Вы находитесь на странице: 1из 10

Paper accepted for presentation at 2003 IEEE Bologna PowerTech Conference, June :!

3-26, Bologna, Italy

PROVISION OF FINANCIAL
TRANSMISSION RIGHTS
T. Kristiansen'

lines or facilities) the IS0 can run into financial credit risks.
Abstract-This paper studies the credit risks faced by the On the other hand a private party does not have to perfom
providers of financial transmission rights (FTRs). The this calculation [I]. As long as, it can cover its expenses in the
introduction o f FTRs in different systems in the USA must be long run,it can undertake the risk of overselling FTRs. An
viewed in relationship to the organization o f the m a r k e t Often,
private players own the central grid, while an independent
element not taken into account in the calculation is the FTR
system operator (ISO) operates the grid. The revenues from prices. Higher FTR prices will allow the provider to take on
transmission congestion collected in the day-ahead and balancing higher risks of overselling. If the party is a generator it may
markets should give the IS0 sufficient revenues to cover the costs have the ability to sell the largest volume of FTRs, since it can
associated with providing FTRs. This can be ensured if the issued affect the generation output anNj thereby the local spot prices.
FTRs fulfill the simultaneous feasibility test described by Hogan.
W e study this test on a three-node network under different
11. FPJANCIALTI(IWSMlSSI0N RIGHTS
assumptions and find the maximum volumes which can be sold,
including contingency constraints. Next w e analyze the feasibility An FTR [2],[3] entitles its owner to be paid the price
test when taking into account the FTR prices, and demonstrate difference between two locati,ms (buses). This payment will
that a higher volume might be issued. W e introduce uncertainty net out any price risk associated with using that path (i.e.
under different scenarios for locational prices and calculate the
paying congestion fees). Such payments will be made to the
maximum provided volumes. As a tool for risk management the
provider of the FTRs can use the Value at Risk approach. Finally owner of the right regardless of the owner's actual usage of
w e discuss provision of FTRs by private parties. the transmission system. The payments under this right are
therefore independent of the wmer's physical use of the grid.
Inder Tern-Financial transmission rights, risk Even if the congestion risk is hedged, traders will still be
management, transmission congestion exposed to locational price signals and should still be able to
make efficient choices for production and consumption. The
I. INTRODUCTION mathematical formulation for the pay-off for the FTR is:
Transmission rights are needed to hedge long-distance
forward trading. If they are well designed, they will minimize FTR =(A, -2.J P,_C_ZO (1)
forward-trading risks. If no such instruments are available 4
where is the bus price at location j, A is the bus price at
trading will be inhibited. An optimal schedule may result in location i and P, is the directed quantity specified in the FTR
loads that are located far from generators and create from point i to point j. The payoff of the FTR is only
counterflows between loads and generators that are netted out dependent on the bus prices, not on the power flow, and it
before the actual schedule. Using fmancial transmission rights may be positive, zero or negalive. An FTR may be acquired
means that transmission costs will net out and every generator by purchasing it in auctions and in secondary markets or by
and load will pay and be paid as if it had traded locally. investing in transmission lines. The auction market clearing-
Financial arrangements will therefore reflect the physical price of an obligation from A lo B is equal to the negative of
properties of electricity. the clearing-price of an obligation kom B to A.
An independent system operator (BO) can provide Locational prices are required before an FTR can be
fmancial transmission rights (FTRs) as long as the payments defined. These should depend on congestion and perhaps
to the rights holders are less than or equal to the revenues the losses. Locational prices will change during the specified time
IS0 receives from transmission congestion (in the day-ahead interval, so the value of the lotal payment is calculated by
and balancing markets) and sales of FTRs. To calculate averaging a series of fluctuating locational bus prices.
whether the volume of issued FTRs is feasible, a model Typically FTRs are long-term 'contracts that are settled in the
network is used that is supposed to represent the actual day-ahead market.
network. If the network is an inaccurate description or there An FTR will accrue negative payment if the contract !mns
are unexpected contingencies or outages (of transmission out to cover a path for which the price at the supply bus is
higher than the price at the demand bus, This can occur
either because the acquired FTI< is the right to transmit a flow
'T. Kristiansen is with the Department of Elec@iical Power Engineerin&
Norwegian University of Science and Technology, N-7491 Trondheim
opposite to the prevailing direction, or because power on the
Noway (email tarjci@elkr&.nhu.nO). route flows from a high to a low price location. The fust

