Академический Документы
Профессиональный Документы
Культура Документы
Introduction
A B C D E
2 2 5 3 3 2 2 2 2 2 2 2 1 2 1 2 1 2 2 2 2 2 2 2 2 2 2 2 2
Introduction
Assumption
We have all the resources needed for the schedule
Reality
Resources may not be available when needed.
Solution
Special adjustments have to be made to the schedule to properly manage available resources and meet project constraints.
How to
Resource Leveling Resource Allocation Time-Cost Tradeoff
Time
Time
Methodology
Shift non-critical activities within their float times so as to move resources from the peaks to the valleys, without any project delay.
Bottom Line
Critical activities remain unchanged No project delays
- Slow progress in beginning (small number hired) - Steady progress midway (full number hired) - Slow progress at end (slow resource release)
H1
Mx=160 My=166 40 RD
H2
Mx=166 My=255 40 RD
H3
Mx=160 My=316 40 RD
Days
(Mx)1 = (Mx)3 < (Mx)2 The single moment Mx does not consider for the extended assignment of the resource.
(Equation 2)
(M ) (M ) (M )
j =1
y 1 y 2 y 3
The value My gets higher as the resource remains employed in the project till a later date. My can be used as a good indicator of the resource release date in the project.
Resource amount
Days
M y = (1 Resource Demand j ) ( j k )
n j =1
(Equation 3)
Scheduling under these resource constraints becomes a complex problem, particularly when more than one resource is limited.
Heuristic solutions
Use simple rules of thumb
Eg: the resource can be assigned to activity that have smaller total float values than others.
The project is scheduled to be 32 days when any resource limits are not considered.
22
40
Example
Activity Name A B C D E F G H I J K L M N O P Q R S T Duration (days) 6 3 4 6 7 5 2 2 2 6 1 2 4 2 3 5 8 2 6 2 Daily Resource Limits A,B C D A,B G,H F C,E E,G,H I,K F,L L J,M,N O D,O P,R Q A Predecessor Activities Resource Requirements per Day R1 5 3 2 5 3 4 4 5 3 1 3 3 2 1 5 3 4 5 2 1 7 R2 2 5 4 4 5 1 1 5 2 5 3 2 2 4 5 2 5 3 4 6 10 R3 2 2 4 3 2 4 4 4 4 4 2 2 2 4 4 3 4 3 6 2 10 R4 2 3 2 5 3 9 3 0 3 6 4 8 2 3 6 4 2 3 2 7 16 R5 7 9 3 5 8 2 9 9 4 7 5 3 4 4 2 7 3 7 3 5 18 R6 4 6 1 4 0 5 8 1 2 3 1 4 8 1 3 8 4 8 4 2 13
Example
Manual Calculation of Resource Allocation
49 days
Time
Duration 6 4 2 6 8
Decision Start Start Start Continue Continue Start Continue Continue Start
2 L3=1 L2