Академический Документы
Профессиональный Документы
Культура Документы
r
, shall be used to select the proper emergency load-current-carrying capability factor
from Table 1-1. Unless rated otherwise by the manufacturer, contacts and conducting
joints in other than oil or air are assumed to have the temperature limitations of silver,
silver alloy, or equivalent materials in air (65C hottest-spot temperature rise, 105C
hottest-spot total temperature).
The four-hour factor shall be used for a cycle of operation consisting of separate periods
of no longer than 4 hours each, with no more than four such occurrences before
maintenance.
The eight-hour factor shall be used for a cycle of operation consisting of separate periods
of no longer than 8 hours each, with no more than two such occurrences before
maintenance.
Each cycle of operation is separate, and no time-current integration is permissible to
increase the number of periods within a given cycle. However, any combination of
separate four-hour and eight-hour emergency periods may be used, but when they total 16
hours, the circuit breaker shall be inspected and maintained before being subjected to
additional emergency cycles.
Emergency Operation at an Ambient Temperature Other Than 40C
When a circuit breaker is operating at an ambient temperature other than 40C, the emergency
load-current-carrying capability I
ea
can be calculated by the equation:
8 . 1
1
8 . 1
r
e
8 . 1
r
a
r ea
1
I
I
I
I
I I
1
1
]
1
,
_
,
_
(1-1)
where,
I
ea
= emergency load current in amperes at actual at actual ambient temperature.
I
r
= rated continuous current amperes.
I
e
= emergency load current in amperes at 40C ambient temperature.
,
_
r
a
I
I
=
8 . 1
1
max
,
_
r
a
(1-2)
where,
max
= allowable hottest spot total temperature.
a
= actual ambient temperature.
1-13
r
= allowable hottest spot temperature rise at rated current .
The ratio of (Iea/Ia) shall not exceed the value of 2.0.
Table 1-1
Emergency Load Current-Carrying Capability Factors (Ie/Ir) (Based on an Ambient Temperature of
40 C)
Emergency
Period
Limiting Temperatures (C) of Different Breaker Components
max
70 80 85 90 105 110 150
r
30 40 45 50 65 70 110
Four- Hour
1.25 1.19 1.17 1.15 1.12 1.11 1.08
Eight Hour
1.17 1.13 1.11 1.10 1.08 1.07 1.05
The guidance provided in ANSI/IEEE C37.010-1979 should be programmed within the PQPM
system if no specific data regarding the emergency load-current-carrying capability of the circuit
breaker is available. In order to verify that the circuit breakers ability to handle emergency load
currents at ambient temperature other than 40
o
C, the power quality monitor should also be able
to log the ambient temperature and send that data to the PQPM system. In addition to the
algorithms for generating flag conditions, the PQPM system should also have the following
information:
Rated continuous current of the circuit breaker I
r.
Limiting hottest-spot temperature rise (
r
) and hottest-spot total temperature (
max
) of
different breaker components.
Algorithms for PQPM Flag Generation
Flag when the emergency load-current magnitude exceeds the recommended capability
based on ANSI/IEEE C37.010b-1985 as outlined in the previous section.
Flag when the duration of the emergency load current exceeds the four-hour or eight-hour
factors as described in the previous section.
Generate maintenance alarms after four occurrences of four-hour operations under
emergency loading or two occurrences of eight-hour operations.
Generate maintenance flags for any combination of four-hour and eight-hour emergency
periods when their total reaches 16 hours.
Reclosers
Functionally, a recloser is similar to a circuit breaker. Some of the maintenance issues addressed
for circuit breakers also apply to reclosers. The objective of this section is to assess the potential
for using power quality monitoring data for predictive maintenance for reclosers. The basic
functionality of reclosers will be reviewed, existing maintenance practices will be assessed, and
the feasibility of a PQPM system for reclosers will be evaluated.
1-14
Most of the faults on overhead distribution lines are temporary in nature. These include
lightning, conductor slap, animal contact, and tree contact. The repeater fuse, a concept that has
been used in the past, is based on a premise of temporary faults. Under such an arrangement, if a
fuse is blown, then a second and, if necessary, third fuse are automatically inserted into the
circuit. The success of this scheme led to the development of automatic circuit reclosers. These
are self-controlled interrupting devices that sense fault currents and step through a predetermined
sequence of opening and reclosing operations, followed by resetting, hold-closed, or lockout.
Typical recloser specifications include:
Voltage rating.
Continuous current rating.
Interrupting current rating.
Minimum tripping current.
Operating or time-current characteristics.
Operating sequence.
Reclosing interval.
Reset time.
Reclosers are manufactured in single-phase and in three-phase units with mechanical or
electronic control with an interrupting medium of vacuum or oil.
Existing Maintenance Practices for Reclosers
ANSI C37.61-1973, IEEE Standard Guide for the Application, Operation, and Maintenance of
Automatic Circuit Reclosers, outlines the maintenance issues that are related to reclosers. In the
absence of manufacturer-specific instructions, a suggested method is to conduct maintenance and
internal inspection at every 100 operations or every three years, whichever occurs first. However,
operating experience with particular designs is the best basis for the establishment of
maintenance schedules. Typical inspection procedures include:
Reviewing the overall condition of reclosers by examining insulators, surge arrestors,
mounting hardware, brackets, clamps, and ground connection.
Recording the number of operations.
Checking connections for signs or corrosion or overheating.
Manually opening and closing the recloser to check operation if equipped with by-passes.
Maintenance of lower-voltage reclosers can involve the removal of existing units and replacing
them with overhauled units. Maintenance of regulators involves:
Replacing oil (for oil reclosers).