0-7803-7967-5/03/$17.0002003 IEEE
situation is a highly desirable from a transmission standpoint, FTRs. The set of financial options that ensures revenue
while the second is one that can exist in a meshed network. In sufficiency must therefore be smaller than the feasible set of
either case, if the traders' FTRs more than cover their FTRs.
transmission needs during slack periods, they may suffer an For FTR obligations, options or a combination of both, the
unpredictable fmancial penalty for owning the unused part of SFT ensures that the flows in the transmission network satisfy
their right. all system constraints K ( ~ )(in the example below, the
FTRs can be designated as one-way options in which case transmission capacity limits):
the holder is not responsible for negative payments. The
mathematical formulation is:
K,(y,) SC,, 1il,] i N (3)
FTR-option =m m ((A, -2.J P, ,0) (2) where y , is the net load at the bus i and N is the number of
buses. In a DC load flow approximation,qy) can be linearized
Payments from an option are non-negative, and will have
value of (i.e. have a higher clearing price) at least the FTR to K ( ~ )K [ ~ ' ) + V K [ ~ * ) ( ~ where
Ij: - ~ ' ) y* is an operating point
obligations. and K ( ~ ' equals
) the matrix of shift factors' H. The matrix H
If the objective is to fully and efficiently utilize the includes negative contributions due to counterflows. It is
network, schedules that create counterflows are necessary assumed that y' = ~b') = HY' = o resulting in ~ b= ) HY.
because they relieve congestion. In the presence of Furthermore (Q;] is the set of FTR obligations and (Q;) is
counterflows, options issued by the I S 0 will not allow full
hedging. For a more thorough introduction to the FTR concept the set of FTR options. For options only positive congestion
refer to [2] and [3]. payments are made by the system operator. The SFT in the
case of obligations is satisfied if and only if:
111. RIE SIMULTANEOUS FEASIBILITY TEST(SFT)
In general the I S 0 can issue more obligations than options
if all FTRs are defined as options. The reason is that
obligations will allow the IS0 to assume that counterflows
will either be provided by the FTR holders or the holders will where the summation is across all obligations ( F ) issued
pay the I S 0 for the negative value of the right. By using between the buses in the network that contribute with a flow
options the I S 0 cannot assume that counterflows will be over the specified transmission line ij. HI,,,,,, is the fraction of a
provided, nor will it receive any payments from the rights transaction from bus m to bus n that flows over a transmission
holder. For these reasons parties should be willing to pay line connecting bus i and busj. The maximum volume (g) of
more for options than obligations. Ideally both options and possible issued options in the case of a DC load flow
obligations could be provided by the IS0 and the market approximation is determined by:
could sort out the mix of rights it found to be most useful,
0
given the market transactions each party wished to pursue. CmaW(O,Hg,Q~SnCq) IS 1 , ) S N (5)
Typically, a system operator would provide FTRs through M

an initial auction held periodically, or by an initial allocation.


The auction price of an FTR obligation should equal the where the summation is across all options (0)issued between
expected future congestion price. After the initial allocation, the buses in the network that contribute with a flow over the
the ETRs could be traded through secondary markets. specified transmission line ij. The interpretation of the above
An important consideration in defining FTRs is that they equation is that counterflows from options must be ignored
fulfill the feasibility condition. If this is the case, revenue (i.e. negative shift factors) and only options with the same
sufficiency is ensured and the congestion rent is sufficient to direction along the constraint are considered.
cover the payments to the holders of FTRs. The feasible set of A combination of obligations and options satisfies the SFT
FTRs is any set of FTRs that corresponds to a feasible power when:
flow. A feasible power flow is one that does not violate any
line's power-transmission limit. Other sets are infeasible. The
set of FTRs to be issued is often restricted to be any feasible
set. Restricting FTRs by restricting the sum of the
corresponding power flows automatically accounts for ensuring sufficient payments to the system operator. The SFT
counterflows, so trade will not be restricted because of is guaranteed by the convexity of the solution set.
physical limitations. If a full set of FTRs is to be issued, then To cany out an SFT we run an optimal power flow model
traders are allowed to purchase any feasible set of FTRs. without economic dispatch and check that no limits are
Traders often prefer FTRs that cannot have negative violated. An FTR between two locations is described as a
values, such as options. Options make revenue sufficiency
impossible to guarantee without severely restricting the sale of 'Also called power transfer distribution factors (PTDFs)
vector:
Then the objective becomes:
fTR,, =Q;(O,....,-1 ,,...., I ,,..., 0)' (7)

where is the amount of energy specified in the FTR. An


FTR is then viewed as an injection of power at bus i of Q;: and s.t.

