SMITH-EMERY LABORATORIES An Independent Commercial Testing Laboratory, Established 1904

781 East Washington Boulevard Los Angeles, California 90021 Toro Glasswall Inc. 470 Edgeley Blvd, Unit A (north side) Concord, Ontario, Canada, L4K 4G4 ATTN. Eduard Ratz PROJECT: Series TGW1 unitized pre-glazed curtain wall system Subject: Performance testing. Mr. Ratz:

Phone (213) 749-3411 Fax (213) 741-8626

At your request, Smith-Emery Laboratories has provided testing at our Los Angeles facility on a series TGW1 unitized pre-glazed curtain wall system Installed by Toro Glasswall Inc. The accompanying report number L-10-259, presents a description of the tests performed, the results of our testing, and our conclusions. We appreciate this opportunity to be of service to you. If you have any questions regarding this report, please do not hesitate to contact us at your convenience.

Respectfully Submitted, SMITH EMERY LABORATORIES, INC.

Dana Nelson Curtain/Window Wall Manager Attachment: Report No. L-10-259 cc: File

CELEBRATING 100-YEARS

SMITH - EMERY LABORATORIES, INC. 781 E. WASHINGTON BLVD. LOS ANGELES, CA 90021 (213) 749-3411 PHONE (213) 741-8626 FAX

1904-2004

REPORT OF:

Series TGW1 unitized pre-glazed curtain wall system .

PREPARED FOR:

Toro Glasswall Inc. 470 Edgeley Blvd, Unit A (north side) Concord, Ontario, Canada, L4K 4G4

PROJECT NUMBER: REPORT NUMBER: REPORT DATE:

SE 39140 L-10-259 FEBRUARY 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 2 of 18

February 19, 2010

TABLE OF CONTENTS SECTION 1.00 1.01 1.02 1.03 1.04 INTRODUCTION Purpose Scope of Testing Specimen Description Test Methods

2.00

TESTING & FINDINGS

3.00 3.01 3.02 1.00 INTRODUCTION 1.01 Purpose

CONCLUSIONS AND CLOSURE Conclusions Closure

The purpose of our testing was to evaluate the installed conditions of the curtain wall mockup. 1.02 Scope of Testing The general scope of this testing program included the following: Perform testing in accordance with the ASTM and AAMA specifications. Preparation of this report providing descriptions and results of the above testing and our conclusions.

1.03 Specimen Description See Toro Glass wall system drawings. The MU was built of 9 unitized pre-glazed CW panels with over all size of 14.6 x 28.2 (4456 x 8596 mm).

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 February 19, 2010 Laboratory No: L-10-259 Page 3 of 18 1.04 Test Methods The general test methods used were. E283-91(1999) Standard Test Method for Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen, E330-02 Standard Test Method for Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference, E331-00 Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference, AAMA 501.1: Standard Test Method for Exterior Windows, Curtain Walls and Doors for Water Penetration using Dynamic Pressure AAMA 501.4 Seismic Drift. In addition to the test standards noted above, testing was performed in general accordance with generally accepted engineering principles and practices. They have incorporated federal, state and local laws, codes, ordinances and regulations, which in our professional opinion are applicable at the time of preparation of this report. 2.00 Testing & Findings. February 2010 TESTING SEQUEANCE 1. PRELOAD TEST PROCEDURE Preload at 50% of the inward design wind pressure 37.5 PSF (1795.5 Pa). ACCEPTANCE CRITERIA: Visually inspect the assembly for any detrimental affects. Results. Pass. Observations: No visual damage observed. 2. AIR INFILTRATION TEST (Ref: ASTM E 283) TEST PROCEDURE Cover and seal the mockup completely with polyethylene sheeting while leaving the chamber uncovered. Develop a positive differential pressure of 6.24 PSF (298.8 Pa) on the chamber. Record the airflow required to maintain this pressure. This number represents the airflow through the chamber. Remove the sheeting and reestablish the positive pressure of 6.24 PSF (298.8 Pa). Record the airflow required to maintain this pressure. This number is the airflow through the mockup and chamber. The difference between the two-recorded airflows is the airflow through the mockup.

