PUP-CAFA BS Interior Design 1 OJT Summer 2012 OJT Daily Log Page of 2
May 7 Senador
Middle Name
, 2012
Francis Joseph
First Name
Office/Company Name:
Address: Suite 221, LRI Design Plaza, 210 Nicanor Garcia St., Brgy. Bel-Air Makati City Project Title: Verar Residence Project Description: Site Visit
Project Location: Unit 5117, West Tower One Rockwell, Makati City Assigned Work Task: Site Visit, Time In Time Out : : 10:00 am 6:00 pm good Total No. of Hour/s Spent: Site Condition: 8 Office / Site Others, pls. specify
Weather Condition:
good
Work Activities Performed: Ocular inspection, preparing working permits, assisting and guiding of workers.
Personal Observations at the Project Site: I observed that workers are being careless in maintaining materials safe. The flooring are full of scratch, the primary architect which is concern is did not doing3his job properly he delivered and prepared materials incorrect. Report/s Submitted, if any: Lesson/s Learned: I learned how accompany people specially workers, materials and furnishings should care properly to avoid problems and should be prepare in decision making in an unexpected situations.
PUP-CAFA BS Interior Design 2 OJT Summer 2012 OJT Daily Log Page of 2
Certified True and Correct by: IDr. Nina Rica M. Santamaria Mentor
(Signature above Printed Name)
Noted by:
May 8 Senador
Middle Name
, 2012
Francis Joseph
First Name
Office/Company Name:
Address: Suite 221, LRI Design Plaza, 210 Nicanor Garcia St., Brgy. Bel-Air Makati City Project Title: Verar Residence Project Description: Turn Over
Project Location: Unit 5117, West Tower, One Rockwell, Makati City Assigned Work Task: Final Set-up Time In Time Out : : 10:00 am 6:00 pm good Total No. of Hour/s Spent: Site Condition: good 8 Office / Site Others, pls. specify:
Weather Condition:
Work Activities Performed: Final Set-up for turn-over of the unit to the owner.
Personal Observations at the Project Site: There is still pending items to use for the designs. Some items are broken; some of furnishings dont look good. Report/s Submitted, if any: Lesson/s Learned: We should guide and instruct the contractors earlier and if not done well we should know and learned to be strict sometimes for the sake of good design results.
PUP-CAFA BS Interior Design 4 OJT Summer 2012 OJT Daily Log Page of 2
Certified True and Correct by: IDr. Nina Rica M. Santamaria Mentor
(Signature above Printed Name)
Noted by:
May 9 Senador
Middle Name
, 2012
Francis Joseph
First Name
Office/Company Name:
Address: Suite 221, LRI Design Plaza, 210 Nicanor Garcia St., Brgy. Bel-Air Makati City Project Title: Verar Residence Project Description: Punch Listing
Project Location: Unit 5117, West Tower, One Rockwell, Makati City Assigned Work Task: Inspection Punch,Listing Time In Time Out : : 10:00 am 6:00 pm good Total No. of Hour/s Spent: 8 / Office / Site Others, pls. specify:
Weather Condition:
Personal Observations at the Project Site: It result good even if there is still pending designs. Report/s Submitted, if any: Lesson/s Learned: I learned how to pinch list and prepared it in a simple way.
PUP-CAFA BS Interior Design 6 OJT Summer 2012 OJT Daily Log Page of 2
Certified True and Correct by: IDr. Nina Rica M. Santamaria Mentor
(Signature above Printed Name)
Noted by:
May Senador
Middle Name
10 , 2012
Francis Joseph
First Name
Office/Company Name:
Address: Suite 221, LRI Design Plaza, 210 Nicanor Garcia St., Brgy. Bel-Air Makati City Project Title: De Quirros Residence Project Description: Updating
Project Location: Unit 1104, Regency Tower, Salcedo Village Makati City Assigned Work Task: Power Point Presentation Time In Time Out : : 10:00 am 6:00 pm good Total No. of Hour/s Spent: Site Condition: 8 / Office Site Others, pls. specify:
Weather Condition:
Certified True and Correct by: IDr. Nina Rica M. Santamaria Mentor
(Signature above Printed Name)
Noted by:
May 11 Senador
Middle Name
, 2012
Francis Joseph
First Name
Office/Company Name:
Address: Suite 221, LRI Design Plaza, 210 Nicanor Garcia St., Brgy. Bel-Air Makati City Project Title: Squirres Bingham Project Description: Shop Drawing Revisions
Project Location: 2nd St. Sapphire Bldg. Bonifacio Global City Tagguig, Assigned Work Task: Shop Drawing Time In Time Out : : 10:00 am 6:00 pm good Total No. of Hour/s Spent: Site Condition: 8 / Office Site Others, pls. specify:
Weather Condition:
Work Activities Performed: Shop Drawing of a Display Shelves and Display Table for Squires Bingham.
Lesson/s Learned: I learned how to make details of a simple construction of the furniture.
PUP-CAFA BS Interior Design 10 OJT Summer 2012 OJT Daily Log Page of 2
Certified True and Correct by: IDr. Nina Rica M. Santamaria Mentor
(Signature above Printed Name)
Noted by: