Peace Corps HSPD-12 Implementation Status Report

Updated Date: Number of Employees requiring PIV credentials* Number of Employees requiring a NACI (or at least equivalent) that have not previously undergone a background check* Number of Employees requiring a NACI (or at least equivalent) with background investigation in process* Number of Employees with completed/ adjudicated NACI (or equivalent background investigation) * Total Number of PIV credentials Issued to Employees * Number of Contractors requiring PIV credentials Number of Contractors requiring NACI (or at least equivalent) that have not previously undergone a background check Number of Contractors requiring a NACI (or at least equivalent) with background investigation in process Number of Contractors with completed/ adjudicated NACI (or equivalent background investigation) Total Number of PIV credentials Issued to Contractors Number of other individuals (e.g. guest researchers) requiring PIV credentials Number of other individuals (e.g. guest researchers) requiring NACI (or at least equivalent) that have not previously undergone a background check Number of other individuals requiring a NACI (or at least equivalent) with background investigation in process Number of other individuals with completed/ adjudicated NACI (or equivalent background investigation) Total Number of PIV credentials issued to individuals other than employees or contractors (e.g. guest researchers)

Mar/2007 Jun/2007 Sept/2007 Dec/2007 Mar/2008 Jun/2008 Sept/2008 Dec/2008 Mar/2009 Jun/2009 Sept/2009 Dec/2009 Mar/2010 Jun/2010 Sept/2010

901 751 575 345 281 244 162 100 0 297 203 111 192 214 231

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

N/A N/A N/A 105 110 107 41 113 61 57 77 24 41 30 23

N/A N/A N/A 798 793 796 862 787 763 914 927 784 801 539 550

2 152 328 558 622 659 741 803 844 674 657 752 701 701 709

217 207 206 206 156 133 130 130 55 16 0 0 10 9 10

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

N/A N/A N/A 25 25 19 11 15 7 23 30 9 5 11 14

N/A N/A N/A 192 192 198 206 194 172 62 67 45 32 42 45

0 10 11 11 61 84 87 87 89 69 65 61 57 57 57

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Updated Date:

Number of Employees requiring PIV credentials*

Number of Employees requiring a NACI (or at least equivalent) that have not previously undergone a background check*

Number of Employees requiring a NACI (or at least equivalent) with background investigation in process*

Number of Employees with completed/ adjudicated NACI (or equivalent background investigation) *

Total Number of PIV credentials Issued to Employees *

Number of Contractors requiring PIV credentials

Number of Contractors requiring NACI (or at least equivalent) that have not previously undergone a background check

Number of Contractors requiring a NACI (or at least equivalent) with background investigation in process

Number of Contractors with completed/ adjudicated NACI (or equivalent background investigation)

Total Number of PIV credentials Issued to Contractors

Number of other individuals (e.g. guest researchers) requiring PIV credentials

Number of other individuals (e.g. guest researchers) requiring NACI (or at least equivalent) that have not previously undergone a background check

Number of other individuals requiring a NACI (or at least equivalent) with background investigation in process

Number of other individuals with completed/ adjudicated NACI (or equivalent background investigation)

Total Number of PIV credentials issued to individuals other than employees or contractors (e.g. guest researchers)

Dec/2010 Mar/2010

225 464

0 0

48 30

899 940

692 506

37 37

0 0

26 0

68 94

57 57

0 0

0 0

0 0

0 0

0 0

Implementation Plan Summary Next Major Milestone:


Per the implementation plan, full implementation date is dependent upon implementation timetable developed by the Department of State All have been completed 04/30/2008 Pending availability of supplies, completion of issuance to all Headquarters staff. COMPLETED 4/30/2009 Completion of issuance to all Domestic staff who have come to the Headquarters building. COMPLETED