Design Basis Site Master Plan Statutory Drawings Plan Sec. & Elevation Of Extension Building Details Of Doors & Window , Finishing Schedule
Civil
Design Basis & General Notes Preparation Of Complete Civil BOQ And Tender Speciifications L/D Of Foundation And Column L/D Of Plinth Beams L/D Of Floor Beams And Slabs L/D Of Roof Truss L/D Of Equipment Supporting Beams
Piping
Design Basis Piping Element Specifications Equipment Layout Piping Layout Mechanical & Piping Tender Specifications
Electrical
Design Basis Electrical Equipment Lists Electrical Equipment Specifications Load List And Transformer Sizing Single Line Diagram Complete Cable Trey Layout Lighting Power And Earthing Layout Cable Schedules Electriacal Tender Specifiacations
Instrumentation
Design Basis & Specifiacations Index Of Instruments
I/O List Cause And Effect Diagram Loop Diagram Hook Up Drawings Instrument Layout / JB Schedule Cable Trey Layout Cable Schedule And JB Schedlue Bill Of Material Instrumentation Tender Specifications
Tendering
Civil Works
Floating Of Tender Receipt And Opening Of Tender Technocommercial Negotiation Draft LOI / Work Order
Electrical
Floating Of Tender Receipt And Opening Of Tender Technocommercial Negotiation Draft LOI / Work Order
Instrumentation
Floating Of Tender Receipt And Opening Of Tender Technocommercial Negotiation Draft LOI / Work Order
PROCUREMENT
Mechanical Items Long Lead Items Enquiry Floating Offer Receipt TBA / CBA & Recommendations Vendor Meeting PO / LOI From Client
DELIVERY
Mechanical Equipments Electrical Equipments
ELECTRICAL
Contractor Mobilization MCC and Cabling Earthing And Cable Termination Lighting Protection System Yard Cabling Parking Area Street Lighting Electrical Fixtures Fixings Testing And Commissioning
INSTRUMENTATION
Contractor Mobilization MCC and Cabling Installation Of Instruments Instrumentation And Control Cabling Termination,Continuty & Loop Checks
HANDOVER
Duration
348 Days
2 Days 10 Days 305 Days 277 Days 7 Days 15 Days 20 Days 15 Days 15 Days 20 Days 20 Days 5 Days 222.8 Days 3 Days 10 Days 25 Days 20 Days 15 Days 6 Days 12 Days 14 Days 7 Days 8 Days 8 Days 8 Days 220.22 Days 10 Days
% Complete
71%
100% 100% 76% 97% 100% 100% 100% 100% 100% 80% 100% 100% 96% 100% 100% 100% 100% 80% 100% 100% 100% 100% 90% 100% 50% 100% 100%
Start
7-May-10 5-Jul-10 6-Jul-10 12-Jul-10 12-Jul-10
Finish
11-Feb-11 7-Jun-10 19-Jul-10