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 4 of 18

February 19, 2010

ACCEPTANCE CRITERIA: 0.06 CFM per square foot of exterior surface, exclusive of any operating window and door areas. Mockup area x.06 = S.F. . Fixed area =25 CFM maximum allowable Total 3.2 CFM Results: Pass. Pretest Results 3. WATER PENETRATION UNDER STATIC PRESSURE (Ref. ASTM E 331) TEST PROCEDURE Establish a positive test pressure of 15 PSF (718.2 Pa) on the mockup. Apply water to the exterior of the mockup at a rate of 5 gallons per hour per square foot for a period of fifteen minutes while maintaining the differential pressure of 15 PSF (718.2 Pa). During this period, visually inspect the interior of the mockup for water penetration. ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior; (b) there would be no staining or other damage to any part of the completed building or its furnishings (c) No appearance of water on any visible interior surfaces. Results: Fail. Observations: Water was observed at the jambs of the mockup at the stack joint at the end dams interface with the chamber closure a non job condition. A Toro Glass wall representative performed remedial repairs. 4. WATER PENETRATION UNDER STATIC PRESSURE (Ref. ASTM E 331) TEST PROCEDURE Establish a positive test pressure of 15 PSF (718.2 Pa) on the mockup. Apply water to the exterior of the mockup at a rate of 5 gallons per hour per square foot for a period of fifteen minutes while maintaining the differential pressure of 15 PSF (718.2 Pa). During this period, visually inspect the

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 5 of 18 interior of the mockup for water penetration.

February 19, 2010

ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior; (b) there would be no staining or other damage to any part of the completed building or its furnishings (c) No appearance of water on any visible interior surfaces. Results: Pass. Observations: No water penetration was observed. 5. WATER PENETRATION UNDER DYNAMIC PRESSURE (Ref.: AAMA 501.1) TEST PROCEDURE Apply an air stream equivalent to a static differential air pressure of 15 PSF (718.2 Pa) to the mockup. Apply water to the mockup at a rate of five gallons per hour per square foot for a period of fifteen minutes. During this period visually inspect the interior of the mockup for water penetration. ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior: (b) there would be no staining or other damage to any part of the completed building or its furnishings: (c) No appearance of water on any visible interior surfaces. Results: Pass. Observations: No water penetration was observed. 6. STRUCTURAL TEST AT 50% & 100% OF INWARD DESIGN PRESSURE TEST PROCEDURE Apply positive pressure to the mockup of listed below PSF and hold for 10 seconds. Release the pressure difference across the mockup. After a recovery period of not less than 1 minute nor more than 5 minutes at zero load, record initial readings. Increase positive pressure to listed below PSF and hold for 10 seconds. Record deflection readings. ACCEPTANCE CRITERIA: Net deflection of any metal-framing members shall not exceed L/175 of the clear span or 3/4 whichever is less for spans less than 13-6 For spans over 13-6 Net deflection of any metal-framing

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 February 19, 2010 Laboratory No: L-10-259 Page 6 of 18 members shall not exceed L240 = center of glass shall not exceed Results. Pass. Transducer locations and deflections. Transducers 1, 2, 3 typical horizontal mullion. Transducers 4, 5, 6 typical vertical mullion. Maximum Allowable deflections at design. Transducer locations and deflections. Transducers 1, 2, 3 = 0.324 (8.2 mm) max Transducers 4, 5, 6 = 0.625 (15.8 mm) max. 30 PSF (1436.4 Pa) Net deflections 1, 2, 3 = 0.001 (0.03 mm) Net deflection 4, 5, 6 = 0.132 (3.4 mm) 45 PSF (2154.6 Pa) Net deflections 1, 2, 3 = 0.007 (0.2 mm) Net deflection 4, 5, 6 = 0.232 (5.9 mm) 55 PSF (2633.4 Pa) Net deflections 1, 2, 3 = 0.004 (0.1 mm) Net deflection 4, 5, 6 = 0.298 (7.6 mm) 7. STRUCTURAL TEST AT 50% & 100% OF OUTWARD DESIGN PRESSURE TEST PROCEDURE Apply negative pressure to the mockup of listed below PSF and hold for 10 seconds. Release the pressure Difference across the mockup. After a recovery period of not less than 1 minute nor more than 5 minutes at zero load, record initial readings. Increase negative pressure to listed below PSF and hold for 10 seconds. Record deflection readings. Reduce pressure to zero. ACCEPTANCE CRITERIA: Same as procedure (6) Results. Pass. Transducer locations and deflections. Transducers 1, 2, 3 typical horizontal mullion. Transducers 4, 5, 6 typical vertical mullion.

