Академический Документы
Профессиональный Документы
Культура Документы
FACTORS TO BE CONSIDERED 1.POPULATION FORECASTING From the available census of previous years for a particular locality,the population after 3decades is decided by Arithmetic Increase method and various units of the project are accordingly designed:Available Census : YEAR 1961 1971 1981 1991 2001 2011 POPULATION 38211 105491 219211 411542 657477 881988
1|Page
2.PER CAPITA DEMAND: According to IS code on Basic Requirements of water supply, Drainage and Sanitation IS: 1172-1993. i. ii. iii. iv. Domestic water demand Industrial water demand Institutional and commercial water demand Fire demand = 135 L /C / = 30L/C/ = 10 L /C / = 1 L /C /
Existing water supply capacity = 240MLD Additional water to be supplied by the end of the year 2041=280240=40MLD.
2|Page
SOURCE OF WATER:
After detailed survey of the various sources of water available in the vicinity of BHUBANESWAR, the selected source of water is nearly river MAHANADI. Considering most important factor, such as: cost , location, quality of water, quantity of water the selected source is OK.
Assuming the pumping takes place for 16 hours a day. The discharge to be pumped : Q= = 1.25 m3/sec m3/sec
3|Page
Let us provide 2 ports at each level. The size of each port will then be of 2.2 m height 2.5 m length. In all, there will be 6 screened ports: 2 at each of the three levels.2 screened parts will thus be provided within the well staining between RL 33.2 m to 31.0 m each having 2.5 m length 2 other screened ports shall similarly be provided between RL 40.5 m to 38.3 m; and 2 others between RL 45.7 m to 43.5 m . These parts can be fitted in a oblong well, consisting of rectangular length 5.2 m (sufficient to fix 2 bar screen of length 2.5 m) and provided with circular ends. The well can have a width of say 3 m.
4|Page
The inlet well can be sunk into the river bed by say 3 m below the river bed, as to provide space for accumulation of sand and silt. So, Let us keep the bottom of inlet well at RL 24.7 m. Also, let us provide a free-board of 2 m over maximum water level to fix the bottom level of the roof of the level.Hence,provide invert level of roof at 47.7 m .The height of inlet will then be 47.7 m -24.7 m =23m.
=1.15 m .
Hence using standard size of 1.2 m diameter RCC intake pipe, giving a velocity of : Using mannings formula, we have v = R2/3
=> 1.1 =
2/3
V =
= 1.1 m/sec.
Slope S=
; Say 1 in 500
5|Page
DESIGN OF PUMPS FOR SUPPLYING RAW WATERFROM JACK WELL TO TREATMENT PLANT:
As the water treatment plant is to be situated far from the intake structure. so the water has to be pumped from the jack well to the treatment plant. Q = 1.25 m3/sec [same as that of intake structure] L = 1450 m [Distance between intake well and raw water tank in water treatment plant] Velocity in pipe to be maintained V =2.4 m/sec. Area required Diameter of main required A = d= =0.814 m .(Say 1 m standard RCC pipe.) Total lift including suction and delivery = 30 m [Height of jack well 3 m] Head loss due to friction in pipe Hf = = =12.77 m . Total height against which pump has to work = 30 + 12.77 = 42.77 m. = =0.52 m2
6|Page
BRAKE HORSE POWER OF PUMP: = = =891.95 HP =1000 HP Hence we can use 3 centrifugal pumps of 500 HP. Two of that operating and one is kept as stand by.
Provide two nos. Of tank area of each tank = 4000 m2 Assuming a ratio of L : B =1.6:1 1.6B B =4000 B = 50 m , L = 80 m
7|Page
+2/3 +2/3
H = 0.058 m.(Say 6 cm). So, total depth of 6 cm shall be flowing over the weir.
STEPS:
Six steps of 0.3 m shall be provided, on which the water shall be flowing down to the outlet chamber. At the outlet chamber, one side wall has be kept 200 mm below the top surface of the tank so as to prevent the excess flow of water towards alum mixing chambers. Twelve pipes of 300 mm diameter have been provided at the outlet of aerator to the alum mixing chamber. Enough discharge of water will flow turf alum mixing through these pipes. The overflow shall take place only when the outlet of alum mixing chamber are clogged.