a withdrawal of Q; at busj. y, =<q,?-$)=-Cq,


i = l , ..., N - I

zqg
,'i
FTRs between different buses in a three-node network can
/ = 1, ...,K - N + I
be allocated according to the generic transaction scheme
shown in Table I. x

Table I &: - d )= 0
1=1

GENERIC TRANSACTION SCHEME DESCRIBING FTRS qu<C, lii, j < N


p,'(q,")=ps itz,, /=1, ..., L

PP (4: 1= P., (13)

The objective function in the model (8) is the total social


welfare equal to the sum of consumer surplus and generator
profits. Equation (9) represents Kirchhoff s junction rules
constituting N-1 independent equations. Equation (10)
represents Krchhoffs loop rules with L =(L,,...,L~.~+,)being
To illustrate, we assume an FTR of 10 units between buses 1-
2. This FTR would have an injection component of 10 at bus 1 the set of independent loops, :md L, being the set of directed
and a withdrawal component of I O at bus 2. Another FTR of arcs in a path going through loop I. Equation (11) describes
15 units between buses 1-3 would similarly have 15 units of the energy conservation. Equi:ion (12) describes the capacity
injection and withdrawal. The total amount of injection would limits. Equation (13) calculates the bus prices. Alternatively
then be 25 units of injection at bus 1,lO units of withdrawal at they can be found as the shadow prices of the Kircbhoffs
bus 2, and 15 units of withdrawal at bus 3. The total amount junction rules. In every bus (node) there are production and
of injected power is 45 units equal to the total amount consumption facilities.
withdrawn, 45 units. The amount of issued FTRs is feasible if The real power flows !?om the buses will depend on the net
no power flow limits are violated. supply at the bus. The decision variables in the model are the
quantities produced and consumed and the nodal prices. The
IV. OPTIMAL POWER FLOW MODEL variables are coupled through the supply and demand
functions. The model can be wed to perform the SFT. In this
We base our analysis on a lossless and linear DC model
case supply and demand is inelastic and the model calculates
with all interface-reactances equal to 1 as described in [4].
the associated power flows. The network considered is shown
The model is a DC-equivalent where the network is described in Fig. 1.
as an AC grid with a DC-like approximation. The model does
The benefit and cost functions are assumed to be quadratic,
not account for losses. The mathematical formulation is: implying linear demand and supply. Demand in bus i is given
p i = ai - b,q, where p is the price in the actual bus and a and b
N the number of buses,
are positive constants. Supply i;sgiven by p i = c,qi where c is a
K: the number of transmission lines, positive constant. We assume identical demand functions at
L: the number of zones,
every bus, and varying cost fun,:tions as shown in Table 11.
the capacity of the transmission line from i toj ,

mTl
C,:
the set of directed arcs in a path going through the Table I1
L,:
independent loop 1 representing Kirchhoff s loop PARAMETERS FOR THE SWP1.Y AND DEMAND FUNCTIONS
rule,
Consum tion
q," : the quantity of real power consumed at bus i,
q; : the quantity of real power produced at bus i,
20 0.05 0.2
y, : the net load at bus i, 20 0.05 0.3
p ; ( q ; ) : the demand function ofbus i,
p;(q;) : the supply function of bus i, Fig. 1 and Fig. 2 show the uncongested case and the congested
qv: the power flow over the line from i to j , case respectively. Maximum transmission capacity over
pz, : the price in zone Z,. interface 1-2 is 15 when transmission congestion is present.
The other interfaces have transmission limits equal to 100.
Because every interface consists of two lines, the capacity of of withdrawals ( 4 ; ) and injections ( 9; ) times the nodal price
each line is half of the total capacity. The reactance of each
at the bus (A),The congestion rent (&) can be stated
line equals 2, resulting in total interface reactance of 1 (two
for the tbee-node nehvork with no losses as:
parallel lines).