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 7 of 18 Maximum Allowable deflections at design. Transducer locations and deflections. Transducers 1, 2, 3 = 0.324 (8.2 mm) max Transducers 4, 5, 6 = 0.625 (15.8 mm) max. 30 PSF (1436.4 Pa) Net deflection 1, 2, 3 = 0.013 (0.3 mm) Net deflection 4, 5, 6 = 0.008 (0.2 mm) 45 PSF (2154.6 Pa) Net deflection 1, 2, 3 = 0.013 (0.3 mm) Net deflection 4, 5, 6 = 0.120 (3.1 mm) 55 PSF (2633.4 Pa) Net deflection 1, 2, 3 = 0.017 (0.4 mm) Net deflection 4, 5, 6 = 0.148 (5.0 mm) 8.

February 19, 2010

WATER PENETRATION UNDER STATIC PRESSURE (Ref. ASTM E 331) TEST PROCEDURE Establish a positive test pressure of 15 PSF (718.2 Pa) on the mockup. Apply water to the exterior of the mockup at a rate of 5 gallons per hour per square foot for a period of fifteen minutes while maintaining the differential pressure of 15 PSF (718.2 Pa). During this period, visually inspect the interior of the mockup for water penetration. ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior; (b) there would be no staining or other damage to any part of the completed building or its furnishings (c) No appearance of water on any visible interior surfaces. Results: Pass. Observations: No water penetration was observed.

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 8 of 18 9.

February 19, 2010

STORY DRIFT INPLANE OF CONSTRUCTION DELTA S DISPLACEMENT 2.25 (57.2 mm) each way from zero (Ref AAMA 501.4)

TEST PROCEDURE Using a hydraulic system the intermediate floor level will be moved to the left of center and then to the right of center this shall be repeated for three cycles. ACCEPTANCE CRITERIA No damage or disengagement of trim or snap on members glazing gaskets or sealant, no breakage of glass shall occur. Results: Pass. Observations: No damage or disengagement was observed. 10. WATER PENETRATION UNDER STATIC PRESSURE (Ref. ASTM E 331) TEST PROCEDURE Establish a positive test pressure of 15 PSF (718.2 Pa) on the mockup. Apply water to the exterior of the mockup at a rate of 5 gallons per hour per square foot for a period of fifteen minutes while maintaining the differential pressure of 15 PSF (718.2 Pa). During this period, visually inspect the interior of the mockup for water penetration. ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior; (b) there would be no staining or other damage to any part of the completed building or its furnishings (c) No appearance of water on any visible interior surfaces. Results: Pass. Observations: No water penetration was observed. 11. WATER PENETRATION UNDER STATIC PRESSURE (Ref. ASTM E 331) TEST PROCEDURE Establish a positive test pressure of 20 PSF (957.6 Pa) on the mockup. Apply water to the exterior of the mockup at a rate of 5 gallons per hour per square foot for a period of fifteen minutes while

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 9 of 18

February 19, 2010

maintaining the differential pressure of 20 PSF (957.6 Pa). During this period, visually inspect the interior of the mockup for water penetration. ACCEPTANCE CRITERIA: There shall be no unacceptable water leakage, defined as follows: The occurrence of condensation during water infiltration tests is acceptable. Other water leakage is acceptable only if all of the following conditions are satisfied: (a) the water is contained and drained to the exterior; (b) there would be no staining or other damage to any part of the completed building or its furnishings (c) No appearance of water on any visible interior surfaces. Results: Pass. Observations: No water penetration was observed. 12. STRUCTURAL TEST AT 75%, & 150% OF INWARD DESIGN PRESSURE (Ref. ASTM E 330) TEST PROCEDURE Apply positive pressure to the mockup of listed below PSF and hold for 10 seconds. Release the pressure difference across the mockup. After a recovery period of not less than 1 minute nor more than 5 minutes at zero load, record initial readings. Increase positive pressure to listed below PSF. Hold for 10 seconds Reduce pressure to zero. ACCEPTANCE CRITERIA: There shall be no glass breakage, permanent damage to panels, fasteners or anchors shall occur, No permanent deformation to wall or framing members. Results. Pass. Readings recorded were taken at load not at zero. Transducer locations and deflections. Transducers 1, 2, 3 typical horizontal mullion. Transducers 4, 5, 6 typical vertical mullion. Maximum Allowable deflections at 1.5 x design. Transducer locations and deflections. Transducers 1, 2, 3 = 0.062 (1.6 mm) max Transducers 4, 5, 6 = 0.125 (3.6 mm ) max

