Академический Документы
Профессиональный Документы
Культура Документы
Integrated
Page 2
1 0.5 0 -0.5 -1 1 4 7 10 13 16 19 22 25
Page 3
Page 4
Distribution SCADA
IVVC Application
Line Regulator
Substation RTU
Page 5
Page 6
Page 7
The system is not continuously monitored The system lacks flexibility to respond to changing conditions out on the distribution feeders can misoperate following automatic reconfiguration System operation may not be optimal under all conditions Cannot override traditional operation during power system emergencies System may misoperate when modern grid devices (e.g., distributed generators) are present reverse power flow from DG can trick standalone controller to believe feeder has been reconfigured
Page 8
Traditional VAR X X
Volt-
Page 9
Operation of these systems is primarily based on a stored set of predetermined rules (e.g., if power factor is less than 0.95, then switch capacitor bank #1 off)
Page 10
Simplified formula for demand reduction due to power factor improvement at peak load:
Demand Reduction = (1 / PKPF 1 / TPF) x 100 Example: (1 / .97 1 / .99) = 2.08%
Page 11
Radio
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Switched & fixed feeder capacitor banks Capacitor bank control interface Communications facility - one-way paging or load management communications is sufficient Means of monitoring 3-phase var flow at the substation Master station running VAR dispatch software
Page 12
Radio
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Page 13
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Page 14
Radio
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Page 15
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Page 16
Capacitor Switched On
VAR Dispatch Processor Determines Additional Capacitors Needed
Radio
Substation RTU
Real Power (MW) Cap Bank Switched On Radio
Substation
OO
Reactive Power (MVAR)
Page 17
Radio
Substation RTU
Real Power (MW) Cap Bank Switched On Radio
Substation
OO
Reactive Power (MVAR) Reactive Power From Supplier Reduced
Page 18
Radio
Substation RTU
Real Power (MW) Cap Bank Switched On Radio
Substation
OO
Reactive Power (MVAR) Reactive Power From Supplier Reduced
Page 19
Radio
Substation RTU
Radio Real Power (MW)
Substation
OO
Reactive Power (MVAR)
Page 20
By reducing voltage at the time of the system peak load, you can reduce the peak and thereby achieve:
reduction in investments for new capacity, or reduction in demand charges for power purchases
Page 21
Page 22
Figure 1: Effect of voltage on motor loss At low loads, motor losses decrease as voltage decreases. Source: Westinghouse Electric Corp.
Page 23
Page 24
Comm Interface
Substation Transformer
LTC
Substation RTU O O O O
Ensures that voltage does not drop below minimum acceptable value Comm Interface
Current Transformer
OO
Real Power (MW) Reactive Power (MVAR)
Voltage OO TransformerOO
End of Feeder
Page 25
Comm Interface
LTC Controller
Substation Transformer
LTC
Substation RTU O O O O OO
Real Power (MW) Reactive Power (MVAR)
Comm Interface
Voltage OO TransformerOO
End of Feeder
Page 26
Comm Interface
LTC Controller
Substation Transformer
LTC
Substation RTU O O O O OO
Real Power (MW) Reactive Power (MVAR)
Comm Interface
Page 27
Comm Interface
Substation Transformer
LTC
Substation RTU O O O O OO
Real Power (MW) Reactive Power (MVAR)
Comm Interface
Page 28
Comm Interface
Substation Transformer
LTC
Substation RTU O O O O OO
Real Power (MW) Reactive Power (MVAR)
Comm Interface
Page 29
Page 30
Volt-VAR Approach
Volt VAR Requirements
Acceptable Voltage Profile Acceptable Power Factor Self Monitoring Operator Override Feeder Reconfiguration SmartGrid Devices Optimal Coordinated Control Selectable Operating Objectives
Traditional VAR X X Volt- SCADA VAR X X X X Volt-
Page 31
Can bias the results to minimize tap changer movement and other equipment control actions that put additional wear and tear on the physical equipment
Page 32
Page 33
Distribution SCADA
IVVC Application
IVVC Software Optimal powerflow solution versus rule-based approach Processor For Running IVVC Software Centralized master station Substation based processor
Substation RTU
Line Regulator
Interfaces to field devices Substation LTC transformers Substation and line regulators Substation and line capacitor banks Voltage monitors (optional) Communication facilities (2 way preferred)
Substation Transformer With Load Tap Changer
Page 34
Solution Technique
Power flow solution used by the optimization procedure to evaluate the effectiveness of the various possible control actions. Optimal IVVC solution utilizes an iterative process designed to reach the objective function within the defined constraints and limits. Selected optimization procedure results in the least number of control actions to achieve the optimum results.
Page 35
Distribution SCADA
IVVC Application
Feeder load, LTC tap position, bus voltage, cap bank status
Substation RTU
Line Regulator
Page 36
Powerflow results
Distribution SCADA
IVVC Application
Feeder load, LTC tap position, bus voltage, cap bank status
Substation RTU
Line Regulator
Page 37
Powerflow results
Opt switching plan for cap banks, LTC, and line regulators
Distribution SCADA
IVVC Application
Feeder load, LTC tap position, bus voltage, cap bank status
Substation RTU
Line Regulator
Page 38
Powerflow results
Opt switching plan for cap banks, LTC, and line regulators
Distribution SCADA
IVVC Application
Feeder load, LTC tap position, bus voltage, cap bank status
Substation RTU
Line Regulator
Page 39
IVVC Benefits
Dynamic model updates automatically when reconfiguration occurs Volt VAR control actions are coordinated System can model the effects of Distributed Generation and other modern grid elements Produces optimal results Accommodates varying operating objectives depending on current need
Page 40
Volt-VAR Approach
Volt VAR Requirements
Acceptable Voltage Profile Acceptable Power Factor Self Monitoring Operator Override Feeder Reconfiguration SmartGrid Devices Optimal Coordinated Control Selectable Operating Objectives
Traditional VAR X X Volt- SCADA VAR X X X X Volt- Integrated VAR X X X X X X X X Volt-
Page 41
Questions?
For further information: Bob Uluski Quanta Technology Ruluski@quanta-technology.com
Page 42