2
?. = 15.32

where 48 is the power flow fiom bus i to bus j. The second


equality would not hold if there were losses.
A. FTR Obligations
The expected value of an FTR between bus i and bus j is
given by the expected future congestion price between the
buses. The maximum provided volume of one FTR is found
by assuming that the payment to the FTR holder equals the
congestion rent:

Fig. 1. Economic dispatch in an uncongested three-bus nehvork. Alternatively we can formulate the maximum volume of FTRs
between the buses i-j connected by a congested line k in a
2 three-bus network with identical reactance as:
A,= 15.93

where C, is the maximum transmission capacity of the line


between buses ij, and c , i s the maximum transmission
capacity of each of the other lines in the network connecting
buses other than i and j. The rule is determined by the matrix
of shift factors, which shows that 213 of the power in the three
node network flows kom the point of injection @us 1) to the
point of withdrawal (bus 2) as illustrated in Fig. 3 (see the
PI, = 28.35 appendix for how to calculate the shift factor matrix
elements). FTRs between the other buses m-n in the three-
node network (i.e. 1-3 and 2-3) will have a maximum issued
volume equal to:
Fig. 2. Economic dispatchwhen transmissioncongestion is present in a three-
bus network.

Security constraints take into account the post-contingency


flows that arise due to loss of lines or generators. The usual due to the shift factor 113. The simultaneous provision of
model is to use the criterion where the outage of one several FTRs modifies this rule so that the congestion rent
transmission line or one generator is considered.’ must be shared among several FTRs. The magnitude of the
congestion rent and the implied FTR power flows determine
V. NUMERICAL EXAMPLES the maximum volume of provided FTRs.
In the presence of losses and congestion, the revenues
collected under a locational pricing model would be greater
than the payments to participants. This net revenue is referred
to as the congestion rent. It is the difference between the sum

‘Including simultaneous outage of several lines andlor generators would


increase the computational burden.
4
2
Point of withdrawal I
22.5

L-
Poi Hma= 113, 45 1-3
H3nI = -1/3
Fig. 4. The feasible space of FTRs 1-z! and 1-3.

Similarly the maximum volumes of FTRs between buses I -


2 and buses 3-2 are:

Fig. 3. Some elements in the shift factor matrix,


We calculate the maximum volume of FTRs between and between buses 1-2 and bur.es 2-3:
different buses. First we consider when the IS0 issues FTRs
between buses 1-2 in the network as shown in Fig. 2. The
maximum volume of FTR is calculated as:
,
" ' - 5 G-e/,(&
4
-&)
(4-4)
= 2i:.5 +o,5QL,

QL =&=-C,, 3 =22.5 The formula shows that increasing the volume of FTRs
(4-4) 2 between buses 2-3 also increases the volume of FTRs between
buses 1-2, due to countertlows. The feasible space of FTRs is
A smaller volume gives the IS0 an excess revenue which illustrated in Fig. 5 .
could be redistributed according to a specified rule. However,
if the IS0 provides the same volume (22.5) in'the opposite
direction (6om 2 to l), the net directed power is 0 because the
power flows cancel. In this situation the IS0 can issue any
volume exceeding 22.5 as long as there is an equal volume in 45

the opposite direction.


Similarly we can calculate the maximum volume of FTRs
22.5
between buses 1-3 as:

45 2-3

Fig. 5. The feasible space of FTRs 1-2 and 2-3


Another possibility is a simultaneous issue of FTRs
between buses 1-2 and 1-3. The maximum volumes of FTRs B. Contingency Constraints
are described as:
Contingency constraints limit the volume of issued FTRs.
For example if we assume an outage of one line at the 1-2
4 )+e& - 4 = RC
~ 9-4 (18)
interface, the remaining capacity will be 7.5 units. The line
reactance for line 1-2 is 2, due to the outage. Line outages in
Atter rearranging the volume of FTRs between 1 and 2 this the other interfaces will not ba a problem because the other
gives: constraints do not bind. The shift factor matrix elements
change because of the new network topology. Examples are
H1212 =112and H,113 =1/4.
The congestion rent kom the economic dispatch in this
case will be 25.6, which is lower than when the line is in
The feasible space of FTRs is illustrated in Fig. 4. service (26 units). The corresponding economic dispatch is
shown in Fig. 6.
2
3
and solving for Q;? gives the maximum volume of options
between buses 1-2:

