Вы находитесь на странице: 1из 21

Title: No.

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

BARAN ENGINEERING (SOUTH AFRICA)

TRAFFIC MANAGEMENT PLAN FOR ZTE ROJECT


Procedure number BRN-HSE-ZTE -PLN-006 - Rev 1

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

Name Prepared By: Reviewed By: Approved By: T. MAGENGELELE

Title HSE Manager Rollout Manager Project Director

Signature

Date

WORKPLACE: MAIN CONTRACTOR : ZTE SUB-CONTRACTOR: BARAN ENGINEERING SECTION: VENTERSBURG TO BLOEMFONTEIN LEG:

DATE FROM: 20/03/2012 TO: 20/09/2012 SANRAL ROUTE MARKERS FROM: N1 VENTERSBURG TO N1 BLOEMFONTEIN CONTRACTOR /SUPV: BARAN ENGINEERING TYPE OF CLOSURE: SHOULDER

================================================================ THE PLAN SHALL CONTAIN THE FOLLOWING: The Advance Warning Area
This area is used to advise motorists that there are temporary conditions ahead of them which require particular care.

The Transition Area


This is the area in which drivers are required to take an action, such as:

shift position on the roadway without reduction in the number of lanes; merge two lanes into one (lane drop); cross the central median (crossover); to enter a detour completely separate from the road under construction.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

The Stabilising Area


The purpose of this area is to allow traffic flow to stabilise after negotiating a transition area before reaching another change of condition.

The Buffer Zone


This is the limiting form of stabilising area. It is normally used between a transition area and the work area.

The Work Area


This area must be adequately defined by delineators in the less complex conditions. Where there is a risk to traffic or workers of vehicles entering the work area, temporary barriers of a standard sufficient to prevent vehicle penetration are recommended.

The Termination Area


This area involves the return of traffic to normal flow conditions. In simple cases, this can be achieved by a relatively rapid taper of delineator signs.

THE SIGNAGE:
The signs will be the right size (1.2m for rural, and 0.9m for urban, as per SARTSM chapter 13), with the correct colours and have a retro- reflective background. All signs will be placed just off of the road surfacing (tar), and are not to be obstructed by any netting, etc. The signs sequence for CONSTRUCTION will be as follows: the men at work 800m with a flag man/women from the work area then the 100km board at 600m, the 80km at 500m, the advance warning at 400m, the 60 km at 200m before the work area, at the work area a flagman/women per machine and the delineators will be spaced at 50m intervals and placed on the outside edge of the surfacing. The 120km and end thank you board will be at the end of the termination area to speed up the traffic again. This sequence will not exceed 5 kms. An open area of minimum 5.0 kms must be allowed between sign sequences. The sign sequence for STOP/GO will be as follows: the men at work 800m with a flagman/women from the stop/go, then the 100km board at 600m, the 80km at 500m, advance warning at 400m, the stop/go ahead at 200m, the 60 km at 100m before the stop/go with a flagman/women, the work area will be covered with delineators spaced at 50m intervals. The 120km and end thank you board will be across the 200m mark of the opposite set of signs. The signs and flag men/women will be on both sites of the highway. The stop/go sequence will not exceed 3km, with an open area of 4km before the next one commence. There will not be more than three (3) stop/go at any time in one section. The sign sequence for SHOULDER DROP (Offloading import soil, offload of equipment or stationary equipment such as compressors parked on the shoulder) will be as follows: the men at work 800m with a flagman/women from the drop site, the 100km at 600m, the shoulder blocked sign (TGS133) at 600m, the 80 km at 400m, this will be applicable on the other side of the highway also. The 120km and end thank you board will be across the 500m mark of the opposite set of signs. The signs and flagmen/women will be on both sites of the highway.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