8|Page
All the masonry walls shall be plastered. The wall thickness has proposed to be kept as 0.4 m.
ALUM DOSE:
The dose of alum varies from 15 to 20 mg/litre of water but actual dose is to ascertained by experiments in the laboratory from time to time. The optimum coagulation occurs when PH value of water is between 6 to 8. Since alum makes the water acidic, the alum dosing tank will be laid with rubber or perfectly polyethylene tanks shall be used .Here, we shall use fire such tanks each of 3000 L capacity. Now, assuming the peak alum dose to be 20 mg/l and normal dose to be 20% of that, we get Alum required @ 20 mg/l = = 800 kg/day
Only 20 % 800 kg shall be used in normal conditions. Thus, for most of the year, the alum to be used will be 160 kg/day.
ALUM DOSERS:
Alum doser is the appurtenance through which measured quantity of alum is added to the water supply system before sedimentation of water.
9|Page
m2 =1457.7 m2.
Providing 2 nos of identical tanks Area of each tank Assume Thus, B =13.5 m and L = 54 m. Provide two tanks of size 54 m Provide a free board of 0.5 m Loading on the tank/overflow rate = = =18.66 m3/ m2/day 13.5 3.5 m (water depth) = m3 = 728 m3 L/B = 4 : 1 4B B = 728
(Which is within the prescribed range of 15 to 30 m3/ m2/day, OK) Hence, use two tank of size 54 m 13.5 m 4 m.
Provide extra depth for sludge storage. Provide longitudinal slope of 1 in 50. Also provide side slope of 1 in 30 towards the longitudinal central line.
, we get VS =
11 | P a g e
Reynoldss number =
SETTELEMENT VELOCITY (VS) BY THE METHOD DISCHARGE ENTERING THE TANK DIMENSIONS:PARAMETER ADOPTED:Discharge entering each basin Q = =850.35 m3/h =0.236 m3/sec Depth of water in the tank , Width of the tank, Length of the tank, Horizontal flow velocity V = H = 3.5 m B = 13.5 m L =54 m = =0.005 m/sec =0.3 m/min Settling velocity VS = = = 0.000324 m/sec =3.24 10-4 m/sec
OF
Thus, the particles having settling velocity greater than or equal to 3.24 10-4 m/sec shall settle in the tank of the dimensions assumed above.
12 | P a g e
Now, the horizontal velocity of flow is 0.005 m/sec and the length of tank is 54 m, the time taken by water to reach the outlet t 2= =1800 sec =3 hours > t1
Thus, the time required by water to flow from inlet to the outlet is more is more than the time required by the particle size 0.02 mm having a settling velocity greater than or equal to m /sec shall be retained in the sedimentation tank. Actual detention time in the sedimentation tank Tank size Discharge =54 13.5 3.5 =2551.5 m3 = 0.236 m3/sec =3.003 hours > 3 hours
Detention time =
)1/2
Since the horizontal flow velocity (v) of 0.005 m/sec the design is OK.
Capacity of chamber =flow required in 20 minutes =0.236 =283.2 m3 Width of chamber =13.5 m
Length of chamber = =10.48 m =10.5 m Thus, the chamber shall have the effective dimensions of 10.5 13.5 m 2 m
14 | P a g e
Provide a 0.6 m wide and 0.6 m deep influent channel than runs across the width of the tank. The design that follows provides overflow tank. The depth of flow over the weir on face over the weir on face discharge shall be :Q =1.65 B(H)3/2(For broad crested weirs) Where B = 13.5 m Q=* =0.048 m. Velocity of flow over the weir : Q =V A V = = =0.364 m/sec
2/3
OUTLET STRUCTURE:
The outlet structure shall consist of skimming weir plate, outlet box, outlet pipe and one overflow pipe to provide overflow when water to pass through the filter is reduced. The concrete weir on the outlet shall be 500 mm below the inlet weir crest. A skimming weir consisting of 8 mm thick and 10 mm depth steel plate with 900 v notches having depth of 5 cm is provided along the total width of the tank.
15 | P a g e
There are four outlet pipes of 300 mm dia. In each tank which take the water to the filter tank. One overflow pipe of 300 mm dia. has been provided on the side of the outlet box to prevent surplus water from flowing towards the filter.