Q?: =22.5-0.5g,, Qi 145 (21)

Social surplus 2734.0


PIS= 13.14
Another possibility is to have options between buses 1-2 and
Congestion rent 25.6
2-3. The relevant constraints are:

-2Q ; ~ s I ~ and -Q;,


1 51s
3 3
I 3
Pu = 28. I4 since the options do not create any counterflows. The
maximum volumes for each option is:

Q; =22.5 and Q& =45


Fig. 6. Economic dispatch when transmission congestion and one
contingency are present in athree-bus network.
which is lower than in the case of obligations. Combinations
The constraint reduces the volume of FTR between buses 1-2 of obligations and options are also possible. For example an
so that the IS0 can issue to 15.0 or 33%. Similarly the obligation between buses 1-2 and an option between buses 2-3
maximum volumes of 1-2 and 1-3 FTRs utilizing the n-1 is represented by the constraints:
criterion are described as:
2
-QG i 15
3
1 2
-Q;,
3 -?QL 11s

which is more restrictive than without contingency. The maximum volume of provided 1-2 obligations is the same
Transpower New Zealand bas excluded transmission lines as before: 22.5 units. The maximum volume of2-3 options is:
with outages longer than 2 days in a 30-day period in its
network describing the SFT. The outage of the remaining lines
Q& =45+2Q(,_, = 4 5 + 2 . 2 2 . 5 = 9 0
describing the network is equivalent to 7% of the duration of
the FTRs. In our network example a conservative criterion is
that the outage of the 1-2 line is present only as long as the which is also lower than in the case with only obligations.
duration of the FTRs and hence the issued volume is 11.25. When we take the security constraints into account, we get the
Usually outages are present for shorter times, and an volumes for obligations and options as specified in Table 111.
optimistic upper bound is therefore 22.5 units. However, in Similarly we can specify some maximum volume
optimal power flow models the practice is to include security combinations of options and obligations in Table IV. The
constraints and run a security-constrained economic dispatch. results demonstrate that the volume of issued options is more
restrictive for some of the lines because they do not create
C. Financial TransmissionRight Options counterflows.
Provision of options will be more restrictive because they Table III
do not provide counterflows. Consider the case when the IS0
THE W M U M VOLUhE OF PROVIDED FTRS WHEN ONLY ONE
issues options between buses 1-2 then the maximum volume, FTR IS ISSUED
22.5 units, will be the same as for obligations. If the I S 0
issues options in opposite directions between the same buses (n-I) criterion
the maximum volume in each direction is still 22.5 units
compared with obligations where any volume could be issued.
The reason is that any possible exercise of options must be 2-3
taken into account, but only one option is exercised at a time 45 45
with an associated maximum volume of 22.5. Utilizing that
option does not result in counterflows in the specific example
we get (disregarding the constraints on lines 1-3and 2-3 since
they are not binding):
Table IV demonstrates that by taking into account the selling price it is
I Ill: MAXIMUM VOI.IIMI.'Ol~PKOVIDED FTKS WIIVH SI'VFKAL possible to issue a higher FTIl volume. This is demonstrated
FTRS AKI: I S S l ' I ~ I SIMULTANC0IJSI.Y
) for obligations between buses 1-2 and a selling price equal to
the half of the price differential as:

I- % = 26
-e45
'I2 - (4- 4 - P , ~ ) (1.15 -0.5 . I . 15)

This is an increase in volurne of 100% fiom 22.5 units.


Similarly, the maximum volumes of FTRs between buses 1-2
and 1-3 are described by:

Q L C -4
~ -P,,)+QL(~, -4-P,,)= & (25)

where Q' is the volume of FTRs. Afier rearranging the volume


of FTRs 1-2 as a function of FTRs between 1 and 3, and
assuming that the selling price is equal to the half of the price
differential between buses 1-2 this is:

= 45 -0.5Q!,
D. Expanding the Feasible Space of FTRs
Until now we have not taken into account the FTR prices
The expansion of the feasible space of FTRs is illustrated in
when calculating the maximum volume issued. When they are
Fig. 7. These examples show that a higher volume of FTRs
considered, the formulas for maximum volume must be
can be issued by taking into account the selling price.
modified since there will be additional revenue from the FTR
sales. The payments to the FTR holders must be less than or
equal to the congestion rent and the revenues 6om the FTR
auction. We assume that the revenues from the FTR auctions 1-2 t
are related to the period when the FTRs are settled. This holds
true for the auctions in the PJM market in the US. The general
relationship between the pay-off, the price and the maximum
45 I\
volume of a single FTR is described as:

