heat ratio Total investment (million Taka) Net present value (million Taka) IRR (per cent) 653.00 900.00 230.00 317.50 5,400.00 7,490.00 184.60 254.60 -3,149.00 -1,090.00 47.00 92.10 0.106 0.11 37.59 51.84 41.11 44.61 31.20 28.00 10,137.00 1,001.50 84,376.00 184.60 75,796.00 47.60 1.87 438.00 597.67 34.90 900.00 88.90 7,490.00 16.40 -1,090.00 -120.60 1.87 38.88 78.61 43.50 4,339.00 520.00 36,112.00 184.60 27,532.00 47.60 0.80 208.29 249.30 32.60
Powe r Match
900.00 107.90 7,490.00 38.30 -1,090.00 -98.70 0.80 43.20 74.83 39.80
With gas turbine thermal match (GTTM) option, about 320 per cent excess electricity is generated, which has to be sold as in the RETM option. Gas turbine power match (GTPM) option takes care of all the power needs though heat deficit is as high as 60 per cent. This will require the adoption of auxiliary natural gas firing in the recovery boiler. Accordingly, the sensitivity analysis carried out to see the impacts of the increase in the investment, fuel and electricity price escalation, was limited to STPM, REPM and GTPM options. What if the investment cost increases?
Internal Rate of Return (IRR)
1%
3%
5%
8%
10%
13%
15%
41% 40% 39% 38% 37% 36% 35% 5% 6% 7% 8% 9% 10% 11% 12% 13% REPM GTPM
155
49% 47% 45% 43% 41% 39% 37% 35% 6% REPM GTPM 7% 8% 9% 10% 11% 12% 13%
From the sensitivity analysis of the potential cogeneration alternatives for the hospital, the reciprocating engine power match option meeting power requirement of 800 kW is found to be the most suitable cogeneration system. It represents an initial investment of 35.6 Million Taka and leads to an internal rate of return of 43.5 per cent.
156
3.4
From the pre-feasibility study of the selected sites, one can conclude that thanks to the availability of natural gas distribution network in some economic areas, gas-based cogeneration is found to be the most cost-effective option for Bangladesh. In view of the present national power situation, cogeneration in sites having a steady need for heat and power, and access to natural gas, can improve the production reliability and efficiency while reducing the burden on the already stressed national grid. Moreover, natural gas-based cogeneration will reduce the dependency on imported fuel and will have less adverse impact on the environment. Power demand in many sites is not very high, ranging from 0.5 to 2 MW. These sites are ideal for gas-based reciprocating engines that already have a good presence in the local market. The internal rates of return in all the cases were found to be quite high (above 40 per cent) for the best feasible options, mainly due to the low price of gas prevailing in the country. In spite of the significant techno-economic potential for cogeneration applications in Bangladesh, cogeneration has not been widely adopted in the country due to several reasons. The foremost among them is the low level of awareness at all levels about the technological alternatives, economic merits, environmental benefits and business opportunities related to the application of cogeneration as an efficient energy use option. No systematic study has been undertaken so far to assess cogeneration potential by taking into account factors such as energy demand patterns, plant size, power-to-heat ratio, access to gas pipeline, etc. There is practically no interaction between the energy utilities and the energy users to explore the cogeneration option though the government is serious about encouraging private investment in the power sector. Recommendation for follow-up actions Since cogeneration development seems to be very promising, the hurdles (institutional structure, policy and planning, energy pricing and tariff, investment and financing etc.) in this sector may be removed for its further propagation. Regulatory measures are needed for the sale of excess electricity to the grid or third party, and back-up power supply from the grid as and when necessary. The establishment of a national interagency co-ordinating committee may be seriously considered. Government may also initiate demonstration projects using advanced technologies in selected public sector enterprise in the industrial estates/export processing zones/satellite city centres. State energy suppliers (electricity and gas companies) may play a greater role in the propagation of cogeneration by establishing partnership with potential cogenerators, public or private, in making investment, guaranteeing operation and maintenance, and sharing costs and benefits in the process.
