Академический Документы
Профессиональный Документы
Культура Документы
EMD-SOP-0007 Document no. IR Revision Title 11th Aug 2011 Date of Issuance 1 of 6 Page HSEQ Dept. CCPP Issuing Department
Authorization: Name Prepared by: Reviewed by: Approved by: M. Laiq Ahmed Nowshad Alam Shabber Imam Rizvi Designation DM Electrical GM Maintenance Director CCPP Signature
Distribution list: 1. 2. 3. 4. 5. 6. 7. 8. Director, 220 MW CCPP GM Maintenance, 220 MW CCPP DGM Operation, 220 MW CCPP DGM HSEQ, Performance & Planning DGM Maintenance Mechanical DGM E&I DM Electrical Manager I&C
Edition
Version no.
Page Amended
Issue Date
Effective Date
TABLE OF CONTENTS:
3 3 3 3 3
5.2)
5.3) 5.4) 6.0)
INTRODUCTION ROUTINE TESTING AND INSPECTION BELOW GROUND ROUTINE TESTING AND INSPECTION ABOVE GROUND
RESULT OF TEST RELATED DOCUMENTS
3 4
5 6 6
(1.0) PURPOSE:
This document lays out the procedure for effective testing and maintenance of Power Station Main Earthing System (MES).
(2.0) SCOPE:
This applies to Earthing System installed at 220MW CCPP, KESC Station.
(3.0) REFERENCES/DEFINITIONS:
1) MET-110701-ER-EP-DW-00-096_1-B (Earthing System Plant Area) 2) MET-110701-ER-EP-DW-00-096_2-B (Earthing System Fuel Tank Area) 3) MET-110701-ER-EP-DW-02-099-B (Earthing System of RO, FGC and GRS)
(4.0) RESPONSIBILITIES:
It is the responsibility of Electrical Section Manager to ensure that the Earthing System is tested and maintained in accordance with this procedure.
When electrical fault occurs, the failure of the earth system can result in damage of catastrophic proportions. Planned routine maintenance, detailed inspection and recording of results can ensure the safe operation of the earthing system at the Power Station site. Therefore, a system of routine electrical testing and some visual inspection is necessary to achieve continued reliable performance.
(5.2) Routine Testing and Inspection of Below Ground Earthing (5.2.1) Inspection
The accessibility to earthing electrodes and the associated connections varies from station to station and also within station. Electrodes pits/mesh often has been buried. It is important that accurate records and drawings of all electrode pits/mesh should be available in station documentation system. The location of buried or built over pits is often undeterminable, the only indication to their existence being the conductor from the electrode to the earthing system as it enters the station buildings at basement, subbasement or cable tunnel level. These electrode mesh/pits are examined for the condition of the conductor connections to the electrodes, corrosion of fixings/fastenings, and the general condition of the civil work and covers. The most common form of deterioration takes place at the joint between the copper conductor and the steel pile or cast iron pipe, where corrosion increases the joint resistance. These joints should be protected by the application of a proprietary anti corrosion system. The visual inspection of these pits and joint resistance measurement is being done at a regular frequency of one year.
(5.2.2) Testing
The grounding system shall be tested at intervals of not more than one year.
conductor from the electrode joins the MES, if this point is accessible. b) The individual electrodes should be tested by comparison. The test procedure should use a low resistance Ohmmeter. Individual electrode resistances should be less than 10 ohms. c) When testing, only one group of rods or a plate should be isolated at a time, such that the remaining electrodes are capable of discharging the prevailing earth fault current. d) Disconnection and testing should not be undertaken at times of lightning risk. e) Prior to disconnecting an electrode, a check is to be carried out to confirm that the system terminating at the point is fully interconnected to other adjacent earth electrodes via the MES. f) If any doubt about connection to the MES exists, the MES side of the termination point should be connected to the MES with temporary conductors of a cross section equivalent to the termination conductor. g) Following the tests, the bolted link connections should be cleaned, remade and checked for continuity. h) Results of the tests will be recorded on the sheets as shown in attachment #1.
3) Link connections between various sections of the MES. 4) Main earthing conductor runs. 5) Transformer neutral connections to the MES. 6) Alternator earthing systems including associated earthing resistors/transformers and the connections of the latter items to the MES. 7) The connections between - switchboard earth conductors, alternator casings, phase isolated bus bar casings, steel support structures for outdoor high voltage overhead conductors, station structural steelwork and the MES. 8) Connections from lightning protection to the MES. 9) Connections between fuel oil storage tanks and driven rod electrodes. 10) Earthing connections and systems associated with flammable gas storage compounds. 11) In addition to the above, portable earthing leads