Qi(2, -4 - P 1~= % (23)

where p is the price of the FTR. & is calculated fiom the bus
45 1-3
prices and their associated net demand in the optimal power
flow model. We fKst assume that the FTR prices are
Fig. 1. The feasible space of FTRs 1-2 and 1-3 taking into account the selling
independent of the FTR volume issued. Consider the case prices.
when (2,- 4 -P,,)> 0, This occurs when the FTR prices are
less than the price differential (i.e. the FTRs are under-priced). Next we assume that the FTR price is linearly dependent on
The greater (1,-4 -Pg) is, the smaller the maximum volume the volume issued
of FTRs, assuming everything else is equal. We intuit that the
= a-bQi (27)
relatively under-priced FTRs (the FTR price is small
compared to the price differential) cause the IS0 to issue a
smaller volume because it is responsible for payments (i.e. where a and b are parameters that characterize the demand of
price differentials) to FTR holders that are greater than the FTRs. Substituting for the FIX price and solving for Q,'
price for which they are sold. When the selling price equals gives:
the price differential, the maximum volume sold is undefined.
The reverse is true if (2,- 4 - Pn)< o the selling price is
greater than the price differential (i.e. the FTRs are over-
priced). The volume provided is then negative, meaning that
the I S 0 profits on the provision of the FTRs. The formula
Consider the special case A, -4= a . The maximum between buses 2-3 (because of a lower price differential) and
the lowest volume between buses 1-2 (a higher price
willingness to pay equals the price differential. Then Q: =$'I differential).
and more restrictive than when the price was considered to be An FTR provider facing uncertainty may use tools to
independent of the volume issued. measure the associated risks. One tool is the Value at Risk
The key issue of the revenue adequacy test is to ensure that (VaR) approach. VaR is an attempt to provide a single number
the implied power flows 6om an FTR do not exceed the for management summarizing the total risk in a portfolio of
transmission capacities. Due to the equivalence between this assets [SI. The objective ofthe approach is to give a fmancial
test and the formula for the feasible volume provided it might measure of the statement: "We are Ph certain that we will not
be possible to modify the feasible FTR volume formulation lose more than Vdollars in the next N days." The variable Vis
for obligations: the VaR of the portfolio. It is usual to assume a confidence
interval of 95%, and a time horizon of up to one week. The
(29) changes in the asset prices are assumed to have a multivariate
distribution3 and a mean of zero (at least approximately).
Mathematically a linear model for the change in the daily
where pm is the price of an FTR 6om zone rn to zone n . To value, AP, of a portfolio of N assets with an amount (or
use this feasibility test in practice we fust run the optimal kaction) x, invested in asset i and with a daily return of bris
power flow model to calculate RC and then use the value formulated as:
found in the above formula.
E. Uncertainty
Until now we have calculated the consequences of FTR
provision under deterministic conditions. Now we will
inaoduce uncertainty by using the scenarios in Table V, where Only the mean and standard deviation of AP is necessary to
we have calculated the expected spot price and the associated calculate the VaR. To calculate the standard deviation of AP,
volatility. Bus 3 experiences the highest expected value and we defme uj as the daily volatility of the ith asset and pq as
volatility. the correlation coefficient between the returns on the asset i
Table V andj. The standard deviation is given by:
THE EXPECTED BUS PRICES UNDER THREE SCENAKIOS

I Scenarios/ Bus2 I Bus3 1

The standard deviation of the change over N days is u,,fi


and the 95% VaR for an N-day time horizon is i . 6 5 . u P f i .