Design :
Filtered water required = 40 MLD =1666.7 m3
Design flow for filter after accounting for back wash water (3 %) And washing time (30 minutes) = = 1753.19 m3 Plan area of filter required = =324.66 m2
Generally, the plan area of the filter unit is kept as 10 m2 to 80 m2 Provide six filter units each of 75 m2 Each filter bed size = 10 m 7.5 m
16 | P a g e
h =Terminal head loss in meters =2.25 m L=Depth of bed in mm. Assume B =4 10-4 per poor response to filtration and average degree of pre treatment.
=> L = 0.45
= 4 10-4 29323
17 | P a g e
18 | P a g e
= 6750 cm2 Area of central manifold = 2 area of laterals = 2 6750 =13500 cm2 Diameter of central manifold =( =131.1 cm Providing a commercially available diameter of 1500 mm Assuming a spacing 15 cm for laterals .No of laterals on both sides of manifold = =133.33 say 134 Cross-sectional area of each lateral = Diameter of lateral =( = 8 cm Provide laterals of diameter 100 mm. No of perforation per lateral = Length of lateral [ = [7.5 1.5] = 3.0 m
19 | P a g e
)1/2
=35.37 say 36 ]
Spacing of perforations =
=15 cm
CHECK:
=
= 30 [Which is less than 60] Now, let us assume that the rate of washing of filter be 45 cm/min. Or 0.45 m/min. The wash water discharge = Velocity of flow for wash water = = 0.5625 m3/sec
=0.5345 m/sec Similarly, velocity of flow in manifold = = = 0.32 m/sec This is less than 1.8 m/sec [Maximum permissible]
20 | P a g e
For a width of 0.4 m, the water depth in the trough is given as: Q = 1.376by3/2 =>0.15 = 1.376 0.4 y3/2 => y = 0.42 m. Assuming a free board 0.08 m ,provide a depth of 0.5 m provide 5 troughs of 0.4 m width 0.5 m depth in each bottom of troughs from filter sand bed is 0.05 m computation of total depth of filter box = sum of depths for drains,(2)Gravel(3)sand(4)water depth(5)free board =1.5+0.3+0.6+1.2+0.5 = 4.3 m
(1)Under
21 | P a g e
Assuming that the filter shall be washed in 15 minutes, the size of the tank required for wash water shall be =625 60 15 =562500 say 6 lakh litres. At 20 m head difference from the filter. The pump is designed to fill the wash water tank in 3 hours The rate of pump outlet shall be = =55.55 L/sec =0.055 m3/sec Water power required = wQH = 9.81 0.055 20 = 10.79KW Brake horse power required = = 18.35 HP say 20 HP
22 | P a g e
=> d = 0.187 m. say 200 mm. The actual velocity in the rising main = =1.75 m/sec
Hence, a pipe of dia shall be used as rising main. Let D be the dia of pipe to supply wash water to filter on 2m/sec velocity Q= D2 2 D2 2
625 10-3 =
D = O.63: say 650 mm. Thus, the rising main shall have a dia of 200 mm. And the pipe to wash the filter shall have the dia of 650 mm.
23 | P a g e
Assuming depth of water in the tank = 3.5 m Area of tank required = = 685.7 m2 20 m 3.5 m (water depth)
Hence, provide a rectangular tank of 35 m Provide a free board of 0.5 m Overall tank size = 35 m 20 m 4m
DESIGN OF CHLORINATOR:
Four polyethylene tanks each of 3000 L capacity shall be installed to mix clear water with the requisite amount of bleaching powder which water will flow by gravity into clear water tank to have contact period of more than hour as to cause disinfection. Quantity of bleaching powder is worked out as followos: Normal dose of chlorine to be taken =0.3 PPM for contact period of 30 minutes Average daily demand of water of the year 2041 = 40 MLD Chlorine require per day = =12 kg
Since chlorine content in bleaching powder is 30 % .it means that 30 Kg of chlorine is contained in 100 kg of bleaching powder Bleaching powder required per day = =40 kg
24 | P a g e
We get plan area of =2 40 20=1600 m2 (OK) A free board of 0.5 m is also provided. Hence, provide two covered tank of 40 m 20 m 3.5 m size of 8 hour detention period.
25 | P a g e