Cleaning or replacing bushings and gaskets.
Checking the timing sequence of curves and the number of lockouts.
Inspecting internal components, arc interrupters, and contacts.
If the reclosers are electronically operated, the power supply and battery are tested too.
1-15
Application of Duty Factor for Determining Maintenance Basis
The standard operating duty of an oil-filled recloser is based on the empirical formula: Operating
duty = (Interrupted current)
1.5
x (Number of operations). The duty factor for each of the recloser
ratings is shown in Table 2 of ANSI C37.60a-1971 and can be calculated by using the above
formula. The duty factor can be used to determine the maintenance schedule based on the
number of operations and the interrupting current. For example, let us consider a 4000-A
interrupting rating recloser with a duty factor 555.6 x 10
4
. If all the faults are at 75 percent of the
maximum interrupting rate, then the duty cycle per operation is (0.75 x 4000)
1.5
= 16.4 x 10
4
.
The permissible number of operations = 34
10 4 . 16
10 6 . 555 Re
4
4
n erOperatio DutyCycleP
Factor closerDuty
If other fault currents have occurred, the accumulated effect, or the sum of all operations, can be
compared with the duty cycle of the recloser to determine the maintenance schedule.
Application of a PQPM System for Reclosers
In order for data from a power quality monitoring system to be applied for predictive
maintenance for reclosers, the placement of the power quality monitors is of critical importance.
Figure 1-2 shows a one-line diagram of two feeders from substations with possible recloser
locations. If a power quality monitor is installed downstream of the recloser and the monitor can
capture the full fault current, then the duty factor approach that is described in the previous
section can be used to determine the maintenance basis. However, cost for installing power
quality monitors for each recloser may be more than the cost of the recloser itself and will not be
an effective strategy for applying power quality monitoring for the sole purpose of predictive
maintenance. If a power quality monitor is installed downstream of a recloser for other reasons,
then incorporating the algorithms that are described in the previous circuit-breaker section along
with the duty-cycle calculation procedure will allow the monitor data to be used for PQPM
application.
If the power quality monitor is installed at the feeder as shown in Figure 1-2, then a simple
algorithm is to count the number of faults originating downstream of the monitor and assume
that each fault resulted in a recloser operation and that the operations are equally divided among
the number of downstream regulators. This algorithm can provide an approximate count of
regulator operations, which can be used for the scheduling of maintenance.
1-16
CB
PQ
MONITOR
100 kvar
Fixed
Substation Secondary Bus
R
R
R
CB
100 kvar
Fixed
R
100 kvar
Fixed
Figure 1-2
Recloser Location on Distribution Feeders
A number of recloser manufacturers provide optional control and communication packages that
have built-in data-acquisition capability that is similar to a power quality monitor. Data from
these controllers can be interfaced with a utilitys SCADA systems. Historical analysis of this
data can provide intelligent scheduling of recloser maintenance. One such system is the SEL-
351R recloser control that has built-in intelligent recloser maintenance scheduling.
The recloser wear-monitor algorithm of SEL 351R measures the line current at the time of the
trip and the number of close-to-open operations as a means of monitoring recloser wear. Every
time the recloser trips, the relay records the magnitude of the raw current in each phase. This
current information is integrated on a per-phase basis. When the result of the integration exceeds
a threshold, an alarm can be initiated. The set points for the threshold are based on the
recommendations for reclosers in ANSI C37.61-1973 or can be user-defined. Only the recloser
type (oil or vacuum) and the interrupt rating are required for the evaluation.
1-17
References
[1] J. Reason, Circuit Breakers with On-line Condition Monitoring, Electrical World,
February 1995.
[2] M. Ohlen, H. Wernli, and W. Dueck, Dynamic Resistance MeasurementsA Tool for
Circuit Breaker Diagnostics, in Proceedings of the IEEE/KTH Stockholm Power
Conference, Stockholm 1995.
[3] M. Runde et al, Vibration Analysis for Diagnostic Testing of Circuit Breakers, in
Proceedings of the 1996 IEEE Winter Meeting, Baltimore, 1996.
[4] W. Dueck, Interpretation of Circuit Breaker Operating Coil Signatures, in Proceedings of
the 1997 Programma Circuit Breaker Test & Maintenance Conference, Pittsburgh, 1997.
[5] P. Hadorn et al, Reasons for Continuous Circuit Breaker Time Monitoring and Proposal for
a Simple Realization, in Proceedings of the IEEE/KTH Stockholm Power Conference,
Stockholm, 1995.
[6] R. Burnett, SFA Timing Test Results, in Proceedings of the Programma TM1600 User
Group Meeting, Chicago, 1994.
[7] G. Johansson, On-Line Measurements on Circuit Breakers, Private Correspondence, 1997.
About EPRI
EPRI creates science and technology
solutions for the global energy and energy
services industry. U.S. electric utilities
established the Electric Power Research
Institute in 1973 as a nonprofit research
consortium for the benefit of utility members,
their customers, and society. Now known
simply as EPRI, the company provides a wide
range of innovative products and services to
more than 1000 energy-related organizations
in 40 countries. EPRIs multidisciplinary team
of scientists and engineers draws on a
worldwide network of technical and business
expertise to help solve todays toughest
energy and environmental problems.
EPRI. Powering Progress
2000 Electric Power Research Institute (EPRI), Inc. All
rights reserved. Electric Power Research Institute and EPRI
are registered service marks of the Electric Power Research
Institute, Inc. EPRI. POWERING PROGRESS is a service
mark of the Electric Power Research Institute, Inc.
1000561
Printed on recycled paper in the United States
of America
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 askepri@epri.com www.epri.com