At all shoulder drop closures, the start and end of the area will be tapered by means of delineators at intervals of 10m, with a flagman/women at the start of the taper. The numbers of all signage will be on the drawing next to the sign and the different areas indicated. Delineators will be next to the road every 50m where the closure is in operation, and will have sand bags on them. The speed of the traffic will be reduced to 80km or 60km per hour, as appropriate, in the working area and after the work area the speed will return to 120km per hour, all boards will be in place as seen on the drawing. Where only REINSTATEMENTS or PRE-CLEARING are done, the signs will be moved along as the reinstatement team is moving. A rotary flag man will be moving with the team and a stationary flag man will be at the men at work sign. The sign sequence will be as follows: the men at work 600m, the advance warning (TW339) at 400m and the 80 km at 200m The sign boards to be used is Warning signs (men at work TW 336-WA, advance warning TW 339, stop/go ahead TW 343-TIN11.2, end thank you TW 336-TIN11.4, road narrow to one side TW330), commonly used Temporary Regulatory Signs (120 km/h - R 201-120), (100 km/h - R 201/100), (80 km/h - TR 201-80), (60 km/h - TR 201-60), (40 km/h - TR 201-40), control Regulatory Signs (stop/go R1.5A R1.58) and delineators of 0.8m high TW401 & TW402 shoulder blocked sign - TGS133. The boards will be a minimum of 1.2m in size, and the sand bags that is going to be used is a minimum of 15kg there will be 4 or more on each signboard frame at the corners. The sand bags will be filled with sand and not with stones.

FLAGMAN/WOMAN:
In the work area there will be a flagman/women at every activity that will take place. Flags will be used that are at least 450mm x 450mm in size, thats made of a red cloth with a fluorescent X on it. Flagmen/women will be located far enough from the work area to ensure that drivers have sufficient distance to slow down before entering the work area. Distinctive PPE clothing will be worn by the flagmen/women (reflective jacket or bright colour overall with reflector strips on the jacket and trousers. Flagmen will be trained and inducted.

TYPES OF CLOSURE: 1. Pre clearing of work area. 2. Normal construction work. 3. Reinstatement & Testing. 4. Shoulder drop Compressor. 5. Stop/Go Blasting & Special circumstances. Deliverys to be incorporated with points 4 & 5, whichever is applicable.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

THE FOLLOWING RECORDS WILL BE KEPT:


Road Traffic Signage control register

Road Traffic Control Training records

Approved Road Traffic Management plan (SANRAL)

Daily Road traffic plan Inspection Records

RISK ASSESSMENT
1. The following risk should be considered when working on roads and freeways. Danger to drivers, danger to workmen, danger of collisions caused by work activity or confusion caused by incorrect signage, danger of blocking view caused by bystanders, crime and theft on site. Remember you may lose signs overnight so have spare ones on site.

2. Pre-Planning Go to the site and look for dangers, a proper risk assessment is the key to success. You need to look out for: blind rises, blind bends, pedestrian traffic, even if not allowed on a freeway, weather conditions, rainy or tends to have fog, cattle crossings, traffic density, and general traffic behaviour. Place your signage with intervals of at least 50m separation between signage. No painting of any road surfaces are allowed, it is an offense. Stopping on the freeway is not allowed, so your vehicle needs to be clearly marked in visible fashion. Your rotating light and hazards of the vehicle should remain on and preferably 1m from the road surface. This means not in the emergency lane but 1m from the end of the road surface on the grass. Wear a reflective jacket at all times.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

3. Requirements on Site You need to have the following on site: Generators and lights for night and or for poor visibility working Spare torches with batteries Road Signage. Portable Toilets Reflective jackets, full PPE for all staff members working in the road or not Risk Assessments I.D document copies of all staff members , required when admitted to Hospital Roll calls and Attendance registers for staff and site vehicle details Amber rotating /LED lights for the site vehicles. Workmans Compensation Number and relevant documents Appointment letters as per OHS ACT First Aiders documentation and equipment Proper First Aid Kit as per OHS Requirements Camera to record progress and also to record an incident that might need to be documented. Way leave and any documents required to work on the road and metro areas. Manhole barricades and trenching barricades Measuring wheel

4. Danger to Drivers Drivers are in control of the vehicle and the signage is there to tell him/her what to expect on the road surface, therefore it is important to make sure all signage is set up correctly before commencement of work.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

The signage must regularly be inspected by the appointed Construction Supervisor.

5. Planning All planning should be done before hand. You need to know what you are going to do work wise, how long it is going to take, where it is going to be. You need to look at traffic specific problems and also a plan for an emergency situation i.e. that your work is taking longer than expected or it starts to rain. On a highway you need to put up signage on both sides of the road and in both directions of the highway. Except for normal construction were signs on one side will be sufficient.

6. Highways 0 -120km/h If the maximum speed is high, more signage needs to be correctly laid out. Blind rises and corners will require a longer period of warning to drivers. Weather conditions should be considered when it becomes misty or the road surfaces are prone to skidding. If it rains no roadwork is allowed on any road surface because of the risk of skidding and low visibility.

7. Signage Signage should be deployed in the following fashion for a freeway and in sequence below and in accordance with Chapter 13, Volume 2 of the South African Road Traffic Signs Manual.

8. Securing Signage All signage will be secure with sand bags filled with river sand, no rocks or stones are allowed to be placed on the road surface at any time, even when the signage has a supporting frame that will seem to collapse. By securing

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

them with sand bags they will remain upright and if a collision occurs the damage will not be severe to the vehicle involved.

9. Placement of 100km/h speed restriction 100km/h boards to be placed first. This is to warn the driver and to increase the distance to your site and that he has a longer period to slow down and to react to the speed.

10. Placement of Men at Work Board This warns you that your driver is to look out for pedestrians or pedestrians that might cross the road. It also warns that construction is taking place.

11. Placement of No passing Signs This warns the driver not to pass as there is a lane restriction.

12. Placement of Road Narrowing Signs This is to warn that lane restrictions will be in effect shortly, and it will show if it is on the left or on the right side of the road.

13. Placement of 80km/h speed restriction Signs 80km/h signs warn the driver to slow down.

14. Arrow Sign Boards This is to show that the road is narrowing and that the traffic has to move to the left or to the right in the direction of the arrow. Also make sure that if the road is closed from both sides that it is indicated as such.

15. 60km/h Speed Restriction Sign Boards Placements 60km/h signs warn drivers to reduce speed and to slow done.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

16. Placement of 40km/h Speed Restrictions (Only if applicable) 40km/h sign warns drivers to slow down and to reduce their speed. The lowest speed on any Freeway is 60km/h and this will indicate the seriousness of the operations. Traffic Police Departments differ on this issue; however try to get the speed low as possible for the areas where you work. This will reduce your liability if someone gets injured in a crash as there were fair warning signs in place.

17. Placement of Cones and Delineators All cones and or delineators are to be deployed 5m interval 100m from the site. This is to warn that people are working next to the road. The cones and or delineators should pass the site at least 50mts. Cones and or Delineators are to be used to guide traffic and not for an informative sign. Note that a cone in the middle or shoulder of the road or freeway is a hazard and could cause injuries or damage to vehicles.

18. Flagman/Women and their use They need to know what signs are applicable to traffic and merely waving a flag means and accomplishes nothing. Flagmen/Women get tired, have a replacement available as it is hard work and a very important function that or which often gets given to a less skilled employee. Flagman/Women should be placed at the beginning of your Workman Board Signage on both sides of the road and should be placed again 150m from your work area to slow traffic down.

19. Lane Closure You are not allowed to close any road if it is not written on your Way Leave, unless you have applied for permission from SANRAL for such lane closure and written approval thereof has been obtained.

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

20. Thank You Construction Work Ended Signage This sign must be placed 100m away from the construction site. This will indicate to the drivers that they may return to normal speed prior to the construction operation.