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 10 of 18 65 PSF (3112.2 Pa) Net deflection 1, 2, 3 = 0.008 (0.2 mm) Net deflection 4, 5, 6 = 0.140 (3.6 mm) 75 PSF (3591 Pa) Net deflection 1, 2, 3 = 0.010 (0.3 mm) Net deflection 4, 5, 6 = 0.210 (5.3 mm) 85 PSF (4069.8 Pa) Net deflection 1, 2, 3 = 0.010 (0.3 mm) Net deflection 4, 5, 6 = 0.258 (6.6 mm ) 13.

February 19, 2010

STRUCTURAL TEST AT 75% & 150% OF OUTWARD DESIGN PRESSURE (Ref. ASTM E 330) TEST PROCEDURE Apply negative pressure to the mockup of listed below listed below PSF and hold for ten seconds. Release the pressure difference across the mockup. After a recovery period of not less than 1 minute nor more than 5 minutes at zero load, record initial readings. Increase negative pressure to listed below listed below PSF hold for 10 seconds. Reduce pressure to zero. ACCEPTANCE CRITERIA: Same as procedure (12). Results. Pass. Readings recorded were taken at load not at zero. Transducer locations and deflections. Transducers 1, 2, 3 typical horizontal mullion. Transducers 4, 5, 6 typical vertical mullion. Maximum Allowable deflections at 1.5 x design. Transducer locations and deflections. Transducers 1, 2, 3 = 0.062 (1.6 mm) max Transducers 4, 5, 6 = 0.125 ( 3.6 mm ) max 65 PSF (3112.2 Pa) Net deflection 1, 2, 3 = 0.015 (0.4 mm) Net deflection 4, 5, 6 = 0.184 (4.7 mm) 75 PSF (3591 Pa)

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 11 of 18 Net deflection 1, 2, 3 = 0.016 (0.4 mm) Net deflection 4, 5, 6 = 0.218 (5.5 mm) 14.

February 19, 2010

STORY DRIFT INPLANE OF CONSTRUCTION DELTA M DISPLACEMENT 3.5 (88.9 mm) each way from zero (Ref AAMA 501.4) TEST PROCEDURE Using a hydraulic system the intermediate floor level will be moved to the left of center and then to the right of center this shall be repeated for three cycles. ACCEPTANCE CRITERIA No damage or disengagement of trim or snap on members glazing gaskets or sealant, no breakage of glass shall occur. Results: Pass. Observations: No damage or disengagement was observed. A maximum load of 100 PSF (4788 Pa) outward was placed on the test assembly with no failure observed. 3.00 CONCLUSIONS AND CLOSURE 3.01 CONCLUSIONS We make no statement of compliance other than a pass fail result of the material tested or analyzed to any specification. Based on specific data and information contained in this report, our general understanding of the test methods and principals involved, and general experience in the materials testing field, it is our professional judgment that all portions of this mockup meet the requirements set forth in the testing specifications and documents. 3.02 CLOSURE The findings in this report were prepared in accordance with generally accepted material engineering and testing principles and practices. No other warranty, either expressed or implied, is made. This report has been prepared for the above named client for the above named project. The use of this report for any other purpose shall be at the users own discretion based on their own interpretation of the results contained within. END OF REPORT

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 12 of 18

February 19, 2010

Respectfully Submitted, SMITH EMERY LABORATORIES, INC.

Dana Nelson Smith-Emery Laboratories 781 E Washington Blvd Los Angeles, Ca 90021 213-749-3411 x 348 213-494-3636 cell 213-746-7228 fax Email: dnelson@smithemery.com

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 13 of 18

February 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 14 of 18

February 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 15 of 18

February 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 16 of 18

February 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 17 of 18

February 19, 2010

SMITH-EMERY LABORATORIES
An Independent Commercial Testing Laboratory, Established 1904 781 East Washington Boulevard Los Angeles, California 90021 Phone (213) 749-3411 Fax (213) 741-8626

File No: 39140 Laboratory No: L-10-259 Page 18 of 18