These conclusions and recommendations are based on the deliberations of participants in the South Asia Sub-Regional Seminar organized at Dhaka on 14 and 15 November 1998. The programme details of the Seminars are included in Appendix 3A.
157
Alternative financing may include third-party participation, leasing, soft loan, bilateral and international funds targeted towards global environmental protection (e.g. clean development mechanism, joint implementation, special environmental Yen loan, global environmental fund). More incentives such as quick depreciation, soft loan, tax benefits, etc., should be extended to those cogeneration projects that satisfy well-specified technical, economic and environmental criteria. An energy conservation act may be established with a view to emphasizing on use of cogeneration and development of energy efficient technologies. To promote cogeneration technology, there should be a separate cell under the Ministry of Energy and Mineral Resources who will look after and will publish information regarding cogeneration regularly. There is a need for introducing courses on renewable energy and cogeneration in the curriculum of technical education in Bangladesh for development of long-term human resources. Large-scale training programme may be contemplated for involvement of national institutions on different aspects of cogeneration. Workshops, seminars and information exchanges are necessary on specialized topics, such as feasibility study, site selection, equipment design, financing and resource management. A comprehensive survey and pre feasibility study should be undertaken for developing an implementation plan. Feasibility studies for cogeneration should be made immediately for all the identified schemes and priorities should be set for their implementation. A cogeneration programme should be incorporated with all suitable existing future projects in Bangladesh. International cooperation through bilateral agreements for technical and financial assistance would be helpful and should be sought.
158
APPENDIX 3.A
Programme of the South Asia Sub-Regional Seminar on ROLE OF COGENERATION IN THE NATIONAL ENERGY SCENARIO : PERSPECTIVES FOR ENERGY POLICY Date: Place: Organiser: Saturday, 14 November 1998 Bangladesh University of Engineering Technology (BUET), Dhaka, Bangladesh Centre for Energy Studies and Mechanical Engineering Department (BUET), in Collaboration with Economic and Social Commission for Asia and the Pacific (ESCAP) Government of Japan Registration Official opening Message from ESCAP Mr. Pranesh C. Saha (Chief of Energy Resources Section, ESCAP) Economic and Environmental Benefits of Cogeneration Applications Dr. B. Mohanty (Cogeneration expert) Use of Cogeneration in Japanese Industries Mr. Akira Ishiyama (JICA/ESCAP Expert on Energy Conservation) Tea Break Potential for Use of Cogeneration in the Industrial Sector in Bangladesh National Study Team of Bangladesh Regulatory Framework for Promoting Cogeneration Panel discussion with policy makers and industry representatives Prayer and Lunch Experiences with Promotion of Cogeneration in South Asia Mr. A. S. Bakshi (Ministry of Power, India) Mr. R. Ghimire (Water and Energy Commission, Nepal) Summary and Conclusion Tea Break Tour of the exhibition on Energy Technology
159
Programme of the South Asia Sub-Regional Seminar on BUSINESS OPPORTUNITIES IN COGENERATION Date: Place: Organiser: Sunday, 15 November 1998 Bangladesh University of Engineering Technology (BUET), Dhaka, Bangladesh Centre for Energy Studies and Mechanical Engineering Department (BUET), in Collaboration with Economic and Social Commission for Asia and the Pacific (ESCAP) Government of Japan Registration Official opening Introductory Statement by ESCAP Mr. Pranesh C. Saha (Chief of Energy Resources Section, ESCAP) Business Potentials and Trends in Use of Cogeneration in Industry Dr. B. Mohanty (Cogeneration expert) Results of Pre-feasibility Studies in Selected Industries in Bangladesh National Study Team from Bangladesh Tea Break Cogeneration Case Studies from South Asian Countries Mr. A. S. Bakshi (Ministry of Power, India) Mr. R. Ghimire (Water and Energy Commission, Nepal) Prospects for Cogeneration Development in Bangladesh Discussions and Conclusion Prayer and Lunch Optional: Individual Consultations Potential cogenerators from industries, manufacturers, suppliers, developers, financiers, consultants, etc.