21. Barricading Barricading net to be used at all times. Barricading which has the support of two wire strands spaced between anchor points and the barrier netting between the wires. The first line wire must be 50 cm from the ground level and the second wire line a meter from ground level. Pegs must be used and placed at intervals of 5m and it should be 500mm below the surface and 1m above the surface. Barricading is not a substitute for signage.

22. Vehicle Markings All vehicles to be marked with a construction vehicle sign and company logo. Each vehicle must have a warning flashing approved high density amber/LED Light (55W AE or similar) and must be visible in the day and when weather conditions are not good (mist/fog).

23. Record Keeping Maintain all documents as stipulated in the SHE Plan and NATIONAL LONG
DISTANCEROADTRAFFIC MANAGEMENT PLAN AND IMPLEMENTATION GUIDELINES

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT ZTE-HSE-FBC-PLN-012 - Rev 0

APPROVED BY:

HSEQ DEPT :

DATE:

Contractor:
for approval 24. Related Documents

DATE:

Ensure that the site specific drawing/sketch for the type of closure is attached

Document Ref. BRN-HSE-ZTE -PLN001Rev 0

Document Title EHS Management Plan ZTE PROJECT

25. Forms

Form No.

Form Title

Rev No.

N/A 26. Notes and Attachments

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

SAFETY, HEALTH AND ENVIRONMENTAL RISK ANALYSIS

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act) Accident, condition Medical

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines) Employment persons controls to for do

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

Driving

Driver competent, wrong

not

Zero

accidents/incidents to driving, audits, Evaluated

required

related reports,

driving. (License, alert, obeys Traffic Act.) Safe driving techniques, Warning of use of drugs, fatigue controls. Accident, fatalities, Clear speed regulation signs, visible traffic control vehicles on site, law enforcement authorities, security officers c 3 4 6 H medical condition

monitor via near miss inspections. monthly Zero accidents/incidents to driving, audits, Evaluated related reports, inspections. monthly

posture, falling asleep Drunk driver Speeding Driver disobeying, road rules and signs, driver overtaking on stop and gos

monitor via near miss

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act) Obstruction signage, of

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines) Protection of the public and controls for entering an area where workers are working at elevations. Where necessary, post a flagman to safely direct passing pedestrians. traffic Never and allow

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

Working site, Safety Awareness

on Public

Adjacent construction sites

to

12

No

reported

incidents, via audits,

creation of

monitored suggestions, inspections.

fall hazards, material falling from vehicles, vehicle accidents near work obstruction roadway pavements. areas, of and

cranes to load and unload vehicles over passing traffic or pedestrians. or covered Construct walkways to temporary protective gantries provide protection when

workers are working above areas where the public or other workers need to pass. Barricade areas under cranes to
23-03-2012

separate

passing

traffic

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act)

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines) from crane-lifted loads. Traffic control around excavations and trenching Barriers, hazard cones, signs, flagmen, two-way radios, etc. as per risk assessment.

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

Traffic management

Roadsides

Traffic

accidents

Traffic management plan to be adhered to, induction training, RA training, signs, flagmen, proper supervision

No

reported

incidents, via audits, Traffic

resulting in injuries or fatalities and property damage. Failure of drivers to adhere signage, to safety flagmen

monitored suggestions, inspections.

management plan to be adhered to Areas to be kept clear, discussed at HSE meetings.

resulting in injury. Workers not adhering to traffic management plan requirements and being
23-03-2012

involved

in

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act) accidents. People and working hit too by close to side of road being vehicles.

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines)

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

Flagman

Roadside

Run over by vehicles.

Training, Use of correct PPE when entering the construction site. (High visible clothing, Safety shoes, etc.) Safety Signage, Induction

12

adhered to Areas to be kept clear, discussed at HSE meetings.

Delivery vehicles/ offload loading and

Work Area

Obstruction of traffic, accident, derailment,

Flagman Hazard signage

to

control

traffic,

No

reported

incidents, via audits,

bunksman to direct vehicles, communication

monitored suggestions, inspections.