Table VI1

Table VI
THE MAXIMUM VOLUME OF FTRS WHEN ONLY ONE FTR IS ISSUED payment
UNDER THREE DIFFERENT SCENARIOS

C13 20% 1.08 2.16 1.08


Expected 0.56 0.61 0.04 -16.8
payment I I I I
Volatility I 0.56 I 0.82 I 0.57 I 18.0

Table VI1 shows the payments per unit to the FTR holders
and the total congestion rent under the different scenarios.
FTRs between buses 1-3 are particular volatile. The
Table VI shows the maximum volume of provided FTRs
when only one FTR is issued under three different scenarios. 'To facilitate calculations we ffisume n o d distributions. In reality the
When there is no congestion we assume a conservative spot prices are observed to have a complex distribution, while the remm on
criterion where there are active contingency constraints that forward prices is assumed to have a log-normal distribution. A new measure
is cumulative value at risk (CvaR)which is based on expectation of loss rather
make the maximum provided volume equal to the minimum of than the mobability of it. and which does not reauire that the distribution is
the congested case's volumes. The hiehest volume is issued
congestion rent is highly volatile and with an expected of 1-2 and 2-3 FTRs have high VaR. Conversely, the lowest
revenue of 16.8 to the ISO. In Table VI11 we calculated the losses (with congestion) are experienced when 25 units of 1-2
FTR provider's net position (excluding the congestion rent) and 2-3 FTRs are issued.
under the provision of FTRs of 22.5 units between each of the Table XI and Table XI1 :!how similar results when the
buses (one at a time) 1-2, 1-3, and 2-3. The provider has the selling prices are taken into account. However, because the
greatest risk exposure when it issues FTRs between 1-3 payments are lower due to thc sales revenue from the FTRs,
because the expected payments are highest in this case. The the VaR will be lower and so will the provider's risk position.
lowest payments are for FTRs between 2-3 due to If the selling price is equal to the expected price differential
counterflows that create a revenue to the provider in scenario the VaR will be zero. Its risk will completely offset by the
C13. revenue from selling FTRs.

Table Vlll Table XI

W]
THE PROVIDERS NET POSITIONS (LONG) UNDER THE PROVISION THE PROVIDERS'S NET POSITlOhS UNDER THE PROVISON OF FTRS
OF FTRS OF 22 5 UNITS BETWEM EACH OF THE BUSES 1-2.1-3 AND OF 22.5 UNITS BETWEEN EACH OF THE BlJSES 1-2.1-3 AND 2-3 ~~~~

2-3 ASSUMING SELLING PKICES EQUAL TO THE HALF OF THE PNCE


DIFFERENTIAL

of a ents

2-3 0.9 0.57 6.85 6.85 0.82


2-3 0.45 0.9 0.45 0.57
Table IX shows the correlation between the expected price
differential correlation matrix with congestion under the Table XI
different scenarios. The price differentials 1-2/2-3 exhibit low VAK ESTIMATE OF PAYMENTS AT 95% CONFIDENCE LEVEI. ~~~~ ~~

correlation, while the price differentials 1-24-3 and 1-3/2-3 ASSUMING SELLING PNCES EQUAL TO THE HALF OF THE PNCE
have a higher correlation. DIFFERENTIAL

Condition I VaR
Table IX Congestion with 1-2 (11.25 units) and 1-3 FTRs I 11.40

Correlation Congestion with 1-2 (25 units) and 2-3 FTRs (25
matrix
1.00 0.67 0.12 Congestion with 1-2 (45 units) and 2-3 FTRs (45
0.67 I .oo 0.82
units)
2-3 0.12 0.82 1.00 Congestion with 1-2, 1-3 and 2-3 I'TRs (22.5 units 14.10
each)
Table X

VAK CSI IMAI'I 01 PAYMliNrS A T PS%('OI\FIDFNCF I.tVt.1. VI. PROVIDERS OF FINANCIAL TRANSMISSION RIGHTS
C'KI)RR DIFFERENT SCEUAKIOS
When a private party provides FTRs, it does not have to
Condition I VaR fulfil the SFT. If the private party can buy insurance in the
Coneestion with 1-2 (11.25 units) and 1-3 FTRs I
~
22.81 market, it can over-sell FTRs compared to the IS0 that issues
(22.5 units)
FTRs satisfying the SFT. It ma:( also charge a higher price if it
Congestion with 1-2 (22.5 units) and 1-3 FTRs (22.5 I 21.69
is the only one providing FTRs. But the private party does not
receive any revenues from transmission congestion (i.e.
congestion rents), so it must at least price its FTRs to cover
the payments to the rights holdirs in the long run.
It is possible that third parties may be able to m the
market for hedging instruments at lower cost than the ISO.
They could offer FTRs, for example, due to specialisation and
Table X shows the VaR estimate of payments at 95% consequently greater expertisi: and/or economies of scale.
Such non-FTR instruments are a natural extension of the risk
confidence level under two different scenarios without taking
into account the selling prices. The results demonstrate that products of other industries and markets. A private party can
hedge itself in the BO'S day-ahead or real-time locational
the greatest potential losses are realized when 22.5 units of 1-
2, 1-3 and 2-3 FTRs are issued because the provider's price market. For example, a. generator in the position to
produce valuable counterflows can safely sell private point-to-
payments to FTR holders are relatively high. Also 22.5 units
point FTRs either as options or obligations up to its expected
generation capacity. These FTRs can be traded freely among
traders whether or not those traders plan to schedule precisely
the same point-to-point transactions, and they will have value
because they are fmncial instruments that can be used for
hedging. For real-time operations, the generator submits bids
:[=I:[ 2 -1

:l-;]
-1

E]
The matrix is called the susceptance matrix. The matrix is
for its generation to the ISO. When counterflows are valuable singular, but by declaring one of the buses to have a phase
so that the generator must pay out under the FTRs it provided, angle of zero and eliminating its row and column 60x11 the
the local spot prices will be high and the generator will make matrix, the reactance matrix can be obtained by inversion.
money in the real-time market. The traders holding the private The resulting equation then gives the bus angles as a function
issued FTRs will receive payments from the generator that of the bus injection:
will offset some or all of the congestion rents they must pay in
the spot market.

VII. CONCLUSIONS
This paper has demonstrated the key issues associated with The shift factor matrix element is the fraction of the amount of
provision of FTR obligations and options. In particular the a transaction from one zone to another that flows over a given
IS0 must conduct an analysis of revenue adequacy, because line. Hymnis the fraction of a transaction from zone m to zone
the maximum volume of FTRs (both obligations and options) n that flows over a transmission line connecting zone i and
will vary with the capacities and contingencies. In a three- zonej . The equation for the His:
node network the maximum volume associated with an issue
of a single FTR is determined by the shift factor matrix
elements and transmission line capacities. We also showed the
alternative relationship for the maximum volume, congestion
rent and locational prices. Due to counterflows a higher
volume of FTRs might be issued between certain buses. where xu is the reactance of the transmission line connecting
Conversely, a lower volume of options than obligations must zone i and zone j and ximis the entry in the I’* row and the mm
be issued because they do not create counterilows. We also column of the bus reactance matrix. For example we fmd the
took into account FTR prices and demonstrated that a higher following elements of H:
volume might be issued. Uncertainty associated with
congestion gave the IS0 an uncertain cash flow, composed of H12,2=213,H,,,, = 1 / 3 , H , , 2 , = - 1 1 3 ,
the congestion rent and payments to the FTR holders. As a H,,,, = 2 / 3 , H , , , , = - l / 3 , H , , , 2 = I 1 3
tool for risk management the provider could utilize the VaR
H,2,2 = 2 / 3 , H , , , , = - l / 3 , H 3 2 1 2= I 1 3
approach. The VaR shows that the greatest potential loss
occurs when FTRs with the highest expected payments are
issued and the lowest when FTRs with the lowest expected IX.REFERENCES
payments are issued. Private parties would not have to fulfil [I] L. E. Ruff, “Flowgates, Contingency-Constrsled Dispatch, and
TransmissionRights,” The Electricity Journal, JanuaryiFebnwq 2001.
the simultaneous feasibility test and might buy insurance in [2] W. W. Hogan, “Contract Networks far Electric Power Transmission,”
the market to hedge any risks associated with providing FTRs. JournalofReplatory Economics,421 1-242, 1992.
[31 W. W.Hogan, Homepage ofprofessor William W. Hogan, Kennedy
v111. fbPENDlX Schwl of Government, Harvard University, available:
wu?u.whogan.com/, 2002.
This appendix derives the shift factor matrix elements (or [4] M.Bjmdal and K. Jmsten, ‘Zonal Pricing in a Deregulated Electricity
Pn>Fs) for the three-node network with identical lines. The Market,” The Energv Journal, Vol. 22, No. I,2001.
net injection (or net generation) of power at each bus is given [5] I. C. Hull, Options ondDerrvalrves,Prentice Hall, 2000.
by P,. The following relationship between the net injection,
the power flows P, and phase angles 0, is:

where xy is the line inductive reactance in per unit


Furthermore, we can Write power flow equations as:

Вам также может понравиться