Rainy Conditions

Roadside

Slippery road

Correct

signage,

avoid

oil c

12

No

reported

incidents, via audits,

accidents, legal liability, losses

spillage, speed control,

monitored suggestions, inspections.

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act)

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines)

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

vehicles parking at the side road of the

Roadside

Injuries Fatalities Legal Production/Serves liability

Site manager/Project manager or c authority on site to speak to the driver.

No

reported

incidents, via audits,

monitored suggestions, inspections.

Construction close roadside to

Road closure

vehicles not adhering to Temporary stop/go signs security patrol

Speed personnel,

humps, c highway

12

No

reported

incidents, via audits,

monitored suggestions, inspections.

Workers civilians working passing roadside Emergency vehicles

and or the

roadside

Accidents, run over by vehicles, fatalities Injuries,

Road control,

signage,

Induction

12

No

reported

incidents, via audits,

monitored suggestions, inspections.

Work area or roadside

Collision/ Derailment

Flagman

to

direct

traffic,

No

reported

incidents, via

Induction training,

monitored

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Location Task activity or conditions

or

Environmental

Likelihood

for Risks to task activity or

"hazard"

means

mitigate the Risk.

(Also

Health & Safety

Hazards source of or exposure to danger. (OHS Act)

Controls to eliminate or refer to the applicable Safe Work Procedures and Safety Guidelines)

Severity

Risk Value (1 Damage 25)

Risk Assessed (High, Medium or low)

Target/objective

suggestions, inspections. Construction works close to road Dust Noise and

audits, incidents, via audits,

Diseases and disability.

Personnel Protection Equipment Use of correct PPE when entering the construction site. (High visible clothing, Safety shoes, etc.)

No

reported

monitored suggestions, inspections.

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

THIS MATRIX MUST BE USED TO RATE THE CRITICALITY OF TASKS 1. SEVERITY INDEX

0 No risk of injury, illness or quality / problems.


2 Minor risk of injury, illness not a lost time, non disruptive property damage, quality/production problems resulting in loss between R1 000-00 R10 000-00. 4 Risk of a lost time injury without permanent disability, disruptive property damage quality / production or other losses between R10 000-00 R50 000-00. 6 Risk of permanent disabling injury, loss of life/body part or other losses exceeding R50 000-00. 2. Frequency Index

NO TIMES TASK PERFORMED BY EACH PERSON

NO OF PERSONS PERFORMING TASK

LESS THAN DAILY

FEW TIMES PER DAY

MANY TIMES PER DAY

FEW

MODERATE NO.

MANY

3. Probability Index -1 Low probability

0 Moderate probability +1 High probability

Factors to be Considered - How dangerous is the task

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

- How difficult is the task - Complexity of task - The chance that there will be a loss if task is performed improperly - Any rating above 8 will require actions to address issues e.g. procedures, guarding, training etc. PRIORITY GUIDE

Once a risk rating has been calculated, the following scheme should be used to assign priority of action. It should be noted that if action is not taken within the time specified, then the continued toleration of the residual downside risk should be explicitly authorized. The suggested level of seniority for authorization is as shown below.

Priority

Risk Rating

Suggested action

Authority for continued toleration of residual risk

Greater than 8

Cessation until the residual risk is reduced to 8 or below - unless exposure is authorized as indicated.

PD

68 46 24

Take action to reduce residual risk to 6 or below

PD

Specific action to deal with risk daily

PD

Plan in keeping with all other priorities

PD

Below 2

Low priority

PD

Related Documents
Document Ref. ZTE-HSE-FBC-PLN001Rev 1 Document Title EHS Management Plan ZTE project

23-03-2012

Title: No.:

RISK ASSESSMENT FIBRECO PROJECT BRN-HSE-ZTE-PLN-012 - Rev 2

Forms
Form No. N/A Form Title Rev No.

Notes and Attachments


None

23-03-2012

Вам также может понравиться